2013 Maryland Code
STATE FINANCE AND PROCUREMENT
§ 17-110 - Retention of percentage of total amount of contract as security [Effective until July 1, 2013].


MD State Fin & Pro Code § 17-110 (2013) What's This?

§17-110.

(a) Subsections (b)(1), (2), and (3), (c), and (d) of this section do not apply to an entity that is required to comply with the provisions of § 13-225 of this article.

(b) (1) If a contractor has furnished 100% payment security and 100% performance security in accordance with this subtitle under a contract for construction awarded by a public body, the percentage specified in the contract for retainage may not exceed 10% of the total amount for the first 50% of the contract.

(2) Unless a public body demonstrates the need to retain more than 5% to protect the public interest, after 50% of the contract is completed, a public body may retain only 5% of the total amount.

(3) In addition to retainage, a public body may withhold from payments otherwise due a contractor any amount that the public body reasonably believes necessary to protect the public body’s interest.

(4) Except as provided in paragraph (5) of this subsection, within 120 days after satisfactory completion of a contract for construction, a public body shall release any retainage due to the contractor.

(5) If there is a dispute or contract claim between the contractor and the public body concerning the satisfactory completion of a contract for construction, the public body shall release the retainage to the contractor within 120 days after the resolution of the dispute or contract claim.

(c) (1) A contractor may not retain a percentage of payments due a subcontractor that exceeds the percentage of payments retained by the public body.

(2) Paragraph (1) of this subsection may not be construed to prohibit a contractor from withholding any amount in addition to retainage if the contractor determines that a subcontractor’s performance under the subcontract provides reasonable grounds for withholding the additional amount.

(d) (1) A subcontractor may not retain a percentage of payments due a lower tier subcontractor that exceeds the percentage of payments retained from the subcontractor.

(2) Paragraph (1) of this subsection may not be construed to prohibit a subcontractor from withholding any amount in addition to retainage if the subcontractor determines that a lower tier subcontractor’s performance under the subcontract provides reasonable grounds for withholding the additional amount.

(e) This section may not be construed to limit the application of the remaining provisions of this subtitle.

§ 17-110 - Retention of percentage of total amount of contract as security [Effective July 1, 2013].

(a) Applicability of subsections (b)(1) through (3), (c) and (d). -- Subsections (b)(1) and (2), (c), and (d) of this section do not apply to an entity that is required to comply with the provisions of § 13-225 of this article.

(b) In general. --

(1) If a contractor has furnished 100% payment security and 100% performance security in accordance with this subtitle under a contract for construction awarded by a public body, the percentage specified in the contract for retainage may not exceed 5% of the total amount of the contract.

(2) In addition to retainage, a public body may withhold from payments otherwise due a contractor any amount that the public body reasonably believes necessary to protect the public body's interest.

(3) Except as provided in paragraph (4) of this subsection, within 120 days after satisfactory completion of a contract for construction, a public body shall release any retainage due to the contractor.

(4) If there is a dispute or contract claim between the contractor and the public body concerning the satisfactory completion of a contract for construction, the public body shall release the retainage to the contractor within 120 days after the resolution of the dispute or contract claim.

(c) Retention of payments due a subcontrator. --

(1) A contractor may not retain a percentage of payments due a subcontractor that exceeds the percentage of payments retained by the public body.

(2) Paragraph (1) of this subsection may not be construed to prohibit a contractor from withholding any amount in addition to retainage if the contractor determines that a subcontractor's performance under the subcontract provides reasonable grounds for withholding the additional amount.

(d) Retention of payments due a lower tier subcontractor. --

(1) A subcontractor may not retain a percentage of payments due a lower tier subcontractor that exceeds the percentage of payments retained from the subcontractor.

(2) Paragraph (1) of this subsection may not be construed to prohibit a subcontractor from withholding any amount in addition to retainage if the subcontractor determines that a lower tier subcontractor's performance under the subcontract provides reasonable grounds for withholding the additional amount.

(e) Construction. -- This section may not be construed to limit the application of the remaining provisions of this subtitle.

Disclaimer: These codes may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.