CENTRAL CEILING & PARTITION INC V PRIMEAU HOMES INC
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
CENTRAL CEILING & PARTITION, INC.,
FOR PUBLICATION
January 29, 2002
9:15 a.m.
Plaintiff-Appellee,
v
No. 225378
Wayne Circuit Court
LC No. 98-810597-CH
DEPARTMENT OF COMMERCE,
Defendant-Appellant,
and
KITCHEN SUPPLIERS, INC.,
Defendant-Appellee,
and
CAPPY HEATING AND AIR CONDITIONING,
INC.,
Updated Copy
April 12, 2002
Intervening-Plaintiff-Appellee,
and
PRIMEAU HOMES, INC.,
Defendant
Before: Neff, P.J., and Wilder and Cooper, JJ.
WILDER, J. (dissenting).
I respectfully dissent. In Northern Concrete Pipe, Inc v Sinacola Cos—Midwest, Inc,
461 Mich 316, 321, 323-324; 603 NW2d 257 (1999), our Supreme Court held that the substantial
compliance provision of the Construction Lien Act, MCL 570.1302(1), does not apply to the
statutorily mandated ninety-day recording deadline found in MCL 570.1111(1). Because the
liens asserted by Central Ceiling & Partition, Inc. (Central), Kitchen Suppliers, Inc. (KSI), and
Cappy Heating and Air Conditioning, Inc. (Cappy) were not recorded within the ninety-day
-1-
deadline, they ceased to exist, and the lower court judgment in favor of Central, KSI, and Cappy
should be reversed.
I
To recover under the Construction Lien Act, a claimant must record the lien within ninety
days of the last date of furnishing material or labor:
Notwithstanding section 109 [MCL 570.1109], the right of a contractor,
subcontractor, laborer, or supplier to a construction lien created by this act shall
cease to exist unless, within 90 days after the lien claimant's last furnishing of
labor or material for the improvement, pursuant to the lien claimant's contract, a
claim of lien is recorded in the office of the register of deeds for each county
where the real property to which the improvement was made is located. A claim
of lien shall be valid only as to the real property described in the claim of lien and
located within the county where the claim of lien has been recorded. [MCL
570.1111(1) (emphasis added).]
To resolve the dispute in this case, we must determine what constitutes "recording" a
claim of lien in the office of the register of deeds. This determination is a matter of statutory
interpretation, a question of law that we review de novo. Etefia v Credit Technologies, Inc, 245
Mich App 466, 469; 628 NW2d 577 (2001), citing Oakland Co Bd of Co Rd Comm'rs v
Michigan Property & Casualty Guaranty Ass'n, 456 Mich 590, 610; 575 NW2d 751 (1998); In
re S R, 229 Mich App 310, 314; 581 NW2d 291 (1998). Our Supreme Court in Macomb Co
Prosecutor v Murphy, 464 Mich 149, 158; 627 NW2d 247 (2001), observed:
In considering a question of statutory construction, this Court begins by
examining the language of the statute. We read the statutory language in context
to determine whether ambiguity exists. If the language is unambiguous, judicial
construction is precluded. We enforce an unambiguous statute as written. Where
ambiguity exists, however, this Court seeks to effectuate the Legislature's intent
through a reasonable construction, considering the purpose of the statute and the
object sought to be accomplished. [Citations omitted.]
Unless defined in the statute, every word or phrase of a statute should be accorded its plain and
ordinary meaning, taking into account the context in which the words are used, Phillips v Jordan,
241 Mich App 17, 22-23, n 1; 614 NW2d 183 (2000), citing Western Michigan Univ Bd of
Control v Michigan, 455 Mich 531, 539; 565 NW2d 828 (1997). Further, the language must be
applied as written, Camden v Kaufman 240 Mich App 389, 394; 613 NW2d 335 (2000); Ahearn
v Bloomfield Charter Twp, 235 Mich App 486, 498; 597 NW2d 858 (1999), and nothing should
be read into a statute that is not within the manifest intent of the Legislature as indicated by the
act itself. In re S R, supra at 314.
The majority concludes that the filing of a lien within ninety days and the acceptance of
the lien filing by the register of deeds substantially complies with the act's requirement to record
the lien claim. Because this conclusion is contrary to the plain meaning of the term "recorded"
as used in the act, I disagree.
-2-
First, while the term "recorded" is not defined in the Construction Lien Act, there is
ample evidence in the act as well as other statutes with regard to its intended meaning. MCL
565.25, relating to entry books, the effect of entry by the register of deeds, recording of certain
instruments of encumbrance, perfection, or conditions, application, nonexempt persons, and
penalties, provides in relevant part:
(1) . . . In the entry book of levies the register shall enter all . . . liens [and]
other instruments of encumbrances, and documentation required under subsection
(2), noting in the books, the day, hour, and minute of receipt, and other
particulars, in the appropriate columns in the order in which the instruments are
respectively received.
* * *
(4) The instrument shall be considered as recorded at the time so noted
and shall be notice to all persons except the recorded landowner subject to
subsection (2) of the liens, rights and interests acquired by or involved in the
proceedings. [Emphasis added.]
MCL 600.2567 provides in relevant part:
(1) A register of deeds is entitled to the following fees . . .
(a) For entering and recording a deed . . . or other instrument, $5.00 for the
first page and $2.00 for each additional and succeeding page. . . . The fee shall be
paid when the . . . instrument is left for record. . . .
(2) In addition to any other fees proscribed in subsection (1) or (5) , a
register of deeds shall collect a fee of $2.00 for entering and recording a deed . . .
or other instrument. The fee shall be paid when the instrument is left for record.
[Emphasis added.]
In MCL 570.1109, which describes notices of furnishing under the act, a sample form is
provided:
(4) The notice of furnishing, if not given on the form attached to the notice
of commencement, shall be in substantially the following form:
NOTICE OF FURNISHING
To: ______________________________________________________________
(name of designee (or owner or lessee) from notice of commencement)
(address from notice of commencement)
-3-
Please take notice that the undersigned is furnishing to _____________________
__________________________________________________________________
(name and address of other contracting party)
certain labor or material for __________________________________________,
(describe type of work)
in connection with the improvement to the real property described in the notice of
commencement recorded in liber, _______ on page ______ (name of county)
records,
It is apparent from these statutes that the recording of a lien does not take place until an
entry has been made in the book of levies, with the assignment of a liber and page number noting
the date, hour, and minute the lien is entered. As both MCL 565.25 and MCL 600.2567 make
clear, the leaving of the instrument for record, i.e., filing, does not constitute the recording of the
document. See People v Madigan, 223 Mich 86, 89; 193 NW 806 (1923); Hollis v Zabowski,
101 Mich App 456, 457; 300 NW2d 597 (1980); see also 36A CJS, File, pp 396-398 (a paper or
document is filed when it is delivered to or received by the proper officer to be kept on file, and
the endorsement of the officer with whom it is filed is but evidence of the time of filing). The
purpose of recording is made clear in MCL 565.25(4): the recording of a lien constitutes notice
to all persons except as provided in subsection 2 that a lien claim is being asserted. The
majority's conclusion that the filing and acceptance of the lien within the ninety-day statutory
period substantially complies with the Construction Lien Act's requirement that the lien be
recorded within that time frame defeats the purpose of the requirement and is inconsistent with
the plain meaning of the term "recorded."
Precedent from our Supreme Court also recognizes that entry in liber must occur to
record a document. In Balen v Mercier, 75 Mich 42, 48; 42 NW 666 (1889), the Court stated
that "[o]ur statutes contemplate that any instrument which is entitled to be recorded shall first be
entered by the register in the entry book, and then it is deemed recorded." (Emphasis added.) In
Brigham v Brown, 44 Mich 59, 61-62; 6 NW 97 (1880), the Supreme Court held that delivery of
a mortgage to the register of deeds did not constitute recording and that recording did not occur
until the actual copying of the mortgage into the record book took place. While the statutes at
issue in these cases obviously are different from the Construction Lien Act that we interpret here,
it is clear that in these prior cases as well as the instant case the purpose of recording is to give
official notice of assertion of a claim on land title.
Further support for the conclusion that filing does not constitute recording is found in the
precedent of several states. In State v Noren, 621 P2d 1224, 1225 (Utah, 1980), the Utah
Supreme Court held: "Although the words 'file' and 'record' have occasionally been used
somewhat interchangeably they have more frequently been interpreted as implying or requiring
different things. 'Recorded' has been held to signify 'copied or transcribed into some permanent
book' while 'filing' signifies merely delivery to the proper official." Id., citing Beatty v Hughes,
-4-
61 Cal App 2d 489, 492; 143 P2d 110 (1943) and Maryland Dep't of Natural Resources v
Hirsch, 42 Md App 457, 502; 401 A2d 491 (1979).
In Markham v Markham, 80 Hawaii 274, 281; 909 P2d 602 (1996), the Intermediate
Court of Appeals of Hawaii, quoting Black's Law Dictionary (6th ed), found that "[a] document
or instrument is considered recorded when it is 'commit[ted] to writing, . . . printing, . . . or the
like[,]' 'or transcribe[d], or enter[ed] in a book, file, docket, register, computer tape or disc, or the
like, for the purpose of preserving authentic evidence . . . [and] for the purpose of giving notice.'"
[Emphasis added.]
The majority rejects application of the plain meaning of the term "recorded," under the
circumstances of this case, as inconsistent with both the intent of the Legislature and the holding
of Northern Concrete Pipe, supra. I disagree with this conclusion because the Supreme Court's
holding in Northern Concrete Pipe, supra, adopts the strict compliance rule.
It is a cardinal rule of statutory construction that a clear and unambiguous
statute warrants no further interpretation and requires full compliance with its
provisions, as written. Within the Construction Lien Act, however, the
Legislature provided an exception to that rule, in the form of the "substantial
compliance" provision. As an exception, this provision should not be interpreted
to nullify altogether the general rule that statutes should be interpreted consistent
with their plain and unambiguous meaning. [Id. at 320-321 (citations omitted).]
In interpreting § 111, the Supreme Court noted in Northern Concrete Pipe, supra, that
because the statute emphasizes that the lien "'cease[s] to exist' if not recorded within the ninetyday deadline . . . [the provision is] not . . . well suited to a 'substantial compliance' application . . .
." Id. at 323. The Court goes on to state that
[t]he case before us is a clear instance in which the Legislature could not have
imposed a more precise requirement. MCL 570.1111(1); MSA 26.316(111)(1)
states without qualification that a subcontractor's right to a lien ceases to exist if
not recorded in the county office of the register of deeds within ninety days after
the last furnishing of labor or material. [Id. at 323-324 (emphasis added).]
In my view, interpreting the term "recorded" to mean entry in the book of levies not only
is consistent with the plain meaning of the statute but is consistent with the Legislature's intent to
require strict compliance with this particular notice provision of the act. On the other hand,
property owners and subsequent purchasers who check the book of levies after ninety days and
find no recordation of a claim of lien will lack notice of a claim merely "filed," and thus will lack
certainty of title under the result reached by the majority. As pointed out by the Supreme Court,
"certainty of title could only be achieved [under these circumstances] by researching the
complete history of improvements with respect to a particular parcel of property and
painstakingly obtaining waivers of lien from each contractor, subcontractor, materials supplier,
and laborer." Id. at 322.
The majority also concludes that attributing delays in recording by the register of deeds to
lien claimants would lead to absurd and unfair results not contemplated by the Legislature. I
-5-
agree that the Legislature likely did not contemplate that the register of deeds would fail to
timely perform the duties imposed on the register by statute. However, departure from the literal
construction of the Construction Lien Act is a diversion from this Court's proper task of
determining the Legislature's expressed intent. People v McIntire, 461 Mich 147, 156, n 2; 599
NW2d 102 (1999). As such, I cannot accept the majority's conclusion that the rules of statutory
construction permit the tacit understanding that the term "recorded" in the act really means filed.
Macomb Co Prosecutor, supra. A goose simply is not a duck, even if it may sound as though it
has a quack.
Where a lien claimant files the claim before the ninety-day recording deadline (as
Central, KSI, and Cappy did in this case), the lien claimant is not without remedies to ensure
timely recording. The claimant, which unlike all others knows the claim has been filed, can
examine the book of levies before the ninety-day deadline expires to determine whether
recording has occurred. Where the deadline is near expiration and the lien has yet to be
recorded, the lien claimant can request immediate action from the register or seek extraordinary
remedies in the circuit court. In any case, the difficulties attendant in determining whether the
register is timely performing the duties of the office are not justification for this Court to redefine
the commonplace and unambiguous statutory term "recorded." McIntire, supra at 156, n 3. The
policy choice with regard to whether notice under these circumstances should be provided by
recording or filing is best left to the Legislature.
For the above reasons, I would reverse the judgment of the lower court and remand for
entry of an order granting summary disposition in favor of defendant Department of Commerce.
/s/ Kurtis T. Wilder
-6-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.