PROBUILD NORTH LLC V STEVEN R ELLIS
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
PROBUILD NORTH, L.L.C.,
UNPUBLISHED
February 4, 2010
Plaintiff-Appellee,
v
STEVEN R. ELLIS, a/k/a STEVE ELLIS, d/b/a
SE BUILDER,
No. 288439
Saginaw Circuit Court
LC No. 06-062509-CK
Defendant,
and
RONALD R. JINKS and KIMBERLY JINKS,
Defendants-Appellees,
and
DEPARTMENT OF LABOR & ECONOMIC
GROWTH,
Defendant-Appellant.
Before: Donofrio, P.J., and Meter and Murray, JJ.
PER CURIAM.
Defendant Department of Labor and Economic Growth (DLEG), through the
Homeowner Construction Lien Recovery Fund (the Fund), appeals as of right from a judgment
entered in favor of plaintiff and against the Fund for $24,543.49. On appeal, the Fund challenges
the trial court’s earlier order granting summary disposition to defendants Ronald and Kimberly
Jinks. We affirm. This appeal has been decided without oral argument pursuant to MCR
7.214(E).
The Jinkses accepted a proposal for home improvements made by defendant Steven Ellis.
The contract price was $37,000, including labor and materials. The Jinkses ultimately paid Ellis
$38,680. Ellis obtained lumber and other building materials from plaintiff on credit. Ellis failed
to fully pay for the materials, so plaintiff filed a claim of lien in March 2006. The claim
indicated that Ellis’s total contract amount with plaintiff was $31,012.31, which, when adjusted
-1-
for payments and other credits of $15,654.75, left an unpaid balance of $15,357.56. In October
2006, plaintiff brought this action to foreclose the lien.
At issue in this appeal is whether the construction lien can be enforced against the
Jinkses’ property because they did not pay Ellis, the contractor, for the improvements to their
property. Plaintiff and the Fund both argue that this determination must be made on the basis of
the value of the improvements, not the contract price. We disagree and conclude that because
the undisputed evidence showed that the Jinkses fully paid Ellis for the amount of the contract
price, the trial court properly granted their motion for summary disposition.
Before MCL 570.1203 was amended by 2006 PA 572, effective January 3, 2007, the
statute provided, in pertinent part:
(1) A claim of construction lien shall not attach to a residential structure,
to the extent payments have been made, if the owner or lessee files an affidavit
with the court indicating that the owner or lessee has done all of the following:
(a) Paid the contractor for the improvement to the residential structure and
the amount of the payment.
(b) Not colluded with any person to obtain a payment from the fund.
(c) Cooperated and will continue to cooperate with the department in the
defense of the fund.
In an effort to satisfy the requirements of this statute, the Jinkses submitted an affidavit from
defendant Ronald Jinks, who averred that he paid $38,680 to the contractor for the improvements
to their residential structure, that he did not collude with any other person to obtain payment
from the Fund, and that he had cooperated and would continue to cooperate with the DLEG in
the defense of the Fund.
The trial court determined that there was no genuine issue of material fact that the Jinkses
had “[p]aid the contractor for the improvement to the residential structure . . . .” On appeal, the
Fund contends that the evidence showed that the contractor underbid the project, and,
accordingly, there was a genuine issue of material fact regarding whether the Jinkses paid the
contractor for the improvement.
Summary disposition may be granted under MCR 2.116(C)(10) when “there is no
genuine issue of material fact, and the moving party is entitled to judgment . . . as a matter of
law.” This Court reviews de novo a trial court’s decision on a motion for summary disposition.
Maiden v Rozwood, 461 Mich 109, 118; 597 NW2d 817 (1999).
Neither plaintiff nor the Fund cite case law supporting their position that payment for the
improvement referenced in former MCL 570.1203 contemplates payment of the value of the
improvement or the market price for the improvement. In fact, pertinent statutory and case law
indicates that payment for the improvement is measured by the contract price.
-2-
Former MCL 570.1107(6) indicates that the total amount of liens cannot exceed the
contract price less payments made:
If the real property of an owner or lessee is subject to construction liens,
the sum of the construction liens shall not exceed the amount which the owner or
lessee agreed to pay the person with whom he or she contracted for the
improvement as modified by any and all additions, deletions, and any other
amendments, less payments made by or on behalf of the owner or lessee, pursuant
to either a contractor's sworn statement or a waiver of lien, in accordance with this
act.
Pursuant to this provision, if the owner has fully paid the amount that he “agreed to pay,” then
the sum of the construction liens shall not exceed zero. As recognized in Vugterveen Systems,
Inc v Olde Millpond Corp, 454 Mich 119, 128; 560 NW2d 43 (1997), “[t]his subsection was
designed to protect an owner from excessive liens by allowing an owner to rely on the price set
forth in its contract with the general contractor.” Thus, the Construction Lien Act provides
protection for owners who pay the contract price. The provision is incompatible with an
interpretation of MCL 570.1203 that would preclude a lien only if the owner paid for the value of
the improvement.
Vugterveen Systems and Erb Lumber v Gidley, 234 Mich App 387; 594 NW2d 81 (1999),
both support the conclusion that full payment of the contract price to the contractor precludes a
construction lien. In Vugterveen Systems, 454 Mich at 129, the owner fired the general
contractor (Vander Wall) and the subcontractor (Vugterveen) and paid additional amounts on a
second general contract. The Court rejected the owner’s contention that the calculation of the
payments made for purposes of MCL 570.1106(6) should include payments under the second
general contract. Vugterveen Systems, 454 Mich at 129. However, the Court explained that the
owner “will have a defense to Vugterveen’s lien if it can show that the sum of payments made
pursuant to sworn statements and waivers of lien under the Vander Wall contract plus
Vugterveen’s claim of lien exceed the price of the Vander Wall contract.” Vugterveen Systems,
454 Mich at 129.
In Erb Lumber, 234 Mich App at 390-391, the owners paid most of the contract price, but
withheld part of the payment because they believed the work was incomplete and then learned
that the contractor intended to declare bankruptcy. Erb Lumber sought to foreclose a lien against
the property for the unpaid balance that the contractor owed. Id. at 391. Although the owners
had not paid the full contract price, the trial court gave them a credit for the unpaid amount
because of poor workmanship and unfinished tasks. Id. The trial court determined that the
amount paid by the owners fully compensated the contractor for the improvement the owners
received. Id. The court then concluded that Erb Lumber was precluded from foreclosing on the
lien because the owners had fully paid the contractor for the improvement. Id. at 392. This
Court affirmed that decision, but analyzed the matter differently. Instead of agreeing with the
trial court’s discount-to-contract price on the basis of the value of the work that the contractor
had performed, the Court concluded that owners seeking to preclude a lien from a supplier need
not show that they fully paid for the entire construction job. Id. at 396. Rather, as a defense to a
lien by a supplier, the owner’s payment to the contractor for the “improvement” provided by the
supplier is sufficient. Id. A supplier’s improvement “is limited to the materials supplied.” Id.
The issue then was whether the owners’ (incomplete) payment to the contractor should be
-3-
deemed to be for the construction materials provided by Erb Lumber. Id. at 396-400. However,
in addressing a dissenting opinion in that case, the majority noted, “We agree that the
homeowners here should be allowed to rely on their overall contract price so that they would not
be forced to pay more for liens than the price stated in the general contract . . . .” Id. at 397.
The analysis of this case does not involve the complications of payments to more than
one contractor, as in Vugterveen Systems, or partial payment to the contractor, as in Erb Lumber.
Thus, there is no need to determine how payments to the contractor should be allocated. The
Jinkses paid the contractor the full contract price, which included materials. Regardless of
whether the contract price was too low, the Jinkses “[p]aid the contractor for the improvement.”
MCL 570.1203(1)(a). Therefore, the trial court correctly determined that the Jinkses were
entitled to summary disposition.
Affirmed.
/s/ Pat M. Donofrio
/s/ Patrick M. Meter
/s/ Christopher M. Murray
-4-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.