2009 Maine Code
TITLE 35-A: PUBLIC UTILITIES (HEADING: PL 1987, c. 141, Pt. A, @6 (new))
Chapter 34-A: EXPEDITED PERMITTING OF GRID-SCALE WIND ENERGY DEVELOPMENT
35-A §3455. Determination of public safety-related setbacks

Title 35-A: PUBLIC UTILITIES HEADING: PL 1987, C. 141, PT. A, §6 (NEW)

Part 3: ELECTRIC POWER HEADING: PL 1987, C. 141, PT. A, §6 (NEW)

Chapter 34-A: EXPEDITED PERMITTING OF GRID-SCALE WIND ENERGY DEVELOPMENT

§3455. Determination of public safety-related setbacks

In making findings pursuant to Title 12, section 685-B, subsection 4 or Title 38, section 484, subsection 3 on whether a wind energy development must be constructed with setbacks adequate to protect public safety, the primary siting authority must consider the recommendation of a professional, licensed civil engineer as well as any applicable setback recommended by a manufacturer of the generating facilities. The primary siting authority may require submission of this information as part of the application. [2007, c. 661, Pt. A, §7 (NEW).]

SECTION HISTORY

2007, c. 661, Pt. A, §7 (NEW).

Disclaimer: These codes may not be the most recent version. Maine may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.