BAKER (HAYWARD) VS. ABS SERVICES, INC., ET AL.
Annotate this Case
Download PDF
RENDERED: JUNE 18, 2010; 10:00 A.M.
NOT TO BE PUBLISHED
Commonwealth of Kentucky
Court of Appeals
NO. 2009-CA-001058-MR
HAYWARD BAKER, INC.
v.
APPELLANT
APPEAL FROM ELLIOTT CIRCUIT COURT
HONORABLE REBECCA K. PHILLIPS, JUDGE
ACTION NO. 06-CI-00051
ABS SERVICES, INC.; AND
AMERICAN SAFETY CASUALTY
INSURANCE COMPANY
APPELLEES
OPINION
AFFIRMING
** ** ** ** **
BEFORE: NICKELL AND STUMBO, JUDGES; WHITE,1 SENIOR JUDGE.
STUMBO, JUDGE: Hayward Baker, Inc. appeals from Findings of Fact,
Conclusions of Law and Judgment of the Elliott Circuit Court in its action to
recover damages for breach of contract. Baker was awarded $104,000 plus interest
1
Senior Judge Edwin M. White sitting as Special Judge by assignment of the Chief Justice
pursuant to Section 110(5)(b) of the Kentucky Constitution and Kentucky Revised Statutes
(KRS) 21.580.
based on the court’s determination that ABS Services, Inc. improperly failed to pay
for construction work performed by Baker. Baker now argues that the court erred
in failing to determine that it also was entitled to recover from American Safety
Casualty Insurance Company, Inc., which was serving as a surety for ABS
Services, Inc. For the reasons stated below, we affirm the Judgment on appeal.
In 2001, Ray Bell Construction Company, Inc. began serving as
general contractor on the construction of the Medium Security Correctional
Facility in Elliott County, Kentucky. As part of the project, Bell executed a
subcontract with ABS Services, Inc. which provided in relevant part that ABS
would furnish all labor and materials to design and install an approximately 3900
square foot retaining wall. Pursuant to the subcontract, ABS was to provide a
Labor and Material Payment Bond from American Safety to secure ABS’s
obligation to pay for labor and materials associated with its construction of the
retaining wall.
In January and February, 2002, ABS installed the retaining wall.
Sometime thereafter, it became apparent that the wall might be moving or bulging.
The parties decided to monitor the wall to determine what approach, if any, was
required to stabilize it. In February, 2004, Bell and ABS President Anthony Bertas
determined that the wall was continuing to crack or bulge, and that something had
to be done to stabilize the structure.
The parties entered into discussions regarding how best to approach
the repair, and which party would bear the cost of repair. Bell believed that ABS
2
was solely responsible for the defective retaining wall and should bear the entire
cost of the repairs. Conversely, ABS asserted that it bore no responsibility for the
wall repairs, pointing to inadequate soil compaction and improper draining as
causes of the wall’s cracks and bulging. As such, ABS believed that Bell should
pay for the repairs.
Eventually, Bell and ABS agreed to split the cost of the repair. On
April 28, 2005, they executed the “MSE Retaining Wall Rock Anchor Stabilization
Agreement” (hereinafter “Repair Agreement”),2 which stated in relevant part that
Bell and ABS would equally share the cost of the repair, and that American Safety
was not a party to the Agreement. The Repair Agreement also stated that it
represented their entire agreement, that no other agreement would be recognized,
and that all previous communications and conduct were merged and integrated into
the Agreement.
In order to complete the repair work, ABS retained the Appellant,
Hayward Baker, Inc., a construction company with expertise in mechanically
stabilized retaining wall design and construction. In April, 2005, ABS and Baker
executed a contract stating that Baker was to provide the equipment and personnel
to complete the repair, and that the personnel would be working under the direction
of ABS.
Baker subsequently completed the remediation, and submitted an
invoice to ABS for its costs in the amount of $104,000. When ABS did not pay
2
The circuit court and American Safety employ the term “Repair Agreement” to describe this
agreement, whereas Baker uses the term “Stabilization Agreement.”
3
Baker, Baker filed the instant action against ABS seeking damages arising under
the April, 2005 agreement. Baker also sought recovery from American Safety as
surety.
The action proceeded to a bench trial in Elliott Circuit Court. After
taking proof, the court rendered its Findings of Fact, Conclusions of Law and
Judgment on April 30, 2009, ruling in favor of Baker on its claim against ABS.
The court went on, however, to deny Baker’s claim as against American Safety,
holding that Baker’s work was performed pursuant to the Repair Agreement
between Bell and ABS to which American Safety was not contracted as surety. In
denying Baker’s claim against American Safety, the court determined that the
repair work was not required as a result of ABS’s original work on the wall; that it
was performed pursuant to the separate Repair Agreement; and, that the
subcontract between Bell and ABS was terminated prior to ABS undertaking
repairs on the wall. This appeal followed.
Baker now argues that the Elliott Circuit Court erred in failing to
render a Judgment in its favor against American Safety. It contends that the court
improperly failed to find that the labor and materials payment bond executed for
the construction project covers not only the original contract work, but also the
remedial work necessary as a result of the original work being defective. That is,
Baker maintains that the payment bond between ABS and American Safety, which
was executed pursuant to the original contract between Bell and ABS, should cover
the remedial work performed by Baker to repair the defective wall. Baker argues
4
that public policy discourages allowing a paid surety to avoid liability under a
payment bond, and that the bond should be construed liberally to effectuate the
purpose for which it was given. Baker also directs our attention to case law which
it claims stands for the proposition that any ambiguity in a payment bond should be
construed most strongly against a compensated surety. Baker argues that the
payment bond continues until the project is completed, and that American Safety’s
approval was not required for Baker to engage in the remediation. In sum, Baker
contends that the Repair Agreement was not a contract for new work, but was
simply a settlement agreement or change order required to complete the project
work.
In response, American Safety argues that the trial court properly
determined that Baker’s work – which was not part of the original subcontract
agreement between Bell and ABS – was not covered by American Safety’s bond.
It contends that under Kentucky law, the scope of a surety’s liability is not
determined by the demands of third parties, but by the terms of the bond. It notes
that the bond at issue expressly relates solely to the contract between Bell and
ABS, and further expressly provides coverage only as to Bell’s subcontractors.
American Safety points out that it is not a party to either the Repair Agreement or
the contract executed by ABS and Baker, and that the bond only covers work
performed under the subcontract between Bell and ABS.
We have closely examined the record and the law, and find no basis
for disturbing the Judgment on appeal. In denying Baker the relief it sought as
5
against American Safety, the court first determined that no formal determination of
fault was ever sought or made by the parties prior to the commencement of the
repair project. Based on this finding, in conjunction with Bertas’ adamant opinion
that the problems experienced in 2005 were distinct and separate from any issues
which arose during the construction of the wall, the court opined that the repairs
undertaken by ABS and Baker did not arise from, nor were part of, the subcontract.
The court went on to find that the repair work resulted from the
Repair Agreement, which was separate and distinct from the subcontract. The
Repair Agreement, it found, expressly stated that no other agreement would be
recognized and that all previous communications and conduct were deemed
merged in and superceded by the Repair Agreement. And finally, the court found
substantial evidence upon which it concluded that the subcontract had been fully
terminated at the end of March, 2005, which was before the repair work had been
undertaken.
We find no error in the court’s determinations on these issues. A trial
court’s findings of fact will not be disturbed if they are supported by substantial
evidence. CR 52.01; Owens-Corning Fiberglas Corporation v. Golightly, 976
S.W.2d 409 (Ky. 1998). The conclusions of law which are based on those findings
are subject to de novo review on appeal. Gosney v. Glenn, 163 S.W.3d 894 (Ky.
App. 2005). Substantial evidence is found in the record in support of the trial
court’s conclusion that the defects in the wall which were corrected by Baker’s
anchor stabilization project were not the result of deficiencies in the work of ABS
6
during the wall construction project. Bertas testified that the problems experienced
in 2005 were separate and distinct from any issues which arose during the
construction of the wall. Additionally, no determination of fault was sought or
made by the parties prior to the commencement of the repair project, and the
parties agreed to split the cost of repairs. It is also noteworthy that Baker’s
installation of anchors was not part of the original design nor encompassed by the
subcontract upon which American Safety served as surety.
Furthermore, the Repair Agreement contained a merger clause
expressly stating that the agreement constituted the “entire agreement with regard
to the work contemplated and no other agreement will be recognized in that all
previous communications and conduct shall be deemed merged in, integrated, and
superseded by this Agreement.” In addition, neither Baker nor American Safety
were parties to the Repair Agreement. The court properly concluded that the
parties could have incorporated provisions of the subcontract into the Repair
Agreement, but chose not to.
Finally, the court relied in part on its determination that the
subcontract had terminated prior to the execution of the Repair Agreement and
before any repair work had commenced. Bertas produced a letter from Bell to
ABS dated March 28, 2005, stating that, “[T]his letter will serve as formal, written
notice of the termination of the ABS Services, Inc. subcontract.” The letter went
on to give ABS 48 hours to cure a purported default by conducting repairs on the
wall. Testimony was adduced that ABS undertook no such repairs during those 48
7
hours, thus providing substantial evidence in support of the court’s conclusion that
the subcontract was terminated at the end of March, 2005. American Safety’s
liability, if any, arose from a bond agreement which referenced only the
subcontract. Irrespective of whether the subcontract terminated in March of 2005,
though, the trial court concluded that the “language of the merger clause clearly
indicates that the terms and/or conditions of any other agreements or of any other
understandings or actions were not to govern or control the repair work being
performed. This language obviously encompasses the subcontract. As such, the
Payment Bond is inapplicable to the debt owed by ABS to Hayward Baker.”
This conclusion is supported by substantial evidence of record.
American Safety’s bond expressly limited claimants to persons providing “labor,
material, or both, used or reasonably required for use in the performance of the
Contract.” The contract to which the bond language refers is the subcontract
between Bell and ABS dated November 27, 2001. As testimony and documentary
evidence exists to support the conclusion that the Repair Agreement under which
ABS and Baker were operating was a wholly separate and distinct agreement from
the subcontract under which American Safety was providing coverage, we find no
error in the trial court’s conclusion that Baker is not entitled to recovery as against
American Safety.
For the foregoing reasons, we affirm the Findings of Fact,
Conclusions of Law and Judgment of the Elliott Circuit Court.
ALL CONCUR.
8
BRIEFS FOR APPELLANT:
Gerald L. Stovall
Brian A. Veeneman
Louisville, Kentucky
BRIEF FOR APPELLEE,
AMERICAN SAFETY CASUALTY
INSURANCE COMPANY:
Thomas E. Roma, Jr.
Louisville, Kentucky
9
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.