Sec. 16-19qq. Outages of nuclear power generating facilities; rate proceedings; rebuttable presumption of imprudent management.

      Sec. 16-19qq. Outages of nuclear power generating facilities; rate proceedings; rebuttable presumption of imprudent management. On or after July 1, 1997, in any proceeding held by the Department of Public Utility Control in which the department considers the principles set forth in subdivision (5) of subsection (a) of section 16-19e concerning an outage of a nuclear power generating facility, there shall be a rebuttable presumption that any costs associated with the outage were incurred as a result of imprudent management of the facility if (1) the outage was ordered by, or prolonged by order of, the United States Nuclear Regulatory Commission, and (2) the order applied only to a facility or facilities in the state.

      (P.A. 97-21, S. 1, 2.)

      History: P.A. 97-21 effective July 1, 1997.

Disclaimer: These codes may not be the most recent version. Connecticut may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.