GRAND RAPIDS HOUSING COMM V OHIO FARMERS INS CO
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
GRAND RAPIDS HOUSING COMMISSION and
MT. MERCY HOUSING CORPORATION,
UNPUBLISHED
February 7, 2008
Plaintiffs-Appellees,
v
No. 273513
Kent Circuit Court
LC No. 05-007189-CK
OHIO FARMERS INSURANCE COMPANY,
Defendant-Appellant.
Before: Davis, P.J., and Murphy and White, JJ.
PER CURIAM.
Defendant Ohio Farmers Insurance Company (OFIC) appeals as of right the circuit
court’s order granting summary disposition to plaintiffs Grand Rapids Housing Commission
(GRHC) and Mt. Mercy Housing Corporation (MMHC). OFIC also challenges the circuit
court’s order denying its motion for reconsideration. We reverse.
I
In December 2003, Cycon Enterprises, Inc. (Cycon), contracted with the GRHC and Mt.
Mercy Limited Partnership (MMLP) to be the general contractor for Assisted Living Mt. MercyPhase II (the Project). Two months later, OFIC, as surety, issued a performance bond on behalf
of Cycon, the principal. The performance bond listed GRHC as the obligee and owner of the
bond. OFIC also issued two obligee riders, which listed MMHC and Fifth Third Bank as
obligees. In December 2004, Mt. Mercy Limited Partnership II (MMLP II) unilaterally
terminated Cycon as general contractor of the project, believing that Cycon failed to perform in
accordance with the contract. MMLP II then commenced this action against OFIC seeking to
recover the amount that it spent above the contract price to finish the project. Thereafter, GRHC
and MMHC, who were the obligees under the performance bond, were substituted as plaintiffs.
Cycon instituted arbitration proceedings against MMLP II and GRHC, claiming that its
termination from the project was improper. A counterclaim was asserted based on the
completion damages. While the arbitration was pending, OFIC sought summary disposition in
the instant action on the limited basis that it could not be liable to GRHC or MMHC under the
performance bond because the plaintiff obligees suffered no damages. Rather, OFIC asserted,
assuming Cycon did, in fact, breach the contract, only MMLP II, an entity that was not an
obligee under the bond, incurred the additional completion expenses.
-1-
Plaintiffs responded to the substance of OFIC’s motion, addressing the issue whether
plaintiffs suffered compensable losses. Plaintiffs’ response included the following:
Under MCR 2.116(C)(10), a moving party is entitled to Summary
Disposition only if there is no genuine issue as to any material fact and the
moving party is entitled to judgment as a matter of law. [Citation omitted]. In
ruling on such a motion, the Court must consider the pleadings as well as any
depositions, affidavits, admissions, or other documentary evidence submitted by
the parties MCR 2.116(G)(5). “If it appears to the Court that the opposing
party, rather than the moving pary, is entitled to judgment, the Court may
render judgment in favor of the opposing party.” MCR 2.116(I)(2).
OFIC’s Motion for Summary disposition must be denied. The attached
evidence that GRHC has paid all Completion Contractors after Cycon’s
termination precludes the conclusion that GHRC [sic] has not been injured by
Cycon’s termination from the Project. Since OFIC now represents that no factual
issues exist, Summary Disposition should be entered in favor of GRHC and
MMHC against OFIC for $1,061.506, plus costs, interest and attorney fees.
[Emphasis in original.]
OFIC filed a reply to plaintiffs’ response to OFIC’s motion for summary disposition in which it
argued that the affidavit attached to plaintiffs’ response supported OFIC’s position that MMLP II
was obligated to reimburse GRHC for the additional expenditures, and so GRHC and MMHC,
the plaintiff obligees suffered no compensable losses.
At argument on OFIC’s motion, counsel for OFIC began by identifying the parties and
their relationships. Defense counsel continued:
They [Cycon] were defaulted. This case doesn’t deal with the propriety of that
and who is right and who is wrong, but they were in December of ‘04 – I’m sorry,
’05. At that point, Mt. Mercy II entered into a contract with Triangle construction
...
Counsel asserted that MMLP II is the owner, hired the completing contractors, and owes GRHC
for the amounts expended, and that therefore GRHC suffered no loss.
Counsel for plaintiffs then responded. He began:
Let me see if I can put this all into perspective, because it’s undisputed, and we - we think that the facts are undisputed at this point, that we’re entitled to summary
disposition.
Counsel went on to explain that GRHC is listed as an owner under the contract with Cycon, and
is also an obligee under the bond. Counsel continued:
The contract called for a performance bond. They issued a performance bond.
There's no debate about that. We're an obligee. No debate about that. No debate
about the default. No debate about the notice of default. The bond required, the
-2-
specific terms of the bond required the bonding company to complete the project
upon default. They didn't complete the project upon default, so the Grand Rapids
Housing Commission, the owner under the contract, then undertook to complete
that work.
We did complete the work. Grand Rapids Housing Commission hired the
replacement contractors. They paid the replacement contractors. They hired the
replacement subcontractors. They paid those subcontractors. All said and done,
the Grand Rapids Housing Commission has paid out of its own bank account $5.4
million for a contract it was only obligated to pay 4.2 million plus some minor
change orders. So as you saw in the map in Carlos' [Sanchez] affidavit, the Grand
Rapids Housing Commission is out hard dollars, 1,061,000 and change.
***
Now, with regard to the claim that there's no compensable losses [sic], under the
development contract, as a developer, the Grand Rapids Housing Commission
was obligated to deliver this project to Mr. Mercy Limited Partnership II for 4.2
million. Mt. Mercy Limited Partnership II wasn’t obligated to pay more money. .
. . we’re not asking for any money that the limited partnership has an obligation to
reimburse back to the Grand Rapids Housing Commission. What we want is we
want the 1,061,000 which the partnership is not obligated to reimburse the
housing commission because that was the housing commission's risk, because
they were the developer. . . .
***
You can't --you can't sell a bond, list a company as an obligee, have that obligee
pay money that it can't recover from anyone, and then turn and walk away and say
we’re not going to pay you, because we have hard dollars we paid, we
demonstrated by the affidavit, and there’s nothing of record right now that
disputes that.
So we’d ask, frankly, not only that the motion be denied, but that summary
disposition, at least on the issue of liability, be granted in our favor.
And incidentally, the whole - - this whole case, there’s a companion case, an
arbitration that’s supposed to be going. I want to talk to you at some point about
maybe extending the deadlines because nothing that happens in this case really
matters until the arbitration is done, but that's another issue for another day.
[Emphasis added.]
The court then announced that it would take the matter under advisement and issue a written
opinion. Plaintiffs’ counsel observed that defense counsel had filed a reply brief, and requested
an opportunity to respond to the reply. The court agreed.
-3-
In its response to OFIC’s reply, filed after argument on the motion, plaintiffs again
argued that GRHC had suffered an actual loss of $1,061,000. Plaintiffs then argued that they
were entitled to summary disposition:
Here, the Affidavit of Carlos Sanchez establishes, without any counter
evidence of any type or kind, and even with partial concession by OFIC; (1) the
existence of the contract between Cycon Enterprises, Inc. and the Grand Rapids
Housing Commission, (2) the existence of the Performance Bond provided by
OFIC, (3) the event of default by Cycon Enterprises, Inc., and (4) the amount of
money spent by one of the named obligees, the Grand Rapids Housing
Commission. This satisfies all of the requirements for granting summary
disposition under MCR 2.116(C)(10). The response of the Grand Rapids Housing
Commission and Mt. Mercy Housing Corporation, which clearly included a
request for summary disposition under MCR 2.116(1), clearly placed OFIC on
notice that the Grand Rapids Housing Commission and Mt. Mercy Housing
Corporation intended to ask this Court that summary disposition be entered in
their favor. Even though the “Reply” filed by OFIC was not permissible under
the Rules, the “Reply” nevertheless failed to address any of the arguments
regarding outstanding balances owed and failed to present any additional
information suggesting that any material issue of fact exists in this case. Further,
no such issue of fact was pointed out or even suggested during oral argument. On
that basis, this Court is fully empowered to enter summary disposition in favor of
the Grand Rapids Housing Commission, and respectfully, that is precisely what
should be done here.
The circuit court then issued a written opinion and order granting plaintiffs a judgment
for $1,061,506. OFIC filed a motion for reconsideration, arguing that the court erred in granting
judgment for plaintiffs because the question of Cycon’s liability under the contract was “hotly
contested” and was yet to be decided in the arbitration proceedings, and that because OFIC’s
liability as the surety depends on Cycon’s liability as the principal, judgment should not have
been granted to plaintiffs. The circuit court denied the motion, finding that
the Motion for Reconsideration’s arguments related to issues that may or may not
be hotly contested in Cycon arbitration (see page 2 of OFIC’s brief in support of
their Motion for Reconsideration) clearly would have been known and were
known by the OFIC defendants at the time of their initial motions but were not
argued.
The court then rejected the argument that it had been misled, and observed that OFIC had
asserted in its motion that “all of the material facts of this case are undisputed,” OFIC’s counsel
had stated at argument “[t]hey were defaulted. This case doesn’t deal with the propriety of that
and who is right and who is wrong . . .”, counsel for plaintiffs had mentioned the ongoing
arbitration, and counsel for OFIC “at no time asserted any arbitration clause issues.” The court
concluded:
The matters before the Court were fully considered, full [sic] evaluated and the
Court made the determination that it did . . . based upon the Court’s analysis and
-4-
understanding of the uncontested facts as suggested by the parties and of the law
that applied to the case.
The Court does not believe palpable error has taken place.
II
On appeal, OFIC claims that the circuit court erred in granting summary disposition to
GRHC and MMHC and ordering it to pay $1,061,506, before Cyclon’s liability was determined
in the arbitration proceeding, and in denying its motion for reconsideration. We agree.
We review a trial court’s decision on a motion for summary disposition de novo. Smith v
Globe Life Ins Co, 460 Mich 446, 454; 597 NW2d 28 (1999). Summary disposition is proper
under MCR 2.116(C)(10) if the affidavits and documentary evidence presented, viewed in the
light most favorable to the nonmoving party, show that there is no genuine issue of material fact
and the moving party is entitled to judgment as a matter of law. Quinto v Cross & Peters Co,
451 Mich 358, 362; 547 NW2d 314 (1996). Pursuant to MCR 2.116(I)(2), “[i]f it appears to the
court that the opposing party, rather than the moving party, is entitled to judgment, the court may
render judgment in favor of the opposing party. ”We review a trial court’s decision on a motion
for reconsideration for an abuse of discretion. Churchman v Rickerson, 240 Mich App 223, 233;
611 NW2d 333 (2000). A trial court abuses its discretion when it fails to select a principled
outcome. Maldonado v Ford Motor Co, 476 Mich 372, 388; 719 NW2d 809 (2006).
MCR 2.119(C), which governs a motion for reconsideration, provides:
Generally, and without restricting the discretion of the court, a motion for
rehearing or reconsideration which merely presents the same issues ruled on by
the trial court, either expressly or by reasonable implication, will not be granted.
The moving party must demonstrate a palpable error by which the court and the
parties have been misled and show that a different disposition of the motion must
result from correction of the error.
“A surety is one who undertakes to pay money or take any other action if the principal
fails therein.” Will H Hall & Son, Inc v Ace Masonry Constr, Inc, 260 Mich App 222, 228-229;
677 NW2d 51 (2003). A surety may plead any defense available to the principal. Id. at 229.
The liability of the surety is coextensive with the liability of the principal and can be extended no
further. Id.
There is no dispute that in order to find OFIC liable under the bond, the court had to find
that Cycon was liable under the contract. Plaintiffs argue that the court so found based upon
their own request for summary disposition and the uncontested affidavit of Carlos Sanchez.
While the court may, indeed, have been justified in assuming that summary disposition in
plaintiffs favor would be proper if the court rejected OFIC’s argument regarding whether
plaintiffs suffered a compensable loss, given OFIC’s exclusive focus on that issue, it is
nonetheless apparent that the parties entered the summary disposition debate with the
understanding that the issue before the court was whether plaintiffs suffered a compensable loss,
not whether there was a genuine issue whether Cycon had breached the contract.
-5-
We have engaged in the extensive account of the proceedings recounted above because
we think it clear that a review of those proceedings can lead to but one conclusion -- that at least
until plaintiffs’ response to OFIC’s reply to plaintiffs’ response to OFIC’s motion, which was
filed after argument, the only issue was whether plaintiffs had suffered a compensable loss under
the bond. Under the circumstances, the court abused its discretion in refusing to grant
reconsideration and modify the judgment to reflect a partial summary disposition in plaintiffs’
favor on the issue whether its completion damages would be covered under the bond if Cycon is
ultimately determined to have breached the underlying contract. The court should have
recognized that on this record, palpable error results from declaring OFIC, the surety, liable in
the sum of $1,061,506, when it is unknown whether the arbitrators will determine that Cycon,
the principal, had breached the contract when it was forced off the job.
Reversed and remanded for entry of partial summary disposition for plaintiffs consistent
with this opinion. We do not retain jurisdiction.
/s/ Alton T. Davis
/s/ William B. Murphy
/s/ Helene N. White
-6-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.