2009 Maine Code
TITLE 35-A: PUBLIC UTILITIES (HEADING: PL 1987, c. 141, Pt. A, @6 (new))
Chapter 43: NUCLEAR POWER GENERATING FACILITIES
35-A §4303. Notice; effective date of certificate; prohibition
Title 35-A: PUBLIC UTILITIES HEADING: PL 1987, C. 141, PT. A, §6 (NEW)
Part 3: ELECTRIC POWER HEADING: PL 1987, C. 141, PT. A, §6 (NEW)
Chapter 43: NUCLEAR POWER GENERATING FACILITIES HEADING: PL 1987, C. 141, PT. A, §6 (NEW)
Subchapter 1: CONSTRUCTION HEADING: PL 1987, C. 141, PT. A, §6 (NEW)
§4303. Notice; effective date of certificate; prohibition
Construction may not commence on a nuclear power plant without approval by the voters, as prescribed in section 4302. [1999, c. 398, Pt. A, §§104, 105 (AFF); 1999, c. 398, Pt. A, §96 (AMD).]
SECTION HISTORY
1987, c. 141, §A6 (NEW). 1999, c. 398, §§A104,105 (AFF). 1999, c. 398, §A96 (AMD).
Disclaimer: These codes may not be the most recent version. Maine may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.