§ 24-8.1-3.1 "As built" plans required.


§ 24-8.1-3.1 "As built" plans required. – Each utility shall submit to the department of transportation a complete set of "as-built" plans, within sixty (60) days of the installation of new utility facilities, or within sixty (60) days of the relocation of existing utility facilities that affect state roads.
History of Section.
(P.L. 1999, ch. 378, § 1.)

Disclaimer: These codes may not be the most recent version. Rhode Island may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.