2005 Arizona Revised Statutes - Revised Statutes §49-290  Exemption from permit requirements; definition

A. Notwithstanding any other statute, a person who performs a remedial action or a portion of a remedial action that has been approved by the department if that action or portion is conducted in compliance with this article is not subject to any requirement to obtain any permit or approval that may otherwise be required by the department.

B. Except as prescribed in subsection D of this section, a person who conducts a portion of a remedial action, where that portion is entirely on site and is conducted in compliance with this article, may be exempted from a requirement to obtain any other state or local permit or approval, other than any requirement of title 45, at the written request of the person conducting the remedial action. The written request shall identify the specific permit to be exempted and the reasons the exemption is requested. The permit may be exempted if the director finds both of the following:

1. The requirement does not arise out of any permit or regulatory program that is required pursuant to the laws of the United States.

2. The requirement presents a substantial impediment to effective performance of the remedial action selected by the department.

C. The director may waive any regulatory requirement adopted pursuant to this title with respect to a site or portion of a site as part of a record of decision adopted pursuant to section 49-287.04 for that site or portion of a site if the regulatory requirement conflicts with the implementation of the selected remedy, provided that the waiver does not result in adverse impacts to public health or the environment. No waiver may be granted under this subsection if it is prohibited by federal law or if the waiver would jeopardize the continued delegation to the state of authority to implement a federal environmental program.

D. Discharge of wastewater to off-site publicly owned treatment works and sewer systems does not constitute an activity conducted entirely on site for purposes of subsection B of this section.

E. The director shall give written notice of any request for exemption made pursuant to subsection B of this section to the remedial action coordinator designated pursuant to subsection G of this section by the governmental entity whose permit requirements are the subject of the request. Before making any finding pursuant to subsection B of this section, the director or the director's designee shall meet and confer with the remedial action coordinator and the person conducting the remedial action to identify alternatives to exemption.

F. Any finding made by the director pursuant to subsection B of this section shall be in writing. The governmental entity whose permit requirement is preempted as a result of such finding is not liable for property damage, personal injury damage or violations of state or local law resulting from the exemption. The director shall notify the affected governmental entity of any finding made pursuant to subsection B of this section. A finding of the director made pursuant to subsection B of this section is a final administrative decision as defined in section 41-1092 and is subject to judicial review pursuant to title 12, chapter 7, article 6.

G. Each city, town and county shall designate a remedial action coordinator who shall have responsibility for monitoring and facilitating any remedial actions conducted within its jurisdiction. The designated remedial action coordinator shall:

1. Regularly consult, as needed, with the department and the person conducting a remedial action throughout the duration of the remedial action.

2. Expedite the processing and issuance of permits, approvals or other authorizations required by the governmental entity represented by the remedial action coordinator, to facilitate the prompt conduct of a remedial action.

3. Provide information to the department and the person conducting the remedial action regarding applicable requirements of the governmental entity represented by the remedial action coordinator and the potential for waiver of such requirements.

H. In order to encourage remediation activities under this article and to conserve the fund, neither this state nor any county that imposes an excise or similar tax that is levied at a rate applied as a percentage of the rates on each business class subject to the tax imposed by title 42, chapter 5, article 1 may impose a tax on the sale or purchase of tangible personal property incorporated or fabricated into any real property, structure, project, development or improvement under a contract specified in section 42-5075, subsection B, paragraph 6.

I. For purposes of this section, "on site" means the areal extent of contamination and all suitable areas in close proximity to the contamination that are reasonably necessary for implementation of the remedial action.

Disclaimer: These codes may not be the most recent version. Arizona may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.