2015 North Dakota Century Code Title 61 Waters Chapter 61-35 Water Districts
Download as PDF
CHAPTER 61-35
WATER DISTRICTS
61-35-01. Definitions.
As used in this chapter:
1. "Auditor" means the county auditor.
2. "Benefit unit" means the fee each member pays, for each service that is planned to be
connected to the water system, for the privilege of using the district's facilities.
3. "Board" means the board of directors of a district.
4. "Bond" means any revenue bond, refunding bond, or improvement bond, or other
evidence of indebtedness of a district issued under this chapter.
5. "Director" means a member of the board of directors.
6. "District" means a water district organized under this chapter.
7. "Federal agency" includes the United States, the president of the United States, or any
agency, instrumentality, or corporation of the United States which has been or may be
designated or created by or pursuant to any act or acts or joint resolutions of the
Congress of the United States or which may be owned or controlled, directly or
indirectly, by the United States.
8. "Holder of bonds" or "bondholder", or any similar term, means any person who is the
registered owner of any outstanding revenue bond, improvement bond, or refunding
bonds.
9. "Law" means any statute of this state.
10. "Member" means an owner of real property that is located within a district, the tenant
of the real property, or another person acting for the owner with the owner's written
consent.
11. "Participating member" means a member who has subscribed to and paid the
established fee for at least one benefit unit in a district, in the manner provided by this
chapter.
12. "Project" means any work, undertaking, enterprise, or any combination of two or more
projects which a district is authorized to construct and from which the district has
derived or may derive revenues. "Project" includes all improvements, betterments,
extensions, and replacements of work, undertaking, or enterprises, and all
appurtenances, facilities, easements, lands, rights in land, water rights, contract rights,
approaches, dams, reservoirs, generating stations, sewage disposal plants,
intercepting sewers, trunk connections, other sewer and water mains, filtration works,
pumping stations, equipment, franchises, and structures in connection with or
incidental to any work, undertaking, or enterprise a district is authorized to construct.
13. "Refinancing" means funding, refunding, paying, or discharging, by means of refunding
bonds or the proceeds from the sale of refunding bonds, all or any part of any notes,
bonds, or other obligations issued to finance or to aid in financing the acquisition,
construction, or improvement of a project and payable solely from all or any part of the
revenue or interest on the revenue of the project in arrears or about to become due
whether or not such interest is represented by interest certificates.
14. "Refunding bonds" means notes, bonds, certificates, or other obligations of a district
issued under this chapter, the proceeds of which are to be used to pay the principal of
or interest on any outstanding bonds or other obligations.
15. "Revenues" means all fees, tolls, rates, rentals, and charges levied and collected by a
district in connection with, and all other income and receipts of whatever kind or
character derived by a district from, the operation of any project.
16. "State engineer" has the same meaning as provided in chapter 61-03.
17. "Warrant" means an order drawn by the proper official of a district on its treasury, the
warrant of order to be so drawn that when signed by the district treasurer in an
appropriate place it becomes a check on the depository of such district, and a warrant
upon the treasury may not be delivered or mailed to the payee or the payee's agent or
representative until the warrant has been signed by the district treasurer and entered
on the district's books as a check drawn on a bank depository.
Page No. 1
61-35-02. Petition.
A petition may at any time be filed with the state engineer requesting the state engineer to
organize a district encompassing an area in one county or in two or more adjacent counties for
the purpose of providing an adequate supply of water for the residents of the area. An area to
be included in a district may not include property then included in any other district or included in
the service area of a nonprofit corporation or cooperative association established under title 10
to operate a rural water system, except as otherwise permitted under section 61-35-25.
61-35-02.1. Conversion of water resource district water supply system to water
district.
A water resource district that has developed a water supply system under chapter 61-16.1
may convert that system to a water district as provided in this section. The water resource
district board operating a water supply system may petition the state engineer to organize a
district in the manner provided by section 61-35-02. The signatures of the water resource
district's board of directors on the petition and a resolution adopted by the water supply system's
users approving the petition suffice in lieu of signatures of owners of fifty percent of the real
property in the proposed district, if the petition presenter provides evidence satisfactory to the
state engineer that a sufficient number of members of the proposed district will subscribe or
have subscribed to benefit units to make its operation feasible. The procedure for hearing and
determination of disposition of the petition is as provided by this chapter. In any district
organized upon the petition of a water resource board of directors, the following procedures
apply:
1. After final approval of the petition by the state engineer, the secretary of the water
resource board shall file a notice with the secretary of state.
2. Upon filing of the notice, the assets and liabilities of the water supply system become
the assets and liabilities of the newly organized district without any further meetings,
voting, notice to creditors, or other actions by the members of the board.
3. The officers and board of directors of the water resource district are the officers and
board of the district.
4. The applicable laws of the state governing the water resource district board control the
initial size and the initial terms of office of officers and the board, in lieu of sections
61-35-08 through 61-35-11.
5. The district shall bring its operation and structure into compliance with the
requirements of section 61-35-08 regarding the number and qualification of directors,
section 61-35-09 regarding new bylaws, section 61-35-10 regarding dividing its
directors into classes, and section 61-35-11 regarding board meetings at the first
annual meeting of the participating members and board. The new district has all the
rights and all the property of the original water supply system and is responsible for all
its obligations. Title to any property is vested in the new district with no reversion or
impairment of ownership rights caused by the conversion to a district. A water supply
agreement entered by a water resource district is binding for its term on a successor
district organized by the water resource district, unless otherwise agreed in writing by
all parties to the agreement. The right of any creditor may not be impaired by this
section without the creditor's consent.
61-35-03. Petition contents.
The petition must be signed by the owners of at least fifty percent of all real property lying
within the outside perimeter of the area designated for inclusion in the proposed district and
must state:
1. The location of the area, describing the area to be served or specifying the area by an
attached map.
2. The reasons a district is needed.
Page No. 2
61-35-04. Hearing after filing.
When a petition for the organization of a district is filed with the state engineer, the state
engineer shall fix a time for a hearing on the petition not less than fifteen nor more than forty-five
days after the filing of the petition. The state engineer shall prepare a notice as required by
section 61-35-05. At least seven days before the date fixed for the hearing on the petition, the
notice must be published in the official county newspapers in the counties included within the
district. The applicant shall pay all costs of the publication notice.
61-35-05. Contents of notice.
The notice prepared by the state engineer must set forth:
1. The location of the area designated by the petitioners to be included in the proposed
district, as described or shown by the original petition.
2. The time and place fixed by the state engineer for the hearing on the petition.
3. That all owners or tenants of real property or other interested persons within the
boundaries described may appear and be heard.
4. That the proposed district, if organized, has no power or authority to levy any taxes.
61-35-06. Appearances.
At the hearing on the petition, any owner or tenant of real property or other interested
person within the boundaries of the area described in the petition may appear, in person or by a
designated representative, and any representative of the state or a political subdivision or an
interested person may appear, in favor of or in opposition to the organization of the proposed
district. The appearances may also be filed in writing before the time set for the hearing.
61-35-07. Findings - Order.
After the hearing, the state engineer may strike off any part of the territory that testimony
shows will not be benefited by the creation of the district. If the state engineer does not find that
the district is reasonably necessary, the state engineer shall dismiss the petition. If the state
engineer finds that required notice of the hearing has been given and that the proposed district
is reasonably necessary for the public health, convenience, and comfort of the residents, the
state engineer shall make an order establishing the district as a political subdivision, designating
its boundary, and identifying it by name or number. The order shall be published in the same
newspaper or newspapers that published the notice of hearing. The applicant shall pay all costs
of the publication of the order. The state engineer shall prepare and preserve a complete record
of the hearing on the petition and the state engineer's findings and action.
61-35-08. Meeting of members - Election of board.
As a part of the order organizing the district, the state engineer shall fix the time and place
at which the members shall meet to select from their number a board of directors. Selection of
the initial board may not be later than thirty days after the order is issued. The number of
directors on the board, not to exceed nine, must be determined by a majority vote of those
members present. Any member elected a director who fails to become a participating member,
within thirty days after entry in the minutes of the board of a declaration of availability of benefit
units for subscription, forfeits the office of director.
61-35-09. Bylaws submitted at special meeting.
Within thirty days after election of the original board, proposed bylaws must be submitted for
adoption at a special meeting of members of the district, written notice of which must be mailed
to each member. Members present at the special meeting may adopt or amend any of the
proposed bylaws, and may propose and adopt alternative or additional bylaws by a majority
vote. The bylaws may subsequently be amended at any annual or special meeting of the
participating members of the district. However, the bylaws of each district must provide:
1. For an annual meeting of participating members each year after the year of
organization of the district and for mailing of written notice of the time and place of
each annual meeting to each participating member and publication of the notice in the
Page No. 3
2.
official newspaper of the county or counties served by the district not less than ten nor
more than thirty days before each meeting.
That each participating member of the district is entitled to one vote at all annual and
special meetings of the district for each benefit unit to which the member has
subscribed.
61-35-10. Directors divided into classes - Terms - Vacancies.
The initial board of each district shall divide its members by lot into three classes of as
nearly equal size as possible. The terms of the directors in the first, second, and third classes
expire on dates of the annual meetings in the first, second, and third years, respectively,
following the year in which the district is organized, or as soon thereafter as their successors are
elected and have qualified. At the annual meeting in each year after the year in which the district
is organized, a director must be elected to succeed each director whose term of office expires
on that date, and each director so elected holds office for a term of three years and until a
successor is elected and has qualified. Vacancies must be filled for the unexpired term by
appointment by the remaining directors.
61-35-11. Board meetings.
The board shall meet annually on the same day as, and immediately following, the annual
meeting of participating members, and may meet at other times it determines, or upon the call of
the president or any two directors. At the first meeting of the initial board following its election,
and at each succeeding annual board meeting, the board shall elect a president, vice president,
secretary, and treasurer for the ensuing year. Board members are entitled to reasonable
compensation to cover the expenses of serving on the board.
61-35-12. Powers of district board.
Each district board has the power to:
1. Sue and be sued in the name of the district.
2. Exercise the power of eminent domain in the manner provided by title 32 for the
purpose of acquiring and securing any rights, titles, interests, estates, or easements
necessary or proper to carry out the duties imposed by this chapter, and particularly to
acquire the necessary rights in land for the construction of pipelines, reservoirs,
connections, valves, pumping installations, or other facilities for the storage,
transportation, or utilization of water and all other appurtenant facilities necessary to
carry out the purposes of its organization.
3. Accept funds, property, and services or other assistance, financial or otherwise, from
federal, state, and other public or private sources for the purpose of aiding and
promoting the construction, maintenance, and operation of projects within the district.
4. Cooperate and contract with the state, its agencies, or its political subdivisions or any
federal agency in research and investigation or other activities promoting the
establishment, construction, development, or operation of projects within the district.
5. Furnish assurances of cooperation, and as principal and guarantor, or either, to enter
into contracts with any federal agency, and with public corporations and political
subdivisions of this state for the performance of obligations for the construction,
operation, or maintenance of the district or for the delivery of water to any such
department, agency, or political subdivision.
6. Construct, lease, or purchase separately or in cooperation with any federal agency or
the state, its agencies, or political subdivisions, and to equip, maintain, and operate an
office and principal place of business for the district, or other buildings or facilities to
carry out activities authorized by this chapter.
7. Appoint and fix the compensation and reimbursement of expenses of such employees
as the board deems necessary to conduct the business and affairs of the district and
to procure the services of engineers and other technical experts, and to retain
attorneys to assist, advise, and act for it in its proceedings.
Page No. 4
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
Sell or exchange any and all real property purchased or acquired by the district. All
money received from any such sale or exchange must be deposited to the credit of the
district and may be used to pay expenses of the district.
Borrow money as provided in this chapter.
Issue and sell bonds in an amount or amounts determined by the board, including an
amount or amounts for costs of issuance and financing, and any necessary reserve
funds, for the purpose of financing the cost of a project.
Refund and refinance its bonds from time to time as often as it is advantageous and in
the interest of the district.
Pledge any and all income, profits, and revenues received by the district in connection
with the operation, lease, sale, or other disposition of all or any part of a project to
secure the payment of bonds issued and sold to finance the project.
Pledge all or any part of any assessments levied under this chapter to secure the
payment or redemption of any bonds issued in anticipation of the levy and collection of
the assessments.
Acquire by gift, purchase, or the exercise of the right of eminent domain, property
required to construct, reconstruct, improve, better, or extend any project, whether
completely or partially within or outside the district, and easements, rights in lands, and
water rights in connection with the project.
Operate and maintain any project for its own use and for the use of public and private
consumers and users within and without the territorial boundaries of the district.
Prescribe, revise, and collect rates, fees, tolls, or charges for the services, facilities, or
commodities furnished by the project, and in anticipation of the collection of the
revenues of the project, issue revenue bonds to finance all or part of the cost of the
acquisition, construction, reconstruction, improvement, betterment, or extension of any
project.
Pledge revenues of the project to the punctual payment of principal and interest on
bonds. A pledge under this subsection applies to the revenues of improvements,
betterments, or extensions of the project which may be constructed or acquired after
the issuance of bonds as well as the revenues of existing systems, plants, works,
instrumentalities, and properties of any part of the project improved, bettered, or
extended.
Make all contracts, execute all instruments, and do all things necessary or convenient
in the exercise of its powers or in the performance of its covenants or duties or in order
to secure the payment of its bonds, but an encumbrance, mortgage, or other pledge of
property of the district may not be created by any such contract or instrument.
Enter into and perform long-term or short-term contracts with any nongovernmental
unit for the provision and operation by the district of sewerage facilities, when the
board of the district determines such action to be in the public interest and necessary
for the protection of the public health, in order to abate or reduce the pollution of
waters caused by discharges of industrial wastes by the nongovernmental unit, and for
the payment periodically by the nongovernmental unit to the district of amounts the
board deems sufficient to compensate the district for all costs associated with
providing, operating, and maintaining the sewerage facilities serving the
nongovernmental unit.
Enter into and perform such contracts and agreements with other districts, political
subdivisions, and state institutions as the board deems proper and feasible concerning
the planning, construction, lease, or other acquisition and the financing, maintenance,
and operation of sewerage facilities. Any districts contracting with each other may
provide in any contract or agreement for a board, commission, or such other body as
their boards deem proper to supervise, manage, and operate the sewerage facilities
and may prescribe its powers and duties and compensation of its members.
Accept from any authorized federal agency loans or grants for the planning,
construction, acquisition, lease, or other provision of any project, and to enter into
agreements with such agency respecting such loan or grants.
Page No. 5
22.
Contract debts and borrow money, pledge property of the district for repayment of
indebtedness other than bonded indebtedness, and provide for payment of debts and
expenses of the district.
23. Notwithstanding any other law, exercise the powers granted to a municipality under
subsection 5 of section 40-33-01 and section 40-34-19, pursuant to the limitations set
forth therein. A district may pay the cost of leasing any waterworks, mains, and water
distribution system and any equipment or appliances connected therewith and any
property related thereto pursuant to subsection 5 of section 40-33-01, or of any
sewage system and all related property for the collection, treatment, purification, and
disposal in a sanitary manner of sewage pursuant to section 40-34-19, solely from
revenues to be derived by the district from the ownership, sale, lease disposition, and
operation of the waterworks, mains, and water distribution system or sewage system;
the funds or any other amounts invested by such district pursuant to section 21-06-07,
or invested on such district's behalf by the state, or any agency or institution of the
state, in conformity with policies of the industrial commission, including investment in a
guaranteed investment contract and any earnings thereon, to the extent pledged
therefor; and funds, if any, appropriated annually by the board of the district or
received from federal or state sources.
24. Enter and perform long-term and short-term contracts for the purchase or sale of water
and to pledge any and all income, profits, and revenues received by the district to
secure payment of the district's obligations created by the contracts.
Property of the district may not be liable to be forfeited or taken in payment of any bonds issued
under this chapter, and debt on the general credit of the district may not be incurred in any
manner for payment of bonds under this chapter.
61-35-13. Contracts for construction or maintenance of a project.
If the cost of construction or maintenance of a project does not exceed the amount provided
for construction of a public improvement under section 48-01.2-02, the work may be done on a
day work basis or a contract may be let without being advertised. If the cost of the construction
or maintenance exceeds the amount provided for construction of a public improvement under
section 48-01.2-02, the lowest and best bid must be accepted. The board must comply with the
requirements of sections 61-35-88 through 61-35-103 when bidding a project.
The competitive bid requirement of this section may be waived if the board determines that
an emergency exists requiring the prompt repair of a project and a contract may be made for the
prompt repair of the project without seeking bids.
61-35-14. Financing project through improvement bonds or special assessments Apportionment of benefits.
A board may acquire needed interest in property and provide for the cost of construction,
alteration, repair, operation, and maintenance of a project with funds raised by special
assessments. A board may issue improvement bonds in anticipation of the levy and collection of
special assessments. If a board decides to acquire property or interests in property to construct,
operate, alter, repair, or maintain a project with funds raised in whole or in part through special
assessments, the assessments must be apportioned to and spread in proportion to benefits
accruing to lands or premises benefited by the project. The board shall assess the proportion of
the cost of the project, or the part of the cost to be financed with funds raised through levy and
collection of special assessments which any lot, piece, or parcel of land bears in proportion to
the benefits accruing to the property and any county, city, or township that is benefited.
61-35-15. Revenue bonds.
A district may issue revenue bonds, not exceeding an aggregate total outstanding of fifty
million dollars, to finance construction of projects and incidental facilities authorized by this
chapter. Issuance of revenue bonds must be approved by two-thirds of all of the members of the
district board. The district shall pledge sufficient revenue from any revenue-producing facility
constructed with the aid of revenue bonds for the payment of principal and interest on the bonds
Page No. 6
and shall establish rates for the facilities at a sufficient level to provide for the operation of such
facilities and for the bond payments. Revenue bonds may not be a general obligation of any
political subdivision and may not be secured by property taxes.
61-35-16. Plans and specifications.
As soon as reasonably possible after organizing a district, the board shall file with the state
engineer copies of the plans and specifications for, and estimates of the cost of, any
improvements authorized by this chapter which the board proposes to construct or acquire. The
board shall determine a reasonable fee that each member shall pay for the privilege of utilizing
the district's facilities, which shall be known as a benefit unit. By publication in the official county
newspaper of each county in which all or part of the district is located, the board shall generally
describe the planned improvements, the area to be served, and the fee members will be
required to pay for each service connected to the water system.
61-35-17. Selling water.
If the capacity of the district's facilities permits, the district may sell water by contract to any
political subdivision, other district, or other person, public or private, not within the boundaries of
the district.
61-35-18. Inclusion of property in district - Inclusion of municipality - Merger.
1. Owners of real property outside any district which can economically be served by the
facilities of the district may petition to be attached to the district. The petition must be
filed with the state engineer and the state engineer shall proceed in substantially the
same manner as is provided by this chapter for filing of and proceeding on a petition
for organization of a district.
2. All or part of an incorporated city may be included in the boundaries of any existing
district or a district being newly organized, provided the governing body of the city by
resolution or ordinance gives its consent.
3. Boards of two or more districts by concurrent action and by approval of the state
engineer may merge their districts into one. In case of merger, the members of the
boards of the merged districts may serve until the next annual meeting at which time
the district shall comply with the requirements of section 61-35-08 regarding the
number and eligibility of directors, adopt new bylaws, and set the terms of the new
board according to section 61-35-10. The resulting district shall take over all the assets
and legal liabilities of the districts joining in the merger. Obligations of any district
secured by the revenue of the systems operated by the district must continue to be
required, or a sinking fund must be established for that purpose created from revenue
from the system operated over the same area by the resulting district in accordance
with the laws under which the obligations were issued, until all obligations of the old
district have been retired.
4. If there is a conflict between two or more districts concerning which district will serve
an area, the state engineer, after a public hearing, shall determine which district can
more adequately and economically provide service within the area.
61-35-19. Taxing prohibited.
A district has no power to levy any taxes. The facilities constructed or otherwise acquired by
any district, including ponds, reservoirs, pipelines, wells, deck dams, and pumping installations,
the revenues obtained by the district from the sale of water, and the revenue bonds or interest
on the revenue bonds issued by any district are not taxable in any manner by the state or a
political subdivision.
61-35-20. Exclusion of real property from district.
If it becomes apparent that any real property included within a district but contiguous to a
border cannot economically or adequately be served by the facilities of the district, the owners
Page No. 7
of the real property or the board may file with the state engineer a petition to the state engineer
requesting that the real property be excluded from the district. The petition must:
1. Describe by full and partial section and by township and range, or by lot number and
subdivision, as the case may be, the real property that it is proposed to exclude from
the district.
2. State that the real property cannot economically or adequately be served by the
facilities of the district and that it is not feasible for the district to enlarge or extend its
facilities to economically and adequately serve the real property.
3. Be signed by the owners of all the real property that it is desired to exclude from the
district or by all of the board.
61-35-21. Inactive district dissolved.
A petition may be filed with the state engineer requesting the state engineer to dissolve an
inactive district. The petition must:
1. List all real and personal property of any kind exclusive of records, maps, plans, and
files and state that all of its debts and obligations have been fully paid.
2. State that the district is not functioning and will probably continue to be inoperative.
3. Be signed by three-fourths of the members of the district.
61-35-22. Hearing.
Upon the filing with the state engineer of a petition under section 61-35-20 or 61-35-21, the
state engineer shall fix a time for consideration of the petition. The state engineer may hold a
hearing on the petition. After consideration of the petition, and after the hearing if one is held,
the state engineer shall ascertain whether:
1. The petition meets all of the requirements prescribed by section 61-35-20 or 61-35-21.
2. It appears from all information available to the state engineer that each allegation
included in the petition is factual.
If the state engineer's finding on each of the foregoing points is positive, the state engineer shall
declare the real property described in the petition detached from the district or declare the
district dissolved, as the case may be. The state engineer shall notify the secretary of the district
of the state engineer's action and the secretary shall amend the records of the district to show
that the real property described in the petition has been detached from the district. Within thirty
days, the secretary shall deliver to the state engineer all records, maps, plans, and files of the
dissolved district.
61-35-23. Disposition of assets.
If a district is dissolved, the state engineer shall provide for the disposition of any property
owned by the district and for the apportionment of the proceeds and any other moneys
belonging to the district to an adjoining district. If there is no adjoining district, the state engineer
shall apportion and dispose of the property and proceeds to the general fund of each county in
the district in proportion to the county's area in the district. Any pledge or lien given with respect
to any outstanding bonds of the district remains and any property so encumbered must be
handled in conformity with the bond resolution or trust indenture. Money, property, or the
proceeds from property may not be distributed to any private interests.
61-35-24. Not exempt from other requirements.
This chapter does not exempt any district from the requirements of any other statute,
whether enacted before or after August 1, 1995, under which the district is required to obtain the
permission or approval of, or to notify, the water commission, or the state department of health,
or any other agency of this state or of any of its political subdivisions before proceeding with
construction, acquisition, operation, enlargement, extension, or alteration of any works or
facilities that the district is authorized to undertake under this chapter.
Page No. 8
61-35-25. Alternate operation by nonprofit corporation or cooperative.
A nonprofit corporation or cooperative association established under title 10 for the specific
purpose of operating a rural water system may petition the state engineer to organize a district,
in the manner provided by section 61-35-02. The signatures of the corporation's or cooperative's
officers on the petition and a resolution adopted by the members in the manner provided in
section 10-15-37 for amendments to articles or in the manner provided in chapter 10-33 for
dissolution, as the case may be, approving the petition suffice in lieu of signatures of owners of
fifty percent of the real property in the proposed district, if the petition presenter provides
evidence satisfactory to the state engineer that a sufficient number of members of the proposed
district will subscribe or have subscribed to benefit units to make its operation feasible. The
procedure for hearing and determination of disposition of the petition is as provided by this
chapter. In any district organized upon the petition of a nonprofit corporation or cooperative
association, the following procedures apply:
1. After final approval of the petition by the state engineer, the secretary of the
corporation or cooperative shall file a notice with the secretary of state or attorney
general, if applicable, in accordance with title 10.
2. Upon filing of the notice, the nonprofit corporation or cooperative ceases to exist as a
title 10 entity and all assets and liabilities of the nonprofit corporation or cooperative
become the assets and liabilities of the newly organized district without any further
meetings, voting, notice to creditors, or other actions by the members of the board.
3. The officers and board of directors of the corporation or cooperative are the officers
and board of the district.
4. The applicable laws of the state and the articles of incorporation and bylaws of the
corporation or cooperative control the initial size and initial term of office of officers and
the board, in lieu of sections 61-35-08 through 61-35-11.
5. The district shall bring its operation and structure into compliance with the
requirements of section 61-35-08 regarding the number and qualification of directors,
section 61-35-09 regarding new bylaws, section 61-35-10 regarding dividing its
directors into classes, and section 61-35-11 regarding board meetings at the first
annual meeting of the participating members and board. The new district has all the
rights and all the property of the original corporation or cooperative and is responsible
for all its obligations. Title to any property is vested in the new district with no reversion
or impairment of ownership rights caused by the conversion to a district. A water
supply agreement entered by a nonprofit corporation or cooperative association is
binding for its term on a successor district organized by the nonprofit corporation or
cooperative association, unless otherwise agreed in writing by all parties to the
agreement. The right of any creditor may not be impaired by this section without the
creditor's consent.
61-35-26. Annexation of land by a municipality.
A district organized under this title or title 10 must be fairly compensated for losses resulting
from annexation by a city under chapter 40-51.2. If a district has outstanding bonds, the
annexation proceedings must be in accordance with the bond resolution or trust indenture. The
governing body of a city and the board of directors of the district may agree to terms that
provide that the facilities owned by the district and located within the city must be retained by
the district for the purpose of transporting water to customers outside the municipality.
61-35-26.1. Statement of intent.
It is the intent of the legislative assembly that potable water should be available in
sufficient quality and quantity to meet citizens' needs for a healthy and safe standard of
living and to promote economic growth and development. In order to meet this objective
in the most economical way, water service districts and city water service systems shall
coordinate their service plans. Competition for users and duplication of service must be
avoided whenever possible.
Page No. 9
61-35-26.2. Plans for water service by providers - Filing plans - Existing agreements.
1. A city planning to expand water service through annexation shall develop a city water
service area plan. The city shall consult with any other water service provider,
including a district, whose water service area is affected by the city's water service
area plan of the establishment of the plan.
2. The city shall file the city water service area plan with the commission. Upon filing of
the plan with the commission, the city may proceed with water service to the annexed
area as provided in section 61-35-26. A city water service area plan is enforceable
when there is a water service agreement among the water service providers, including
a district, that are encompassed by or which abut the water service area boundary.
3. Sections 61-35-26.1 through 61-35-26.4 do not supersede an existing water service
agreement between a city and a district.
61-35-26.3. State water commission funding.
Before providing a grant or loan to a district or city for a water service project in any area
within the extraterritorial zoning jurisdiction of any affected city, the commission shall require that
district and city to have a water service agreement. The absence of a water service agreement
may not affect the funding by the commission of other projects for a district or city which are not
related to potable water service and are not located within the extraterritorial zoning jurisdiction.
61-35-26.4. Water service agreement - Mediation - Administrative law judge.
1. If a water service agreement between the district and the city is not executed within
sixty days after the city notifies the district that a city water service area plan has been
developed, the matter must be submitted to a committee for mediation. The committee
must be comprised of a mediator retained jointly by the city and the district, two
members appointed by the governing body of the city, and two members appointed by
the district. The retained mediator shall arrange and preside over the mediation
proceedings.
2. If the mediation committee is unable to resolve the dispute to the satisfaction of the
parties involved, either party may petition the office of administrative hearings to
appoint an administrative law judge to determine the terms of the water service
agreement. Before a hearing may be held, at least two weeks' written notice must be
given to the parties involved in the dispute. At the hearing, the retained mediator who
presided over the mediation proceedings may provide information to the administrative
law judge on the dispute between the parties involved and any proposed resolutions or
recommendations made by a majority of the members appointed to the committee.
Any resident of or person owning property in a city or district involved in the dispute, or
a representative of such a resident or property owner, and any representative of a city
or district involved, may appear at the hearing and present evidence on any matter to
be determined by the administrative law judge. A decision by the administrative law
judge must consider the following factors related to water service in the annexed area
in making a decision under this subsection:
a. The recommendation of the mediation committee;
b. The firefighting flow capacity of the water system;
c. The anticipated growth patterns of the district and city involved in the dispute;
d. Special conditions or needs, including topographic or physical features
influencing service;
e. The system capacity and trunk main delivery structure of each provider;
f. The age, condition, and worth of the affected existing infrastructure;
g. Outstanding debt attributable to current users;
h. The impact on future revenues lost from existing and future customers;
i. Whether development would have occurred without annexation; and
j. Any other factor determined to be relevant by the administrative law judge.
Page No. 10
61-35-27. Personal liability.
Except as otherwise provided in this chapter, a director, officer, employee, or other
personnel of the board are not liable for the district's debts or obligations and a director, officer,
employee, or volunteer of the board is not personally liable in that capacity for a claim based
upon an act or omission of the person in the discharge of the person's duties, except for any of
the following:
1. A breach of the duty of loyalty to the district.
2. Acts or omissions not in good faith or which involve intentional misconduct or knowing
violation of the law.
3. A transaction from which the person derives an improper personal benefit.
61-35-28. Proceedings to confirm contracts, special assessments, and other acts.
Any district board, before making any contract, levying special assessments, or issuing
special assessment improvement bonds or revenue bonds, or before taking any special action,
may commence a special proceeding in district court by which the proceeding leading up to the
making of such contract, levying special assessments, issuing improvement bonds or revenue
bonds, or leading up to any other special action, may be judicially examined, approved, and
confirmed. Such judicial proceedings must substantially comply with the procedure required in
the case of judicial confirmation of proceedings, acts, and contracts of an irrigation district.
61-35-29. Authorization to organize association of rural water systems.
A district, upon resolution of the district board, may organize and participate in an
association of rural water systems organized under chapter 10-33.
61-35-30. Resolution authorizing project and the issuance of revenue bonds.
The acquisition, construction, reconstruction, improvement, betterment, or extension of any
project and the issuance of bonds in anticipation of the collection of the revenues of such project
to provide funds to pay the associated costs may be authorized by a resolution of the board
adopted after appropriate notice by the affirmative vote of a majority of the board. The amount
of such bonds may not exceed the amount authorized by the participating members of the
district as provided in this chapter. Unless otherwise provided in the resolution, the resolution
under this section takes effect immediately and need not be laid over, published, or posted.
61-35-31. Refunding bonds authorized by resolution - Adoption - Taking effect.
Refunding bonds must be authorized by resolution of the board. The resolution may be
adopted at a regular or special meeting, including the meeting at which it is introduced, by the
affirmative vote of a majority of the members of the board, and takes effect immediately upon
adoption. Other proceedings or procedure are not required for the issuance of refunding bonds
by the district.
61-35-32. Cost of project - How determined.
In determining the cost of a project, the board may include the estimated cost of bond
issuance, all engineering, inspection, fiscal, and legal expenses, any bond reserves, and the
estimated interest that will accrue during construction, and within six months after completion of
construction.
61-35-33. Provisions governing bonds.
The resolution authorizing the issuance of revenue bonds or refunding bonds under this
chapter or resolutions adopted after the adoption of the original resolution must prescribe:
1. The rate or rates of interest, payable semiannually.
2. Whether the bonds will be in one or more series.
3. The date or dates the bonds will bear.
4. The time or times, not exceeding forty years from their respective dates, when the
bonds will mature.
5. The medium in which the bonds will be payable.
Page No. 11
6.
7.
8.
9.
10.
11.
The place or places where the bonds will be payable.
Whether or not the bonds will carry registration privileges and what those privileges, if
any, will be.
The terms of redemption, if any, to which the bonds will be subject.
The manner in which the bonds will be executed.
The terms, covenants, and conditions that the bonds will contain.
The form in which the bonds will be issued.
61-35-34. Sale of bonds - When private sale authorized - Public sale and notice.
Revenue bonds or refunding bonds must be sold at not less than ninety-eight percent of
par. The bonds may be sold at private sale without notice or at public sale after notice of the
sale has been published once at least five days before the sale in a newspaper circulating in the
district. Bonds sold at private sale must bear interest at a rate and be sold at a price resulting in
an average net interest cost not exceeding twelve percent per annum. There is no interest rate
ceiling on issues sold at public sale or to the state or any of its agencies or instrumentalities. As
to any series or issue of bonds for which a notice of sale was published but for which no bids
were received or all bids received were rejected, the board, without readvertising the bonds for
sale, may negotiate the sale of all of the bonds to any person upon terms complying with those
specified in the published notice of sale and, if bids were rejected, more favorable to the district
than those specified in the rejected bid.
61-35-35. Bonds and receipts or certificates issued pending preparation of bonds Negotiability.
Pending the preparation of the definitive bonds, bond anticipation notes may be issued and
sold in the form and with the provisions determined by the board.
61-35-36. Validity of bonds.
Revenue bonds or refunding bonds bearing the signatures of the appropriate officers who
are in office on the date of signing are valid and binding obligations notwithstanding that before
the delivery and payment any or all of the persons whose signatures appear on the bonds have
ceased to be officers of the issuing district. The validity of the bonds is not dependent upon or
affected by the validity or regularity of any proceedings relating to the acquisition, purchase,
construction, reconstruction, improvement, betterment, or extension of the project for which the
bonds are issued. The resolution authorizing the bonds may provide that the bonds must
contain a recital that they are issued under this chapter and the recital is conclusive evidence of
their validity and of the regularity of their issuance.
61-35-37. Bonds exempt from taxation.
Bonds issued under this chapter and their income are exempt from taxation by the state or
by any political subdivision.
61-35-38. Covenants that may be inserted in resolution authorizing bonds.
Any resolution authorizing the issuance of bonds under this chapter to completely or
partially finance or refinance the acquisition, construction, reconstruction, improvement,
betterment, or extension of a project may contain covenants that limit the exercise of powers
conferred by this chapter as to:
1. The rates, fees, tolls, or charges to be charged for the services, facilities, and
commodities of the project.
2. The use and disposition of the revenues of the project.
3. The creation, maintenance, regulation, use, and disposition of reserves or sinking
funds.
4. The purpose to which the proceeds of the sale of bonds may be applied and the use
and disposition of the proceeds.
Page No. 12
5.
The events of default and the rights and liabilities arising upon default and the terms
and conditions upon which the holders of bonds issued under this chapter may bring
any suit or action on said bonds.
6. The payment by the district to the account of the project of a fair and reasonable
amount for the services, facilities, or commodities furnished the district or any of its
departments by the project.
7. The issuance of other or additional bonds or instruments payable from or constituting a
charge against the revenue of the project.
8. The insurance to be carried upon the project and the use and disposition of insurance
moneys.
9. The keeping, inspection, and audit of books of account.
10. The terms and conditions upon which any or all of the bonds become or may be
declared due before maturity and the terms and conditions upon which the declaration
and its consequences may be waived.
11. The rights, liabilities, powers, and duties arising upon the breach by the district of any
covenants, conditions, or obligations.
12. The vesting in a trustee of the right to enforce any covenants made to secure, to pay,
or in relation to, the bonds, the powers and duties of such trustee, and the limitations
of liabilities thereof.
13. The terms and conditions upon which the holders of the bonds, or the holders of any
proportion or percentage of them, may enforce any covenants made or any duties
imposed under this chapter.
14. A procedure by which the terms of any resolution authorizing bonds or of any other
contract with bondholders, including an indenture of trust or similar instrument, may be
amended or abrogated, and the amount of bonds that holders of which must consent
to the resolution or contract, and the manner in which such consent may be given.
15. The subordination of the security of any bonds issued under this chapter and the
payment of principal and interest on those bonds, to the extent deemed feasible and
desirable by the governing body, to other bonds or obligations of the district issued to
finance or refinance the project or that may be outstanding when the bonds thus
subordinated are issued and delivered.
Nothing in this section authorizes any district to do anything in any manner or for any purpose
which would result in the creation or incurring of a debt or indebtedness or the issuance of any
instrument which would constitute a debt or indebtedness within the meaning of any provision,
limitation, or restriction of the Constitution of North Dakota relating to the creation or incurring of
a debt or indebtedness or the issuance of an instrument constituting a debt or indebtedness.
61-35-39. Liability of district for bonds - Taxing power prohibited - Bond not a lien.
Revenue and refunding bonds issued under this chapter may not be payable from or
charged upon any funds other than the revenue pledged to their payment and the district issuing
the bonds may not be subject to any pecuniary liability. The holder of any such bonds may not
enforce payment of the bonds against any property of the district. Bonds issued under this
chapter do not constitute a charge, lien, or encumbrance upon any property of the district. Each
bond issued under this chapter must recite in substance that the bond, and interest on the bond,
is payable solely from the revenue pledged to the payment and that the bond does not
constitute a debt of the district within the meaning of any constitutional or statutory limitation.
61-35-40. Duties of district and officers.
To adequately secure the payment of bonds and interest on the bonds, any district issuing
bonds under this chapter, and the district's officers, agents, and employees shall:
1. Pay or cause to be paid punctually the principal and interest of every bond on the
dates, at the places, in the manner, and out of the funds provided in the refunding
bond and in accordance with the resolution authorizing its issuance.
2. Operate the project in an efficient and economical manner and establish, levy,
maintain, and collect related necessary or proper fees, tolls, rentals, rates, and other
charges. Such fees, tolls, rentals, rates, and other charges must be sufficient, after
Page No. 13
making due and reasonable allowances for contingencies and for a margin of error in
the estimates, at least:
a. To pay all current expenses of operation and maintenance of the project;
b. To pay the interest and principal on the bonds as they become due;
c. To comply with the terms of the resolution authorizing the issuance of the bonds
or any other contract or agreement with the holders of the refunding bonds; and
d. To meet any other obligations of the district which are charges, liens, or
encumbrances upon the revenues of the project.
3. Operate, maintain, preserve, and keep every part of the project in good repair, working
order, and condition.
4. Preserve and protect the security of the bonds and the rights of the bondholders and
warrant and defend such rights against all claims and demands.
5. Pay and discharge all lawful claims for labor, materials, and supplies, which, if unpaid,
might become by law a lien or charge upon the revenues, or any part of the revenues,
superior to the lien of the bonds or which might impair the security of the bonds.
6. Hold in trust the revenues pledged to the payment of the bonds for the benefit of the
holders of the bonds and apply the revenues only as provided by the resolution
authorizing the issuance of the bonds, or, if the resolution is modified, as provided in
the modified resolution.
7. Keep proper separate books of record and accounts of the project in which complete
and correct entries must be made of all transactions relating to any part of the project.
All books and papers of the district are subject to inspection by the holders of ten
percent or more of the outstanding bonds or of their representatives authorized in
writing.
None of the duties contained in this section require any expenditure by the district of any funds
other than revenue received from the project. The performance of the duties enumerated in this
section is of the essence of the contract of the district with the bondholders.
61-35-41. Remedies of bondholders in general.
Subject to any contractual limitations binding upon the holders of any issue of bonds, or a
trustee for the holders, including the restriction of the exercise of any remedy to a specified
proportion or percentage of the holders, any holder of bonds or trustee, for the equal benefit and
protection of all bondholders similarly situated, may:
1. By mandamus or other suit, action, or proceeding at law or in equity, enforce the
holder's rights against the district and its board and any of its officers, agents, and
employees and may require the district or the board or any officers, agents, or
employees of the district or board to perform their duties and obligations under this
chapter and their covenants and agreements with bondholders.
2. By action or suit in equity, require the district and the board to account as if they were
the trustees of an express trust.
3. By action or suit in equity, enjoin any acts or things that may be unlawful or in violation
of the rights of the bondholders.
4. Bring suit upon the bond.
A right or remedy conferred by this chapter upon any bondholder, or upon any trustee for a
bondholder, is not intended to be exclusive of any other right or remedy, but each such right or
remedy is cumulative and in addition to every other right or remedy and may be exercised
without exhausting and without regard to any other remedy conferred by this chapter or by any
other law of this state.
61-35-42. Receiver of project - When appointed.
If the district defaults in the payment of the principal or interest on any of the bonds when
due, whether at maturity or upon call for redemption, and the default continues for a period of
thirty days, or if the district or the board, or officers, agents, or employees of the district fail or
refuse to comply with the provisions of this chapter, or default in any agreement made under this
chapter, or default in any agreement made with the holders of the bonds, any bondholder, or the
trustee for any bondholder, may apply to the district court of the county in which all or any part of
Page No. 14
the project is located for the appointment of a receiver of the project whether or not all of the
bonds have been declared due and payable and whether or not the holder or trustee is seeking
or has sought to enforce any other right or to exercise any other remedy in connection with the
bonds. Upon such application, the court may appoint a receiver of the project. If the application
is made by the holders of twenty-five percent in principal amount of the outstanding bonds, or by
any trustee for holders of the bonds in that principal amount, the court shall appoint a receiver of
the project.
61-35-43. Powers and duties of receiver of project.
A receiver appointed under section 61-35-42, directly or by agents and attorneys, shall
immediately enter into and upon and take possession of the entire project and may exclude
from the project the district, its board, officers, agents, and employees, and all persons claiming
under them. The receiver shall have, hold, use, operate, manage, and control the entire project
in the name of the district or otherwise as determined by the receiver. The receiver shall
exercise all the rights and powers of the district with respect to the project. The receiver shall
maintain the project and restore and keep it insured and make all repairs the receiver deems
necessary, proper, or expedient. The receiver shall establish, levy, maintain, and collect such
fees, tolls, rentals, and other charges in connection with the project as the receiver deems
necessary, proper, and reasonable. The receiver shall collect all revenues, deposit them in a
separate account, and apply them as the court directs.
61-35-44. Court may direct receiver to surrender possession of project.
After payment of all that is due upon the bonds and any other obligations that are a charge,
lien, or encumbrance on the revenues of the project under any of the terms of any covenants or
agreements with bondholders, and after all defaults have been made good, the court, after
notice and hearing as it deems proper, may direct the receiver to surrender the possession of
the project to the district. The holders of the bonds have the same right to secure the
appointment of a receiver upon any subsequent default as is provided in this chapter in the case
of an original default.
61-35-45. Receiver subject to jurisdiction of court - Jurisdiction of court.
A receiver under this chapter acts under the direction and supervision of the appointing
court and is subject to the orders of that court and may be removed by it. This chapter does not
limit the jurisdiction of the court to enter orders it deems necessary for the receiver to exercise
any functions set forth in this chapter.
61-35-46. Construction.
Powers under this chapter are in addition and supplemental to and not in substitution for,
and the limitations imposed by this chapter do not affect the powers conferred by, any other law.
Bonds may be issued under this chapter without regard to any other laws of this state, except as
provided in section 61-35-39. The project may be acquired, purchased, constructed,
reconstructed, improved, bettered, and extended, and bonds may be issued under this chapter
for those purposes, notwithstanding that any other law may provide for the acquisition,
purchase, construction, reconstruction, improvement, betterment, and extension of a like project
or for the issuance of bonds for like purposes, and without regard to the requirements,
restrictions, debt, or other limitations or other provisions contained in any other law, including
any requirement for any restriction or limitation on the incurring of indebtedness or the issuance
of bonds. If this chapter is inconsistent with any other law of this state, the provisions of this
chapter are controlling with reference to the issuance of bonds.
61-35-47. Limitations on authorizations contained in chapter - Effect of chapter on
bonds issued before August 1, 1995.
Nothing in this chapter may be deemed in any way to:
1. Alter the terms of any agreements made with the holders of any outstanding notes,
bonds, or other obligations of the district, before August 1, 1995;
Page No. 15
2.
3.
Authorize the district to alter the terms of any such agreements, or to impair, or to
authorize the district to impair, the rights and remedies of any creditors of the district;
or
To authorize any district to do anything in any manner or for any purpose which would
result in the creation or incurring of a debt or indebtedness or the issuance of any
instrument that would constitute a debt or indebtedness within the meaning of any
provision, limitation, or restriction of the Constitution of North Dakota relating to the
creation or incurring of a debt or indebtedness or the issuance of an instrument
constituting a debt or indebtedness.
61-35-48. Power of district to defray expense of improvements by special
assessments.
Upon complying with this chapter, a district may defray the expense of any or all of the
improvements by special assessments, including the construction of all or part of a water supply
system or a sewerage system, or both, or any improvement, extension, or replacement of such
systems, including the construction and erection of wells, intakes, pumping stations, settling
basins, filtration plants, standpipes, water towers, reservoirs, water mains, sanitary and storm
sewer mains and outlets, facilities for the treatment and disposal of sewage and other district,
industrial, and domestic wastes, and all other appurtenances, contrivances, and structures used
or useful for a complete water supply and sewerage system. In planning an improvement
project, the board may include in the plans any and all items of work and materials which in its
judgment are necessary or reasonably incidental to the completion of an improvement project of
that type.
61-35-49. Waterworks and water mains - Acquisition of waterworks, sewage treatment
and disposal plants, and sewer systems.
The provisions of this chapter relating to water mains and waterworks apply only to districts
that own or contemplate owning a system of waterworks and water mains. In the purchase of a
waterworks system or of a sewage treatment or disposal plant or of a system of sewers, either
by eminent domain in accordance with chapter 32-15, or otherwise, a district may create
improvement districts, direct the preparation of plans and specifications, adopt a resolution
declaring the purchase of the facilities necessary, and take all other proceedings prescribed by
this chapter which would be taken in case of the construction of such facilities by the district
itself for the purpose of defraying the cost by special assessment of the benefited property. The
benefited property may be specially assessed for the purchase of such facilities, either
separately or as a part of a new system, the same as if the facilities were constructed entirely
anew.
61-35-50. Acquiring property for sewers, water mains, and water supply beyond
district limits.
When it is necessary to conduct the sewage of a district or to acquire a supply of water
beyond the district limits and to construct mains or aqueducts to conduct water or sewage to the
district limits, the board by grant, purchase, or condemnation proceedings may acquire private
property over which to construct the sewer, or upon and over which to establish facilities for
obtaining and storing such water supply and aqueducts or mains for conducting water to the
corporate limits. Public property may be acquired for those purposes by grant or purchase from
the government or public corporation owning the property. The cost of acquiring such property
and building such sewer or other facilities upon or over the property may be included in the cost
of construction or acquisition of a district waterworks or sewerage system and in the district's
special assessments levied, or the entirety of such a project may be completed as an
improvement to an existing waterworks or sewage system and special assessments may be
levied for that purpose in accordance with the provisions of this title.
Page No. 16
61-35-51. Condemnation of land and rights of way for special improvements - Taking
of possession - Trial - Appeal - Vacation of judgment.
When property required to make any improvement authorized by this chapter is to be taken
by condemnation proceedings, the court, upon request by resolution of the board of the district
making the improvement, shall call a special term of court for the trial of the proceedings and
may summon a jury for the trial. The proceedings must be instituted and prosecuted in
accordance with chapter 32-15, except that when the interest sought to be acquired is a right of
way for the laying of any main, pipe, ditch, canal, aqueduct, or flume for conducting water, storm
water, or sewage, whether within or without the district, the district may make an offer to
purchase the right of way and may deposit the amount of the offer with the clerk of the district
court of the county in which the right of way is located, and may then take possession of the
right of way. The offer must be made by resolution of the board of the district, and a copy of the
resolution must be attached to the complaint filed with the clerk of court in accordance with
section 32-15-18. The clerk shall immediately notify the owners of the land on which the right of
way is located of the deposit by causing a notice to be appended to the summons when served
and published in the proceedings as provided in the North Dakota Rules of Civil Procedure,
stating the amount deposited or agreed in the resolution to be deposited. The owner may then
appeal to the court by filing an answer to the complaint in the manner provided in the North
Dakota Rules of Civil Procedure, and may have a jury trial, unless a jury is waived, to determine
the damages. However, upon due proof of the service of the notice and summons and upon
deposit of the aggregate sum agreed in the resolution, the court may without further notice
make and enter an order determining the district to be entitled to take immediate possession of
the right of way. If under laws of the United States proceedings for the acquisition of any right of
way are required to be instituted in or removed to a federal court, the proceedings may be taken
in that court in the same manner and with the same effect as provided in this section and the
clerk of the district court of the county in which the right of way is located shall perform any and
all of the duties set forth in this section, if the clerk is directed to do so by the federal court. The
proceedings must be determined as speedily as practicable. An appeal from a judgment in the
condemnation proceedings must be taken within sixty days after the entry of the judgment and
appeal must be given preference by the supreme court over all other civil cases except election
contests. No final judgment in the condemnation proceedings awarding damages to property
used by a district for sewer or other purposes may be vacated or set aside if the district pays to
the defendant, or into court for the defendant, the amount awarded in cash. The district may
levy special assessments within the district to pay all or part of the judgment. To provide funds
for the payment of the judgment or for the deposit of the amount offered for purchase of a right
of way, the district may issue bonds on the fund of the improvement district as provided in
section 61-35-84, in anticipation of the levy and collection of special assessments or revenues
to be appropriated to the fund in accordance with this chapter. The bonds may be issued upon
or after the commencement of the condemnation proceedings. Upon the failure of the district to
make payment in accordance with this section, the judgment in the condemnation proceedings
may be vacated.
61-35-52. Improvement districts to be created.
For an improvement project under section 61-35-48 and defraying the cost of the project by
special assessments, a district may create water districts, sewer districts, and water and sewer
districts, and may extend any such district when necessary. The appropriate special
improvement district must be created by resolution. The district must be designated by a name
appropriate to the type of improvement for which it is created and by a number distinguishing it
from other improvement districts. Nothing in this chapter prevents a district from making and
financing any improvement and levying special assessments for the improvement under any
alternate procedure in this title. For examinations or surveys, the board or its employees, after
written notice to each landowner, may enter upon any land on which the proposed project is
located or any other lands necessary to gain access.
Page No. 17
61-35-53. Size and form of improvement districts - Regulations governing.
Any improvement district created by a district may embrace two or more separate property
areas. Each improvement district must be of such size and form as to include all properties
which in the judgment of the board, after consultation with the engineer planning the
improvement, will be benefited by the construction of the improvement project which is
proposed to be made in or for the district, or by any portion of the project. A single district may
be created for an improvement of the type specified in section 61-35-48, notwithstanding any
lack of uniformity among the types, items, or quantities of work and materials to be used at
particular locations throughout the improvement district. The jurisdiction of a district to make,
finance, and assess the cost of any improvement project may not be impaired by any lack of
commonness, unity, or singleness of the location, purpose, or character of the improvement, or
by the fact that any one or more of the properties included in the improvement district is
subsequently determined not to be benefited by the improvement, or by a particular portion of
the improvement project, and is not assessed for that purpose. The board may omit from a
water or sewer district properties within the district limits which are benefited by the
improvement but do not abut upon a water or sewer main, without prejudice to the right and
power of the district subsequently to assess such properties to the extent and the manner
permitted by law. The board may by resolution enlarge an improvement district in which an
improvement is proposed or under construction upon receipt of a petition signed by the owners
of three-fourths of the area to be added to the district.
61-35-54. Engineer's report required - Contents.
After a special improvement district has been created, the board, if it deems it necessary to
make any of the improvements set out in section 61-35-48 in the manner provided in this
chapter, shall direct the engineer for the district, or some other competent engineer, to prepare a
report as to the general nature, purpose, and feasibility of the proposed improvement. The
engineer shall prepare profiles, plans, and specifications of the proposed project and estimates
of the total cost. The estimate of costs prepared by the engineer must include acquisition of right
of way and must be in sufficient detail to allow the board to determine the probable share of the
total costs that will be assessed against each of the affected landowners in the proposed
assessment district.
61-35-55. Approval of plans, specifications, and estimates.
After receiving the engineer's report required by section 61-35-54, the board may direct the
engineer to prepare detailed plans and specifications for construction of the improvement. The
plans and specifications must be approved by a resolution of the board.
61-35-56. District engineer to retain copy of plans, specifications, and estimates Sale of copies.
The engineer acting for the district shall retain a copy of the plans, specifications, and
estimates that have been prepared for any improvement. The engineer shall furnish copies at
the request of any person at a reasonable cost.
61-35-57. Plans, specifications, and estimates filed in office of district.
The plans, specifications, and estimates prepared as directed under section 61-35-55 are
the property of the district, must be filed in the district office, and must remain on file subject to
inspection by any interested person.
61-35-58. Hearing - Notice - Contents.
Upon the filing of the engineer's report provided for in section 61-35-54, and after satisfying
the requirements of section 61-35-55, the district board shall fix a date and place for public
hearing on the proposed project. The place of hearing must be in the vicinity of the proposed
project and must be convenient and accessible for the majority of the landowners subject to
assessment for the project or whose property is subject to condemnation for the proposed
project. The board shall cause a complete list of the benefits and assessments to be made,
Page No. 18
setting forth each county, township, or city assessed in its corporate capacity as well as each
lot, piece, or parcel of land assessed, the amount each is benefited by the improvement, and
the amount assessed against each. At least ten days before the hearing, the board shall file with
the county auditor of each county in which the project is or will be located the list showing the
percentage assessment and approximate assessment in dollars against each parcel of land
benefited by the proposed project. Notice of the filing must be included in the notice of hearing.
Notices of the hearing must contain a copy of the resolution of the board as well as the time and
place where the board will conduct the hearing. The notice of hearing must specify when and
where votes concerning the proposed project may be filed and contain an assessment list
showing the percentage assessment and approximate assessment in dollars against each
parcel of land benefited by the proposed project. The board shall cause the notice of hearing to
be published once a week for two consecutive weeks in newspapers of general circulation in the
area in which the affected landowners reside and in the official county newspaper of each
county in which the benefited lands are located. The date set for the hearing may not be fewer
than twenty days after the mailing of the notice. A record of the hearing must be made by the
board, including a list of affected landowners present in person or by agent, and the record must
be preserved in the minutes of the meeting. Affected landowners and the governing body of any
county, township, or city to be assessed must be informed at the hearing of the probable total
cost of the project and their individual share of the cost and the portion of their property, if any,
to be condemned for the project.
61-35-59. Voting on proposed projects.
At the hearing, the affected landowners and any county, township, or city to be assessed
must be informed when and where votes concerning the proposed project may be filed. Affected
landowners and the governing body of any county, township, or city to be assessed have thirty
days after the date of the hearing to file their votes with the secretary of the district. Once the
deadline for filing votes has been reached, no more votes may be filed and no person may
withdraw a vote. Any withdrawal of a vote concerning the proposed project before that time must
be in writing. When the votes have been filed and the deadline for filing votes has passed, the
board shall immediately determine whether the project is approved. If the board finds that fifty
percent or more of the total votes filed are against the proposed project, then the vote
constitutes a bar against proceeding further with the project. If the board finds that the number
of votes filed against the proposed project is less than fifty percent of the votes filed, the board
shall issue an order establishing the proposed project and may proceed, after complying with
the requirements of sections 61-35-62 and 61-35-63, to contract or provide for the construction
or maintenance of the project in substantially the manner and according to the forms and
procedure provided in sections 61-35-88 through 61-35-103. The board may enter into any
agreement with any federal or state agency under the terms of which the contract for the project
is to be let by the federal agency, the state agency, or a combination thereof. In projects where
there is an agreement that a party other than the board will let the contract, the board may
dispense with all of the requirements of sections 61-35-88 through 61-35-103. Upon making an
order establishing or denying establishment of a project, the board shall publish notice of the
order in a newspaper of general circulation in the area in which the affected landowners reside
and in the official county newspaper of each county in which the benefited lands are located.
Any right of appeal begins to run on the date of publication of the notice.
61-35-60. Voting right or powers of landowners.
In order that there may be a fair relationship between the amount of liability for assessments
and the power of objecting to the establishment of a proposed project, the voting rights of
affected landowners on the question of establishing the project are as provided in this section.
The landowner of land affected by the project has one vote for each dollar of assessment to
which the land is subject or one vote for each dollar of the assessed valuation of land
condemned for the project, as determined in accordance with title 57. The governing body of
any county, township, or city to be assessed has one vote for each dollar of assessment against
such county, township, or city. There may be only one vote for each dollar of assessment,
regardless of the number of owners of a tract of land. If more than one owner of a tract of land
Page No. 19
exists, the votes must be prorated among them in accordance with each owner's property
interest. A written power of attorney authorizes an agent to protest a project on behalf of any
affected landowner or landowners.
61-35-61. Assessment of cost of project.
When the district board proposes to make any special assessment under this chapter, the
board, prior to the hearing required under section 61-35-58 shall inspect any and all lots and
parcels of land that may be subject to assessment and shall determine from the inspection the
particular lots and parcels of lands which, in the opinion of the board, will be especially benefited
by the construction of the work for which the assessment is made and shall assess the
proportion of the total cost of acquiring right of way and constructing and maintaining such
improvement in accordance with benefits received but not exceeding such benefits, against:
1. Any county, township, or city, in its corporate capacity, which may be directly or
indirectly benefited by the improvement.
2. Any lot, piece, or parcel of land that is directly benefited by the improvement.
In determining benefits, the board shall consider, among other factors, property values, degree
of improvement of properties, and productivity. Property belonging to the United States is
exempt from assessment unless the United States has provided for the payment of any
assessment that may be levied against its property for benefits received. Benefited property
belonging to the state, a county, a city, a school district, a park district, or a township is not
exempt from assessment and political subdivisions that own assessed property shall provide for
the payment of such assessments, including installments and interest, by the levy of taxes
according to law. Any county, township, or city assessed in its corporate capacity for benefits
received shall provide for the payment of those assessments, installments, and interest from its
general fund or by levy of a general property tax against all the taxable property in the political
subdivision in accordance with law. No tax limitation provided by any statute of this state applies
to tax levies made by any political subdivision for paying any special assessments made under
this chapter. There must be attached to the list of assessments a certificate signed by a majority
of the members of the board certifying that it is a true and correct assessment of the benefit
described to the best of their judgment and stating the several items of expense included in the
assessment.
61-35-62. Assessment list to be published - Notice of hearing - Alteration of
assessments - Confirmation of assessment list - Filing.
After entering an order establishing the project, the district board shall cause the
assessment list to be published once each week for two successive weeks in the newspapers of
general circulation in the district and in the official county newspaper of each county in which the
benefited lands are located. The publication must include a notice of the time and place the
board will meet to hear objections to any assessment by any interested party, or an agent or
attorney for that party. The date set for the hearing must be not less than twenty days after the
first publication of the notice. At the hearing, the board may make such alterations in the
assessments as in its opinion may be just and necessary to correct any error in the assessment
but must make the aggregate of all assessments equal to the total amount required to pay the
entire cost of the work for which the assessments are made or the part of the cost to be paid by
special assessment. An assessment may not exceed the benefit as determined by the board to
the parcel of land or political subdivision assessed. The board shall then confirm the
assessment list and the secretary shall attach to the list a certificate that it is correct as
confirmed by the board. The secretary shall file the list in the office of the district secretary.
61-35-63. Appeal to state engineer.
Within ten days after the hearing under section 61-35-62, affected landowners and any
political subdivision subject to assessment, having not less than twenty-five percent of the
possible votes as determined under section 61-35-60, who believe that the assessment has not
been fairly or equitably made, or that the project is not properly located or designed, may appeal
to the state engineer by petition, to review the assessments and examine the location and
Page No. 20
design of the proposed project. Upon receipt of a petition, the state engineer shall examine the
lands assessed and the location and design of the proposed project, and if it appears that the
assessments have not been made equitably, the state engineer may proceed to correct the
assessments, and the state engineer's correction and adjustment of assessments is final. If it
appears to the state engineer that the project has been improperly located or designed, the
state engineer may order a relocation and redesign, which must be followed in the construction
of the proposed project. Upon filing a bond for two hundred fifty dollars with the board for the
payment of the costs of the state engineer in the matter, any landowner or political subdivision
claiming to receive no benefit from the project may appeal to the state engineer the question of
whether there is any benefit. The appeal must be filed with the state engineer within ten days
after the hearing on assessments in section 61-35-62. The state engineer may not determine
the specific amount of benefit upon an appeal by an individual landowner or political subdivision
and may determine only if there is any benefit to the landowner or political subdivision. The
determination of the state engineer upon the appeal is final.
61-35-64. When assessments may be made.
After the requirements of this chapter have been satisfied and a contract and bond for any
work for which a special assessment is to be levied have been approved by the district board,
the board may direct special assessments to be levied for the payment of appropriate costs and
the secretary shall certify to the board the items of total cost to be paid by special assessments
so far as they have been ascertained. The certificate must include the estimated construction
cost under the terms of any contract, a reasonable allowance for cost of extra work that may be
authorized under the plans and specifications, acquisition of right of way, engineering, fiscal
agents' and attorney's fees for any services in connection with the authorization and financing of
the improvement, cost of publication of required notices, printing of improvement bonds, cost
necessarily paid for damages caused by such improvement, interest during the construction
period, and all expenses incurred in making the improvement and levy of assessments.
A contract or contracts may not be awarded which exceed, by forty percent or more, the
estimated cost of the project as presented to and approved by the affected landowners.
61-35-65. Reassessment of benefits.
The district board may hold at any time or, upon petition of any affected landowner or
political subdivision which has been assessed after a project has been in existence for at least
one year, shall hold a hearing for the purpose of determining the benefits of the project to each
tract of land affected. At least ten days' notice of the hearing must be given by publication in the
newspaper or newspapers having general circulation in the district and in the official county
newspaper of each county in which the benefited lands are located and by mailing notice by
ordinary mail to each owner of land whose assessment is proposed to be raised as determined
by the records of the recorder or county treasurer. The provisions of this chapter governing the
original determination of benefits and assessment of costs apply to any reassessment of
benefits carried out under this section. The board may not be forced to make a reassessment
more than once every ten years. Any assessment or balance of an assessment supporting a
project fund may not be reduced or impaired by reassessment or otherwise so long as bonds
payable out of such fund remain unpaid and moneys are not available in such fund to pay all
such bonds in full, with interest. Costs of maintenance must be prorated in accordance with any
plan for reassessment of benefits that has been adopted.
61-35-66. Correction of errors and mistakes in special assessments - Requirements
governing.
If mathematical errors or other mistakes occur in making any assessment resulting in a
deficiency in that assessment, the district board shall cause additional assessments to be made
in a manner substantially complying with chapter 40-26 as it relates to special assessments.
Page No. 21
61-35-67. Lien of special assessment.
A special assessment imposed by a district, with accrued interest and penalties, is a lien
upon the property on which the assessment is levied from the time the assessment list is
approved by the district board until the assessment is fully paid. The liens have precedence
over all other liens except general tax liens and may not be divested by any judicial sale.
Mistake in the description of the property covered by the special assessment lien or in the name
of the owner of such property does not defeat the lien if the assessed property can be identified
by the description in the assessment list. This chapter must be considered notice to all
subsequent encumbrances of the priority of special assessments imposed under this chapter.
61-35-68. Sewer or water improvements in districts may be paid for by service
charges.
A district constructing a sewer or water improvement under the special assessment method
may resolve in the resolution or ordinance required by section 61-35-52, that a portion of the
cost of the improvement must be raised by service charges for the use of the improvement and
of the utility of which it forms a part. If the district so resolves, it may determine in its resolutions,
ordinances, and other proceedings relating to the levying of special assessments and the
issuing of bonds to pay the cost of such improvement, that a specified portion or all of such cost
must be assessed specially against any property specially benefited and may cause to be
assessed only the portion so determined. In that event the entire remainder of the cost,
including interest as well as principal of any bonds issued, over and above the amount of
special assessments actually collected and received from time to time in the fund of the
improvement district, must be paid from the net revenues derived from the service charges. All
of the applicable provisions of this chapter relating to special assessments are applicable to
such improvements except as to the portion of the cost of improvements resolved or ordained to
be paid by service charges. The board of the district shall provide for the establishment,
imposition, and collection of service charges for the services furnished by the improvement and
the utility of which it forms a part, and in that connection it has all the rights and powers
respecting such service charges as it would have with respect to like matters if the improvement
were made in accordance with chapter 40-35. The net revenues derived from the imposition and
collection of the service charges or any portion of the service charges as are determined by the
board in the resolutions and ordinances must be paid into the appropriate improvement district
funds created under section 61-35-83. The revenues when collected must be used and applied
in the same manner as moneys paid into such funds from the collection of special assessments.
The board of any district issuing bonds to finance any such improvement, in its resolutions and
ordinances, may establish an assessment reserve in the fund of the improvement district, to
which it may appropriate net revenues of the utility or system from time to time received in
excess of amounts required, with special assessments then on hand, to meet the principal and
interest next due on the bonds. Before November first of any year the district may by resolution
determine the proportion which the amount then on hand in the assessment reserve, and
irrevocably appropriated to the payment of the bond, bears to the aggregate amount of the
installment of the special assessments levied for the improvement which is payable in the
following year, including interest. The district may direct the auditor to reduce, by not more than
a proportionate amount, the total of that installment and interest which would otherwise be
placed upon the tax list of the district for the current year, against each lot and tract of land
assessed or taxed for improvement. If the installment of the special assessment on any property
has been prepaid, the board may direct the district to refund, out of the assessment reserve, to
the owner of the property at the time of the refund as indicated in the records of the recorder of
the county, a sum not exceeding a similar proportion of the principal amount of such installment,
excluding interest.
61-35-69. Abbreviations, letters, or figures may be used in proceedings for levy and
collection of special assessments.
In all proceedings for the levy and collection of special assessments, abbreviations, letters,
and figures may be used to denote all or parts of additions, lots, lands, blocks, sections,
townships, ranges, years, days of the month, and amounts of money.
Page No. 22
61-35-70. District office to keep complete record of improvements - Record as
evidence.
The district office shall keep a complete record of all the proceedings taken in the matter of
making any improvements under this chapter. The record must include all reports and
confirmations, all petitions, orders, notices and proofs of publication, and resolutions of the
board. The record, a certified transcript of the record, or the original papers, proofs of
publications, orders, or resolutions on file in the office must be admitted in evidence in any court
or place in this state without further proof as evidence of the facts in those documents.
61-35-71. Defects and irregularities in improvement proceedings are not fatal.
Defects and irregularities in any proceedings had or to be had under this chapter relating to
district improvements by the special assessment method, if the proceedings are for a lawful
purpose and are unaffected by fraud and do not violate any constitutional limitation or
restriction, do not invalidate the proceedings, and no action may be commenced or maintained
and no defense or counterclaim in any action may be recognized in the courts of this state
founded on any such defects or irregularities in the proceedings, unless commenced within
thirty days of the adoption of the resolution of the board awarding the sale of bonds to finance
the improvement.
61-35-72. Payment of special assessments - Interest.
All special assessments levied under this title may be paid without interest within ten days
after they have been approved by the board and thereafter bear interest at an annual rate not
exceeding one and one-half percentage points above the average net annual interest rate on
any bonds for the payment of which they are pledged on the total amount remaining unpaid.
61-35-73. Lien between vendor and vendee of special assessments.
As between a vendor and vendee of real property, unless the purchase contract otherwise
provides, the installments of all special assessments for local improvements which are required
to be certified and returned to the county auditor in each year become a lien upon the real
property upon which they are assessed from and after the first day of December in that year.
61-35-74. Sewer special assessments extended over a period of not more than thirty
years.
Special assessments for the payment of the cost of constructing any sewer are payable in
equal annual amounts, or in such annual amounts as will permit the annual increase in payment
of principal to approximate the annual decrease in the interest on amounts remaining unpaid,
extending over a period of not exceeding thirty years as the board may fix by ordinance or
resolution.
61-35-75. Water main and waterworks special assessments extended over a period of
not more than thirty years.
Special assessments for the payment of the cost of constructing or laying any water mains
or constructing any waterworks are payable in equal annual amounts, or in such annual
amounts as will permit the annual increase in payment of principal to approximate the annual
decrease in the interest on amounts remaining unpaid, extending over a period of not more than
thirty years as the board may fix by ordinance or resolution.
61-35-76. Payments in full of assessments - Payments to county treasurer or district
treasurer - Receipts.
The owner of any property against which an assessment has been made under this title for
the cost of any improvement may pay in full or in part the amount remaining unpaid and the
unpaid accumulated interest. The payment in full discharges the lien of the assessment upon
that property. The payment may be made to the county treasurer upon all installments of the
assessments which have been certified to the county auditor, and may be made to the district
treasurer upon all portions of the assessment which have not been certified. Any person
Page No. 23
desiring to pay any portion of the assessment to the district treasurer shall obtain from the
district treasurer a certificate of the amount due upon the assessment which has not been
certified to the county auditor and shall present the certificate to the district treasurer. The
district treasurer shall receive and collect that amount and issue a receipt to the person paying
the assessment. The district treasurer shall note upon the treasurer's records the payment of
the assessment.
61-35-77. Certification of assessments to county auditor.
When a district board, by resolution, has caused special assessments to be levied to cover
the cost of constructing a project, the board shall determine the rate of interest unpaid special
assessments are to bear, which rate may not exceed one and one-half percent above the bond
rate. Interest on unpaid special assessments commences on the date the assessments are
finally confirmed by the board. Special assessments may be certified and made payable in
equal annual installments, the last of which must be due and payable not more than thirty years
after date of the bonds to be paid. The secretary of the district shall certify to the county auditor
of the county in which the district is situated, or if the district embraces more than one county, to
the county auditor of each county in which district lands subject to such special assessments
are situated, the total amount assessed against each piece, parcel, lot, or tract of land. The
secretary of the district shall also file with the county auditor of each county in which district
lands lie a statement showing the cost of the project and the part of the project to be financed by
special assessments. Funds needed to pay the cost of maintaining a project may be raised in
the same manner as funds were raised to meet construction costs. If the project was financed in
whole or in part through the use of special assessments, the district board shall prorate the cost
of construction or, if a reassessment of benefits has been adopted, the costs must be prorated
in accordance with the reassessment of benefits as authorized by section 61-35-65. The district
treasurer shall annually certify to the county auditor all uncertified installments of assessments
which are to be extended upon the tax lists of the district for the current year, in the manner
provided in this section. The annual certification must continue until the amount of moneys on
deposit in the fund established under section 61-35-83 is sufficient to cover outstanding
principal of and interest on any obligations issued to fund the projects, and in addition, to repay
the district for any payments made by the district to fund deficiencies in the fund established
under section 61-35-83.
61-35-78. District treasurer to insert amount of improvements in county real estate
book or other forms - Regulations governing.
The district treasurer shall notify the county auditor not later than August twentieth in each
year of any special assessments that were made in the district in addition to those reported in
the previous year. The county auditor shall make and deliver to the district treasurer on or
before September twentieth each year a copy of the real estate assessment book or other forms
for the current year covering all additions in which any special assessments have existed and
where any will appear for the current year as advised by the district treasurer. The district
treasurer shall insert in the proper columns under the appropriate headings the amount of each
of the installments of the assessments on the lots or subdivisions of lots or tracts of land which
are to be extended upon the tax lists of the district for the current year. The district treasurer
shall show the total amount of special assessments certified to the county auditor for the current
year. If a division of property has been made since the original assessment, the district treasurer
shall make or cause to be made the proper division of the special assessments on the lots or
tracts of land in the same manner as general taxes are divided and assessed as furnished by
the county auditor. The district treasurer shall certify the special assessments to the county
auditor by November first of each year.
61-35-79. Extension of special assessments on tax lists - Collection - Payment over to
district.
The county auditor shall extend the special assessments upon the tax lists of the district for
the current year and the assessments with interest and penalties must be collected as general
Page No. 24
taxes are collected and paid over to the district treasurer and shall be placed by the district
treasurer in the respective funds for which they were collected.
61-35-80. Special assessment record book kept by county auditor - Assessments
certified for more than one year.
The county auditor shall keep a special assessment record. When any district causes the
installments of special assessments for a period of more than one year to be certified, the
county auditor shall cause the certified special assessments to be recorded for the respective
years and in the amounts shown in the certificate of the district treasurer. The certificate of the
district treasurer must include a list of all lots and tracts of land upon which such assessments
are levied, designating the purpose of the assessment, the fund to which it belongs, and the
installment of such assessment for each year against each lot or tract, including interest.
61-35-81. County treasurer to certify and receipt for amount of special assessments
collected - Contents of certificate - Procedure for abatement.
Special assessments of any kind certified to the county auditor by the district treasurer must
be paid to the county treasurer and included in the receipt required by section 57-20-08. If the
county treasurer receives less than the full amount of taxes and special assessments due at any
time on any lot or tract of real estate, the county treasurer shall allocate the amount of such
payment between taxes and special assessments in proportion to the respective amounts of
taxes and special assessments which are then due. When prorating any tax payment received
before October fifteenth, the term "due", as it pertains to real estate taxes, includes only the first
installment of real estate taxes. Special assessments are not subject to abatement or refund by
proceedings under chapter 57-32 but may be reviewed and corrected only in the manner and
upon the conditions provided in chapter 40-26. The county treasurer, at the time set by law for
the payment to the district treasurer of all the taxes and special assessments collected during
the preceding month, shall certify the amounts of special assessments collected. The certificate
must state specifically the lot or known subdivision as it appears on the tax books of the county
treasurer, and the block, addition, amount collected, and amount credited to each lot or known
subdivision, and the year for which the sum was collected. The certificate must be furnished to
the district treasurer.
61-35-82. Interest and penalties added to special assessments - County treasurer to
collect and pay over.
The county treasurer shall add to all special assessments the same interest and penalties
that are added in the case of general taxes and at the same time. The county treasurer shall
collect the interest and penalties with the special assessments and shall pay all such interest
and penalties collected over to the district treasurer.
61-35-83. Special improvement moneys to be kept separate - Designation and
numbering of funds - Diversion of moneys prohibited.
All special assessments and taxes levied and other revenues pledged under the provisions
of this chapter to pay the cost of an improvement constitute a fund for the payment of that cost,
including all principal of and interest on bonds and other obligations issued by the district to
finance the improvement, and may be diverted to no other purpose. The district treasurer shall
hold all moneys received for any such fund as a special fund to be applied to payment for the
improvement. Each fund must be designated by the name and number of the improvement
district in or for which the special assessments, taxes, and revenues are collected. When all
principal and interest on bonds and other obligations of the fund have been fully paid, all
moneys remaining in a fund may be transferred into the general fund of the district.
61-35-84. Bonds - When payable - Amounts - Interest.
At any time after entering into a contract for a project to be financed in whole or in part by
special assessments, a district may issue temporary and definitive bonds on the project fund,
created for that purpose, in the manner and subject to the limitations prescribed in section
Page No. 25
40-24-19. If the bonds are issued to finance a sewer or water project, the net revenues derived
from the imposition of service charges to be imposed and collected with respect to the project
as provided in section 61-35-68 may be pledged to payment of those bonds, except that the first
maturity date of any such bond may not be less than two years from the date of issuance.
Bonds issued under this section must be in amounts as in the judgment of the board will be
necessary for the project. The bonds must bear interest at a rate or rates and be sold at a price
resulting in an average net interest cost not exceeding twelve percent per annum if sold at
private sale. There is no interest rate ceiling on bond issues sold at public sale or to the state or
any of its agencies or instrumentalities. The bonds must state upon their face the purpose for
which they are issued and the project fund from which they are payable and must be signed by
the chairman of the board and countersigned by the secretary of the district. The bonds must be
payable serially in such amounts as the board determines, extending over a period of not more
than thirty years.
61-35-85. Bonds may be used in making payments on contract - Bonds payable out of
fund on which drawn - May be used to pay special assessments.
Improvement bonds may be used in making payments on contracts for construction of the
project for which the special assessment fund was created, or may be sold for cash at not less
than ninety-eight percent of par and accrued interest, and the proceeds, less accrued interest,
must be credited to the construction account of the fund and must be used exclusively to pay
those contracts and construction costs. Any balance remaining in any construction account after
completion of any project must be transferred to the sinking fund account of the assessment
fund. The treasurer of the district shall pay special assessment bonds as they mature and are
presented for payment out of the fund on which they are drawn and shall cancel the bonds
when paid.
61-35-86. Refunding special assessment bonds - Purposes for which such bonds
may be issued - Payment of bonds.
Any district having outstanding special assessment bonds, payable in whole or in part out of
collections from special assessments, which are past due or which are redeemable, either at the
option of the district or with the consent of the bondholders, may issue refunding special
assessment bonds if there is not sufficient money in the project fund against which such bonds
are drawn to pay the same. The issuance of refunding bonds must be authorized by resolution
of the district board. The resolution must describe the bonds to be refunded and their amount
and maturity. Refunding bonds may be issued for any of the following purposes:
1. To extend the maturities of bonds payable in whole or in part by special assessments.
2. To reduce the interest on the bonds.
Refunding bonds must bear such date, be in such date, be in such denominations, and
mature serially within such time, not exceeding thirty years from date of issuance, as the board
determines. The average rate of interest on the bonds may not exceed the average rate of
interest on refunded bonds.
The treasurer of the district shall pay special assessment bonds as they mature and are
presented for payment out of the fund against which they are drawn and shall cancel the bonds
when paid. Any deficiency in any fund created for the payment of district bonds payable in whole
or in part out of collections of special assessment taxes must be the general obligation of the
district.
61-35-87. Foreclosure of tax lien on property when general and special assessment
taxes are delinquent.
Special assessments imposed under this chapter become due and delinquent and are
subject to penalties for nonpayment at the same date and rates as first installments of real
estate taxes at the same time and in the same manner as provided in title 57.
If there is no delinquent general property tax against a tract or parcel of land and it is
foreclosed for special assessments alone, the notice of foreclosure of tax lien must state that
Page No. 26
the foreclosure is for special assessments and a tax deed in such case must be issued in the
usual course of procedure.
61-35-88. Call for bids - Contents - Advertising.
Proposals for the work of making improvements provided for in this chapter that exceed the
amount provided for construction of a public improvement under section 48-01.2-02 must be
advertised for by the board in the official newspaper of the county where the district office is
located once each week for two consecutive weeks. The board may cause the work on two or
more improvements to be combined in one advertisement and one contract awarded pursuant
to that advertisement. The advertisement for bids must:
1. Specify the work to be done according to the plans and specifications on file in the
office of the district;
2. Call for bids upon the basis of cash payment for the work;
3. State the time within which the bids will be received; and
4. State the time within which the work on the improvement is to be completed.
The board may require bidders to state also the rate of interest, not exceeding seven percent
per annum, which the bonds to be received and accepted by the bidder at par in payment for
the work are to bear.
61-35-89. Bid to be accompanied by a bond - Bond retained upon failure of bidder to
contract - Amount of bond.
Each bid for any work to be done under this chapter must be accompanied by a separate
envelope containing a bidder's bond in the amount of five percent of the amount of the bid,
executed as provided in this chapter and running to the district that the bidder will enter into a
contract for performance of the work in case a contract is awarded to the bidder. If any bidder to
whom a contract is awarded fails or refuses to enter into the contract when requested to do so,
the bond accompanying the bidder's bid must be retained by the district as liquidated damages
for the failure. The bond must be delivered to the district office and credited to the fund from
which the consideration for the work is payable. The sufficiency of any bond filed by a bidder
must be determined by the board at the time of considering bids.
61-35-90. Execution of bidder's bond.
The bidder's bond must be executed by the bidder as principal and may be provided by a
surety company authorized to do business in this state as surety or by a bank letter of credit, a
cash bond, or a certified check.
61-35-91. Conditions of bidder's bond.
A bidder's bond must be made payable to the district and conditioned that if the principal's
bid is accepted and the contract for the work of improvement awarded to the bidder, the bidder,
within ten days after the acceptance of the bid, or within such further time as the board grants,
will enter into and execute a contract bond in a sum equal to the amount of the bid, and a
contract in writing to and with the district well and faithfully to perform and complete the work for
which the bid was accepted, in accordance with the plans and specifications and the terms of
the bid and within the time required by the terms of the contract, and that the bidder will pay for
all the labor and materials used in such work. The bond must be for the benefit of the district.
61-35-92. Bids - Filing - Sealing - Endorsing - Opening - Considering.
Bids for the work to be let under this chapter must be forwarded to the district office and
must be sealed securely to prevent opening without detection. There must be endorsed upon
the outside of the envelope containing the bid a statement of what work the proposal is for. The
bids must be opened by the board at the expiration of the time limited in the advertisement for
receiving the same, which may not be less than fifteen days after the first publication of the
advertisement, or at such other time as the board may appoint. Only bids that are accompanied
by the bond provided for in section 61-35-89 may be considered by the board.
Page No. 27
61-35-93. Opening of bids - Bids to be entered on minutes.
After the bids have been opened and made public, they must be entered upon the minutes
of the meeting of the board of the district at which they are considered, and they must be
preserved carefully by the district secretary.
61-35-94. Rejection of bids - Readvertising for bids or construction by district without
contract - Reevaluation of project.
If in its opinion the best interests of the district require, the board may reject any and all bids
filed under this chapter. If all bids are rejected, the board may:
1. Readvertise for new bids;
2. Cause the work described in the plans, specifications, and estimates to be done
directly by the district by the employment of labor and the purchase of materials
required, or in any other manner the board considers proper, and payment for the work
may be provided through special assessments in the same manner as though the
work had been performed under contract, provided this work amounts to no more than
the amount provided for construction of a public improvement under section
48-01.2-02; or
3. Cause the work described in the plans, specifications, and estimates to be reviewed
and reevaluated by the engineer for the district so that the board may determine
whether the entire project or only a portion of the project is feasible.
61-35-95. Engineer's statement of estimated cost required - Board to enter into
contracts.
Before adopting or rejecting any bid filed under this chapter, the board shall require the
engineer for the district to make a careful and detailed statement of the estimated cost of the
work. The board may not award the contract to any bidder if the engineer's estimate prepared
under this section exceeds the engineer's estimate prepared under section 61-35-54 by forty
percent or more. If all bids are not rejected, the board shall award the contract to the lowest
responsible bidder, upon the basis of cash payment for the work, if the bidder has furnished the
certified check or bidder's bond required under the provisions of this chapter.
61-35-96. Contractor's bond - Execution.
Within the time fixed by the board for executing the contract, the successful bidder shall file
with the district a contract bond in a sum equal to the full amount of the contract. The bond must
be executed by the bidder or contractor as principal and by a surety company authorized to do
business in this state as surety.
61-35-97. Conditions for contractor's bond.
The contractor's bond must be made payable to the district and must be conditioned:
1. That the contractor well and faithfully will perform the work bid for in accordance with
the terms of and within the time provided for in the contract, and pursuant to the plans
and specifications for the work on file in the district office;
2. That the contractor will pay for all labor and material used in that work; and
3. That in case of a default on the part of the bidder or contractor in the performance of
the work as provided in the contract, the sum named in the bond must be taken and
held to cover the amount necessary to compensate the district for the correction,
repair, or replacement caused by the default, and that the full amount may be
recovered from the bidder and the bidder's sureties in an action by the district against
them on the bond only in the event of a complete failure of performance on the part of
the contractor. Nothing in this section may be construed to prevent the district from
receiving the amount, not in excess of the amount of the bond, necessary to
compensate the district for correction, repair, or replacement caused by default of the
contractor which does not constitute complete failure of performance by the contractor.
Page No. 28
61-35-98. Approval of bonds - Return of bidder's bond.
The contractor's bond must be approved by the governing body, and thereupon it is and
remains in full force and effect. Upon the execution of the contract and the approval of the
contract bond, the bidder's bond must be returned.
61-35-99. Failure to execute contractor's bond.
If the successful bidder, within ten days after the acceptance of the bid or such further time
as the board may grant, does not execute a contractor's bond and a contract for the completion
of the work described in the bid, the board may cause the work to be done, or it may contract
with some other contractor to do or complete the work. In that case, the district may recover in a
suit on the defaulting bidder's bond the difference between the actual cost to the district of the
improvements and the sum that it would have cost if the defaulting bidder had complied with the
bidder's bid.
61-35-100. Insufficiency of bonds - New bonds required - Failure to furnish.
If the board, at any time, deems the bond of a contractor insufficient either in form or as to
sureties, it may require the successful bidder or contractor to furnish, within such reasonable
time as the board may fix, a new bond to be approved by the board. If the contractor fails, after
notice, to furnish the new bond within the time required, the contractor's contract may be
canceled, and in that event the contractor's bond will be liable as if the contractor had failed to
perform the contract.
61-35-101. Execution and filing of contract.
All contracts entered into for any work provided for in this chapter must be entered into in
the name of the district and must be executed on the part of the district by the president and
countersigned by the secretary. After the contract is signed by the contractor, it must be filed in
the office of the district.
61-35-102. Conditions and terms.
A contract let under this chapter requires the work to be done pursuant to the plans and
specifications on file in the office of the district, subject to the approval of the engineer acting for
the district, and must provide:
1. That the board has the right to suspend the work at any time for improper construction
and to relet the contract or to order a reconstruction of the work as to any part
improperly done.
2. The time within which the work must be completed.
3. The period of time for which the work must be guaranteed as to workmanship and
materials.
4. The fund from which the contract price is to be paid by the district.
5. That the consideration expressed in the contract is payable only in bonds drawn on the
fund described in the contract.
6. That the district assumes and incurs no general liability under the contract.
7. That failure of the engineer to reject work and materials that are not up to
specifications and acceptance of the job by the engineer does not release the
contractor from liability for any failure on the contractor's part to perform work or
furnish materials in accordance with the plans and specifications.
The engineer acting for the district shall provide construction administration and observation of
the work during its progress. In addition to any rights a district may have under its contract for
construction of part or all of an improvement after a contract has been awarded and before work
under the contract has been completed, a district, with the consent of the contractor and without
advertising for bids, may order additional work done by that contractor of the same character as
the work that was contracted for, whether within or without the improvement district for which the
original contract was made, and upon the same terms and conditions specified in the original
contract except as to time of performance, and at the same prices for the additional work;
provided, that the total price payable to the contractor for the additional work may not exceed
Page No. 29
twenty percent of the amount estimated by the engineer for the district to be payable for that
character of work under the original contract.
61-35-103. Contractor to be paid during progress of work - Retainage - Failure to pay Rate of interest - Investment of retainage.
If the contractor to whom a contract is let properly performs the work designated in the
contract, the board, at least once in each calendar month during the continuance of the contract
work, shall meet and receive and consider estimates furnished by the agent, engineer, or
architect acting for the district or if not so furnished, then by the contractor, and shall allow such
estimates in an amount of the estimated value of the labor and material furnished upon the
contract, and of the material then upon the ground for use in the contract, subject to retentions
as follows: ten percent of each estimate presented until such time as the project is fifty percent
completed, with no further retainage on estimates during the continuance of the contract. Upon
completion of ninety-five percent of the contract according to the estimates, the board may pay
to the contractor ninety-five percent of the amount retained from previous estimates. Any
amount retained after ninety-five percent completion of the contract must be paid to the
contractor in such amounts and at such times as are approved by the district, upon estimates by
its agent, engineer, or architect or the contractor, with final payment of all moneys due to the
contractor to be made immediately following completion and acceptance of the project.
Immediately after considering and allowing any such estimate, the board shall certify and
forward the same to the district treasurer or other official having the power to draw bonds, who
forthwith shall draw a warrant upon the proper fund and transmit the same promptly to the
contractor. If the board fails or neglects to receive and allow such estimate or certify any
estimate or final payment upon completion and acceptance or the proper officer required to
issue such warrant fails or neglects to issue a warrant as provided in this section, for a period of
more than thirty days from the date of such estimate or completion date, then the estimate or
final payment, together with any retainage properly payable, draws interest from its date at the
rate per annum of two percentage points below the Bank of North Dakota prime interest rate as
set thirty days from the date of such estimate or completion date until the issuance of a proper
warrant. Interest must be computed and added to the face of the estimate, final payment, or
retainage by the officer required to issue the warrant, must be included in the warrant when
drawn, and must be charged to the fund from which payment for the improvement is to be
made. On the amounts of estimates retained, as provided in this section, the board, authorized
committee, or public body in charge of the work may invest or deposit the retained amounts in
any financial association or institution in this state earning interest or dividends for the benefit of
the contractor. Any amounts so invested or deposited must remain in the name of the board,
authorized committee, or public body in charge of the work until final payment of all money due
to the contractor is to be made. Further, a contractor may not use or pledge such amount in any
manner until released and received by the contractor upon completion of the contract.
Page No. 30
Disclaimer: These codes may not be the most recent version. North Dakota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.