BAILEY ENGINEERS, INC. v. JST ACQUISITION COMPANY, L.L.C., No. 2:2011cv00063 - Document 17 (W.D. Pa. 2011)

Court Description: MEMORANDUM OPINION AND ORDER granting 11 Motion to Dismiss Complaint; denying as moot 4 Motion for Preliminary Injunction; and denying as moot 9 Motion for TRO, as explained therein. Signed by Judge Terrence F. McVerry on 4/19/11. (mh, )

Download PDF
IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF PENNSYLVANIA BAILEY ENGINEERS INC., Plaintiff, v. JST ACQUISITION COMPANY, L.L.C., Defendant. ) ) ) ) 2:11-cv-00063 ) ) ) ) ) MEMORANDUM OPINION AND ORDER OF COURT Presently pending before the Court for disposition is the DEFENDANT S MOTION TO DISMISS COMPLAINT (Doc. No. 11), with brief in support (Doc. No. 12) filed by Defendant JST Acquisition Company, L.L.C. ( JST or Defendant ). Plaintiff Bailey Engineers, Inc. filed a Response in Opposition (Doc. No. 15), and Defendant filed a reply brief (Doc. No. 16). Accordingly, the motions are now fully briefed and ripe for disposition. BACKGROUND On August 30, 1996, Plaintiff and PVS Chemicals, Inc. ( PVS ), Defendant s predecessor-in-interest, entered into an Operating Agreement to organize and manage a jointventure, Bailey-PVS Oxides, L.L.C. ( BPO ), a Michigan limited liability company that the parties co-own as fifty percent (50%) members. PVS transferred its membership interest in BPO to Defendant in 2002. Thereafter, on August 6, 2010, representatives of Plaintiff and Defendant met to discuss BPO. At the meeting, Defendant requested that Plaintiff consent to the voluntary dissolution of BPO, and Plaintiff disputed whether voluntary dissolution was permissible under the terms of the Operating Agreement. Defendant then stated that it would seek to dissolve BPO and Plaintiff advised that it would dispute whether sufficient ground existed for the dissolution. To settle this dispute, Defendant initiated an arbitration proceeding with the American Arbitration Association on January 4, 2011. The Operating Agreement, Article XI, outlines the procedures that a party must follow to dissolve the company. The Operating Agreement also contains a provision for the Settlement of Disputes, which mandates that the parties arbitrate any dispute that arises as follows: Section 13.1 Settlement of Disputes. If any dispute or difference shall arise among the Members touching on any clause, matter or thing contained in this Operating Agreement or the operation or construction of this Agreement, any matter or thing in any way connected with this Agreement or the rights, duties or liabilities of any party under or in connection with this Agreement, then and in every such case, the dispute or difference shall be referred to . . . arbitration proceedings . . . (Doc. No. 4-1 at 22-23). The parties disagree as to whether this provision governs their dispute over the dissolution of BPO. On January 18, 2011, Plaintiff initiated this diversity action by the filing of a two-count complaint (Doc. No. 1), seeking declaratory and injunctive relief. Plaintiff avers that Defendant improperly sought dissolution through an arbitration proceeding filed with the American Arbitration Association ( AAA ), which is allegedly outside the context of the Operating Agreement. Moreover, Plaintiff claims that Defendant initiated that proceeding, despite failing to comply with the contractual notice of intent to dissolve and affording Bailey the option to acquire JST s interest in BPO. (Doc. No.1 at 4). Plaintiff also alleges that AAA lacks jurisdiction over the Arbitration Proceeding. In sum, Plaintiff contends as follows: (1) Bailey never contracted with JST, as successor to PVS under the Operating Agreement, to arbitrate claims with regard to dissolution of BPO under Michigan statutory and common law; and (2) under the Operating agreement, the parties contractually limited their ability to obtain dissolution of BPO, waiving the right to seek judicial (or tribunal)-ordered dissolution of the company. (Doc. No. 1 at 6-7). Thus, as Plaintiff claims, 2 a separate non-arbitration procedure contained within the operating agreement governs dissolution of the company. On March 3, 2011, Defendant filed the instant motion to dismiss pursuant to Fed. R. Civ. P. 12(b)(6). Defendant contends that the Complaint must be dismissed because the parties agreed to submit "any dispute or difference . . . touching on any clause, matter or thing contained in this Operating Agreement or the operation or construction of this Agreement, any matter or thing in any way connected with this Agreement . . . to arbitration. Defendant also alleges that the operating agreement touches on every issue raised in [it s] Arbitration Demand, explicitly addressing the dissolution of the partnership, management obligations, and the requirements of the Michigan Limited Liability Company Act. (Doc. No. 12 at 2). STANDARD OF REVIEW A motion to dismiss pursuant to Fed. R. Civ. P. 12(b)(6) challenges the legal sufficiently of the complaint filed by a plaintiff. The United States Supreme Court has held that [a] plaintiff s obligation to provide the grounds of his entitle[ment] to relief requires more than labels and conclusions, and a formulaic recitation of the elements of a cause of action will not do. Bell Atlantic Corp. v. Twombly, 550 U.S. 554, 555 (207) (citing Papasan v. Allain, 478 U.S. 265, 286 (1986)) (alterations in original). The Court must accept as true all well-pleaded facts and allegations, and must draw all reasonable inferences therefrom in favor of the plaintiff. However, as the Supreme Court made clear in Twombly, the factual allegations must be enough to raise a right to relief above the speculative level. Id. The Supreme Court has subsequently broadened the scope of this requirement, stating that only a complaint that states a plausible claim for relief survives a motion to dismiss. Ashcroft v. Iqbal, -- U.S. --, 129 S. Ct. 1937, 1950 (2009) (emphasis added). 3 Thus, after Iqbal, a district court must conduct a two-part analysis when presented with a motion to dismiss for failure to state a claim. Fowler v. UPMC Shadyside, 578 F.3d 203, 210 (3d Cir. 2009). First, the Court must separate the factual and legal elements of the claim. Id. Although the Court must accept all of the complaint s well-pleaded facts as true, [it] may disregard any legal conclusions. Id. at 210-211. Second, the Court must then determine whether the facts alleged in the complaint are sufficient to show that the plaintiff has a plausible claim for relief. In other words, a complaint must do more than allege the plaintiff s entitlement to relief. A complaint has to show such an entitlement with its facts. Id. at 211 (citing Iqbal 129 S. Ct. at 1949). The determination for plausibility will be a context-specific task that requires the reviewing court to draw on its judicial experience and common sense. Id. at 211 (quoting Iqbal 129 S. Ct. at 1950). As a result, pleading standards have seemingly shifted from simple notice pleading to a more heightened form of pleading, requiring a plaintiff to plead more than the possibility of relief to survive a motion to dismiss. Id. at 211. That is, all civil complaints must now set out sufficient factual matter to show that the claim is facially plausible. This then allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged. Id. at 210 (quoting Iqbal, 129 S. Ct. at 1948). However, nothing in Twombly or Iqbal changed the other pleading standards for a motion to dismiss pursuant to Fed. R. Civ. P. 12(b)(6) and the requirements of Fed. R. Civ. P. 8 must still be met. See Phillips v. Co. of Allegheny, 515 F.3d 224, 231 (3d Cir. 2008) (internal citations omitted). Fed. R. Civ. P. 8 requires a showing, rather than a blanket assertion, of entitlement to relief, and contemplates the statement of circumstances, occurrences, and events in support of the claim presented and does not authorize a pleader s bare averment that he wants relief and is 4 entitled to it. Twombly, 550 U.S. at 555 n.3 (internal citations and quotations omitted). Additionally, the Supreme Court did not abolish the Fed. R. Civ. P. 12(b)(6) requirement that the facts must be taken as true and a complaint may not be dismissed merely because it appears unlikely that the plaintiff can prove those facts or will ultimately prevail on those merits. Phillips, 515 F.3d at 231(citing Twombly, 550 U.S. at 553). LEGAL ANALYSIS Under the Federal Arbitration Act (FAA), 9 U.S.C. §§ 1-10, in order to determine whether there is an enforceable arbitration agreement between the parties which would compel arbitration and dismissal of the present action, a court must consider: (1) whether a valid agreement to arbitrate exists between the parties; and (2) whether the specific dispute falls within the substance and scope of that agreement. Trippe Mfg. Co. v. Niles Audio Corp., 401 F.3d 529, 532 (3d Cir.2005) (citations omitted). The FAA also establishes a policy favoring arbitration, requiring that courts rigorously enforce arbitration agreements. Shearson/American Exp., Inc. v. McMahon, 482 U.S. 220, 226 (1987). Here, the Court finds and rules that the Operating Agreement contains a valid agreement to arbitrate, and that the present dispute falls within the scope of that agreement. It is undisputed that § 13.1 of the Operating Agreement reflects a broad agreement to arbitrate. The essence of the current dispute is the dissolution of BPO. Article XI of the Operating Agreement provides for the dissolution procedures that the parties must follow. The Operating Agreement provides that any dispute or difference . . . touching on any clause, matter, or thing contained in [the Agreement] . . . shall be arbitrable. (Doc. No. 4-1 at 22-23). Similarly, in the AAA proceeding JST is seeking a determination of the rights, duties or liabilities of any party under or in connection with [the Operating] Agreement. Pursuant to the Operating Agreement, every such 5 case shall be referred to arbitration. In sum, the Operating Agreement provides for dissolution procedures, and contains a broad arbitration clause. The current dispute falls within the substance and scope of the parties agreement to arbitrate their disputes. CONCLUSION In accordance with the foregoing, the DEFENDANT S MOTION TO DISMISS COMPLAINT (Doc. No. 11) filed by Defendant JST Acquisition Company, L.L.C. will be GRANTED in its entirety. An appropriate Order follows. McVerry, J. 6 IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF PENNSYLVANIA BAILEY ENGINEERS INC., ) ) ) ) 2:11-cv-00063 ) ) ) ) ) Plaintiff, v. JST ACQUISITION COMPANY, L.L.C., Defendant. Order of Court AND NOW, this 19th day of April, 2011, for the reasons set forth in the foregoing Memorandum Opinion, it is hereby ORDERED, ADJUDGED and DECREED that the DEFENDANT S MOTION TO DISMISS COMPLAINT (Doc. No. 11) ) filed by Defendant JST Acquisition Company, L.L.C. is GRANTED. It is further ORDERED that all other outstanding motions are DENIED AS MOOT. The clerk shall docket this case closed. BY THE COURT: /s/ Terrence F. McVerry United States District Court Judge Cc: John M. Smith Email: jmsmith@smithbutzlaw.com Brendan A. O'Donnell Email: bodonnell@smithbutzlaw.com Brian A. Lawton Email: blawton@smithbutzlaw.com Ronald W. Crouch Email: rcrouch@mcguirewoods.com Matthew Monsour Email: mmonsour@mcguirewoods.com 7

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.