In re Application of Duke Energy Ohio, Inc.
Annotate this CaseThe Supreme Court affirmed the order of the Public Utilities Commission that authorized Duke Energy Ohio, Inc. to recover costs associated with the environmental remediation of two manufactured-gas-plant (MGP) sites near downtown Cincinnati. The court held that the Commission did not exceed its authority when it allowed Duke to recover the costs incurred to remediate the MGP sites. The court dismissed Appellants’ remaining arguments as moot. Because Appellants did not carry their burden of demonstrating that the Commission’s order was unjust, unreasonable or unlawful, the Supreme Court affirmed the Commission's order.