CHAPPELLE DEVELOPMENT CO V HOWARD J SHOOLTZ
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
CHAPPELLE DEVELOPMENT COMPANY,
UNPUBLISHED
July 23, 2002
Plaintiff/Counter-DefendantAppellant,
No. 225920
Clinton Circuit Court
LC No. 98-008834-CK
V
HOWARD J. SHOOLTZ,
Defendant/Counter-PlaintiffAppellee,
and
MRS. HOWARD J. SHOOLTZ,
Defendant,
and
SCOTT A. CHAPPELLE, P.C.,
Counter-Defendant.
Before: Bandstra, P.J., and Hoekstra and O’Connell, JJ.
PER CURIAM.
Plaintiff appeals as of right from a judgment awarding defendant $5,840 for a breach of
contract. This case arose out of a claim and counterclaim alleging breach of a contract pursuant
to which plaintiff was to purchase and remove five hundred trees from defendant’s property.
Within two months after the contract had been signed, defendant had denied plaintiff access to
the trees, and plaintiff had failed to pay for those trees that had been removed. After a jury found
that both parties had breached the contract but awarded damages only to defendant, plaintiff filed
a motion for a new trial or additur, which was denied. Plaintiff appeals the denial of this motion
as well as the imposition of certain attorney fees and costs. We affirm.
We review a trial court’s decision regarding the denial of a new trial or additur for an
abuse of discretion. Joerger v Gordon Food Service, Inc, 224 Mich App 167, 172; 568 NW2d
365 (1997). In determining whether additur is appropriate, the proper consideration is whether
-1-
the jury award was supported by the evidence. Setterington v Pontiac General Hospital, 223
Mich App 594, 608; 568 NW2d 93 (1997). The grounds for granting a new trial are codified at
MCR 2.611(A)(1), which provides the only bases on which a jury verdict may be set aside.
Kelly v Builders Square, Inc, 465 Mich 29, 38; 632 NW2d 912 (2001).
Plaintiff argues that three of these grounds for granting a new trial are applicable: (1)
excessive or inadequate damages appearing to have been influenced by passion or prejudice; (2)
a verdict clearly or grossly inadequate or excessive; and (3) a verdict or decision against the great
weight of the evidence or contrary to law. MCR 2.611(A)(1)(c)-(e). The party asserting a
breach of contract has the burden to prove its damages with reasonable certainty, and may
recover only those damages which are the direct, natural and proximate result of the breach. In
re F Yeager Bridge & Culvert Co, 150 Mich App 386, 401; 389 NW2d 99 (1986). Generally,
the adequacy of the amount of the damages is a matter for the jury. Hill v Henderson, 107 Mich
App 551, 554; 309 NW2d 663 (1981).
Plaintiff argues that it proved damages by showing that he purchased trees from another
supplier at greater cost after defendant’s initial refusal to allow plaintiff access to the property.
However, plaintiff also had the burden of showing that this expense was proximately caused by
defendant’s breach. F Yeager, supra. The contract specified that the trees could only be
removed at a time that was mutually agreeable, and expressly allowed defendant flexibility in
determining the timing of tree removal. Although the jury found that defendant’s denial of
access at some point constituted a breach of contract, it did not specify when the breach had
occurred. Furthermore, testimony indicated that plaintiff used many of defendant’s trees on a
site near Detroit, raising the question whether plaintiff’s purchase of trees from a third party was
necessary. As a result, it is not clear whether plaintiff incurred these expenses as a proximate
result of the breach.
Plaintiff also argues that at least nominal damages should have been awarded for
defendant’s breach of the agreement. See Litvin v Joyce, 329 Mich 56, 59-60; 44 NW2d 867
(1950). However, “[t]here is no legal requirement that a jury award damages simply because
liability was found.” Joerger, supra at 173. Because a reasonable juror could have found that
plaintiff failed to prove damages that were proximately caused by defendant’s breach, the trial
court did not abuse its discretion in refusing to grant a new trial or additur.
Finally, plaintiff contests the trial court’s mediation sanction award of attorney fees and
costs to defendant. We review this award for an abuse of discretion. Id. at 177-178. Having
examined the record and the reasoning employed by the trial court, we do not conclude that the
contested order is so “grossly violative of fact and logic” as to constitute an abuse of discretion.
See Spalding v Spalding, 355 Mich 382, 384; 94 NW2d 810 (1959).
We affirm.
/s/ Richard A. Bandstra
/s/ Joel P. Hoekstra
/s/ Peter D. O’Connell
-2-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.