Salem Vegas, LP v. Guanci, No. 2:2012cv01892 - Document 157 (D. Nev. 2015)

Court Description: ORDER Granting 148 Motion to Dismiss. IT IS FURTHER ORDERED that Plaintiffs Third Amended Complaint is DISMISSED with prejudice. The Clerk shall enter judgment accordingly and close the case. Signed by Chief Judge Gloria M. Navarro on 6/3/2015. (Copies have been distributed pursuant to the NEF - DC)

Download PDF
Salem Vegas, LP v. Guanci Doc. 157 1 UNITED STATES DISTRICT COURT 2 DISTRICT OF NEVADA 3 4 Salem Vegas, L.P. and Salem Vegas Investments, LLC, Plaintiffs, 5 vs. 6 Anthony Guanci, 7 Defendant. 8 ) ) ) ) ) ) ) ) ) ) Case No.: 2:12-cv-1892-GMN-CWH ORDER 9 10 Presently before the Court is the Motion to Dismiss, (ECF No. 148), filed by Defendant 11 Anthony Guanci. Plaintiffs Salem Vegas, L.P. (“Salem Vegas”) and Salem Vegas Investments, 12 LLC (“SV Investments”) filed a Response in opposition, (ECF No. 149), and Defendant Guanci 13 filed a Reply, (ECF No. 150). For the reasons set forth herein, the Court will grant Defendant 14 Guanci’s Motion and dismiss Plaintiffs’ Third Amended Complaint with prejudice. 15 I. 16 BACKGROUND This case centers upon allegations that Defendant Guanci breached his duties as a 17 partner of Salem Vegas by executing a subordination agreement that may have delayed 18 payments owed to Salem Vegas under a prior loan agreement. (Third Am. Compl., ECF No. 19 147). 20 Salem Vegas is a limited partnership formed under Delaware law by an agreement that 21 was executed in June 2005 (the “Partnership Agreement”). (Third Am. Compl. 2:22-27). The 22 Partnership Agreement named Salem Realty, LLC1 as Salem Vegas’ general partner, and 23 Defendant Guanci, Eugene Kessler, Stuart Kessler, and Jack Kessler as limited partners. (Id. at 24 25 1 Salem Realty was a limited liability company registered in Delaware whose managing members were Defendant Guanci and Stuart Kessler. (Third Am. Compl. 4:1-5). Page 1 of 9 Dockets.Justia.com 1 3:20-27). The Partnership Agreement was formed in order to facilitate the partners’ investment in 2 3 a resort construction project known as “Palms Place Vegas.” (Id. at 2:10-18). The resort was to 4 include “a 50 floor tower . . . consisting of 599 residential for-sale condominium units . . . and 5 common facility areas including a full-service spa, swimming pool, recreation spaces, and shell 6 bar and restaurant spaces.” (Building Loan Agmt. at 8, ECF No. 39-6). The development of the 7 project was overseen by Palms Place, LLC. (Third Am. Compl. 2:15-18). 8 9 Under the terms of the Partnership Agreement, Defendant Guanci had sole authority to negotiate with Palms Place, LLC. (Id. at 4:28-5:2). The Partnership Agreement specifically 10 provided that no “managing person”2 could be held liable for any loss to Salem Vegas except in 11 the case of bad faith, gross negligence, or willful misconduct. (Partnership Agmt. § 9.5, ECF 12 No. 39-3). The Partnership Agreement also contained a provision expressly allowing its 13 members to pursue other business opportunities, stating, “[E]ach Partner may have other 14 business interests and may engage in other activities in addition to those relating to [Salem 15 Vegas], even if such activities may be in competition with the business of [Salem Vegas].” (Id. 16 at § 9.6). 17 In 2005, Defendant Guanci, on behalf of Salem Vegas, executed an agreement (the 18 “Salem Loan”) providing that Salem Vegas would loan a sum of up to 10% of the costs of the 19 Palms Place Project that exceeded the amount provided under an anticipated construction loan. 20 (Salem Loan Agmt. § 2.1, ECF No. 39-4). In return, Salem Vegas was entitled to receive, inter 21 alia, 10% of the proceeds of the sale of each condominium unit. (Id. at § 3). 22 23 In March 2005, before the Salem Loan Agreement was executed, Defendant Guanci had entered into a separate agreement with Palms Place, LLC which provided that Defendant 24 25 “Managing Person” is defined as “a General Partner, an officer of [Salem Vegas] or of the General Partner, and their agents.” (Partnership Agmt. § 1.1, ECF No. 39-3). 2 Page 2 of 9 1 Guanci would advise Palms Place regarding planning, construction, architecture, sales, and 2 entitlements in order to ensure the project’s timely completion (the “Consulting Services 3 Agreement”). (ECF No. 39-2). In return, Palms Place agreed to pay a fee of $1,000,000 to 4 Defendant Guanci that would be distributed in equal monthly installments from the proceeds of 5 the anticipated construction loan. (Id.). Plaintiffs allege that they did not become aware of the 6 Consulting Services Agreement until 2012. (Third Am. Compl., 7:1-6). 7 On March 13, 2006, Palms Place obtained a $240,000,000 loan for the project (the 8 “Building Loan”), funded by Wells Fargo Bank, Bank of Scotland, and JPMorgan Chase Bank 9 (the “Bank Lenders”). (Building Loan Agmt., ECF No. 39-6). The Building Loan Agreement 10 specified that the distribution of these funds was contingent upon Salem Vegas’ agreeing to 11 subordinate its interest under the Salem Loan. (Id. at § 3.1(i)). On that same day, Defendant 12 Guanci executed an agreement (the “Subordination Agreement”), which rendered Salem 13 Vegas’ interest junior to that of the Bank Lenders. (ECF No. 10-4). Plaintiffs claim that they 14 did not become aware of the Subordination Agreement until 2012. (Third Am. Compl. 7:1-6). 15 Plaintiffs allege that Defendant Guanci’s execution of the Subordination Agreement has 16 delayed the repayment of the Salem Loan. (Id. at 8:16-9:9). Plaintiffs’ Second Amended 17 Complaint set forth claims for (1) breach of contract, (2) contractual breach of the implied 18 covenant of good faith and fair dealing, (3) breach of fiduciary duty, and (4) tortious breach of 19 the implied covenant of good faith and fair dealing. (Sec. Am. Compl. 7:19-11:23, ECF No. 20 89). On October 17, 2014, the Court dismissed the latter three claims with prejudice pursuant 21 to Federal Rule of Civil Procedure 12(b)(6). (Order 11:3-4, ECF No. 144). The Court also 22 dismissed Plaintiffs’ breach of contract claim, but after finding that it was not certain that 23 Plaintiffs could not correct deficiencies in the claim through amendment, the Court granted 24 leave for Plaintiffs to file a Third Amended Complaint. 25 Plaintiffs’ Third Amended Complaint was filed on December 3, 2014. In the Third Page 3 of 9 1 Amended Complaint, Plaintiffs re-assert their prior breach of contract claim, set forth a list of 2 previously unaddressed provisions of the contract that they believe Defendant Guanci breached, 3 and allege an entirely new claim for fraud in the inducement. 4 In the instant Motion, Defendant Guanci argues that the new claims in the Third 5 Amended Complaint should be stricken pursuant to Federal Rule of Civil Procedure 15 and that 6 Plaintiffs’ re-asserted breach of contract claim should be dismissed pursuant to Federal Rule of 7 Civil Procedure 12(b)(6). For the reasons discussed herein, the Court will grant the Motion and 8 dismiss the Third Amended Complaint with prejudice. 9 II. 10 LEGAL STANDARD Dismissal is appropriate under Rule 12(b)(6) where a pleader fails to state a claim upon 11 which relief can be granted. Fed. R. Civ. P. 12(b)(6); Bell Atl. Corp. v. Twombly, 550 U.S. 544, 12 555 (2007). A pleading must give fair notice of a legally cognizable claim and the grounds on 13 which it rests, and although a court must take all factual allegations as true, legal conclusions 14 couched as a factual allegation are insufficient. Twombly, 550 U.S. at 555. Accordingly, Rule 15 12(b)(6) requires “more than labels and conclusions, and a formulaic recitation of the elements 16 of a cause of action will not do.” Id. 17 “To survive a motion to dismiss, a complaint must contain sufficient factual matter, 18 accepted as true, to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Iqbal, 556 19 U.S. 662, 678 (2009) (quoting Twombly, 550 U.S. at 555). “A claim has facial plausibility 20 when the plaintiff pleads factual content that allows the court to draw the reasonable inference 21 that the defendant is liable for the misconduct alleged.” Id. This standard “asks for more than a 22 sheer possibility that a defendant has acted unlawfully.” Id. 23 “Generally, a district court may not consider any material beyond the pleadings in ruling 24 on a Rule 12(b)(6) motion.” Hal Roach Studios, Inc. v. Richard Feiner & Co., 896 F.2d 1542, 25 1555 n.19 (9th Cir. 1990). “However, material which is properly submitted as part of the Page 4 of 9 1 complaint may be considered.” Id. Similarly, “documents whose contents are alleged in a 2 complaint and whose authenticity no party questions, but which are not physically attached to 3 the pleading, may be considered in ruling on a Rule 12(b)(6) motion to dismiss” without 4 converting the motion to dismiss into a motion for summary judgment. E.g., Branch v. Tunnell, 5 14 F.3d 449, 454 (9th Cir. 1994). On a motion to dismiss, a court may also take judicial notice 6 of “matters of public record.” Mack v. South Bay Beer Distrib., 798 F.2d 1279, 1282 (9th Cir. 7 1986). Otherwise, if a court considers materials outside of the pleadings, the motion to dismiss 8 is converted into a motion for summary judgment. Fed. R. Civ. P. 12(d). 9 If the court grants a motion to dismiss for failure to state a claim, leave to amend should 10 be granted unless it is clear that the deficiencies of the complaint cannot be cured by 11 amendment. DeSoto v. Yellow Freight Sys., Inc., 957 F.2d 655, 658 (9th Cir. 1992). Pursuant 12 to Rule 15(a), the court should “freely” give leave to amend “when justice so requires,” and in 13 the absence of a reason such as “undue delay, bad faith or dilatory motive on the part of the 14 movant, repeated failure to cure deficiencies by amendments previously allowed, undue 15 prejudice to the opposing party by virtue of allowance of the amendment, futility of the 16 amendment, etc.” Foman v. Davis, 371 U.S. 178, 182 (1962). 17 III. DISCUSSION In the instant Motion, Defendant Guanci argues that Plaintiffs’ newly asserted breach of 18 19 contract theories as well as their claim for fraud in the inducement should be stricken, as 20 Plaintiffs did not receive leave from the Court to assert new claims. Defendant Guanci also 21 argues that Plaintiffs have also failed to sufficiently state a breach of contract claim in regard to 22 /// 23 /// 24 /// 25 /// Page 5 of 9 1 the Subordination Agreement. 3 The Court will address each of these arguments in turn. Defendant Guanci’s Request to Strike Pursuant to Rule 15 2 A. 3 In its October 17, 2014 Dismissal Order, the Court found that Plaintiffs had failed to 4 sufficiently allege that Defendant Guanci’s execution of the Consulting Services Agreement or 5 Subordination Agreement were “so far beyond the bounds of reasonable judgment that [they 6 seemed] essentially inexplicable on any ground other than bad faith.” (Order 7:17-21, 10:4-8, 7 ECF No. 144). In light of these findings, the Court dismissed Plaintiffs’ breach of contract 8 claim without prejudice and granted leave for Plaintiffs to file the Third Amended Complaint. 9 (Id. at 8:3-5, 10:9-11, 11:7-9). 10 In addition to re-stating their prior breach of contract claim, Plaintiffs, without 11 requesting leave, assert for the first time that Defendant Guanci failed to sufficiently contribute 12 capital as required by Section 4.2 of the Partnership Agreement, failed to adequately maintain 13 books and records in violation of Section 8.1 of the Partnership Agreement, and failed to 14 maintain Salem Realty’s corporate existence in violation of Section 9.1 of the Partnership 15 Agreement. (Third Am. Compl. 9:11-15). Plaintiffs also set forth an entirely new cause of 16 action for fraud in the inducement. (Id. at 10:11-12:9). 17 Under Rule 15 of the Federal Rules of Civil Procedure, a party may amend his pleading 18 once as a matter of course within twenty-one days after serving it, or after a pleading or motion 19 responsive to it has been filed, whichever is earlier. Fed. R. Civ. Proc. 15(a). In all other cases, 20 a party can amend his pleading only with the opposing party’s written consent, or leave of 21 22 23 24 25 3 As each is expressly relied upon by the Third Amended Complaint and no party questions their authenticity, the Court takes judicial notice of the Partnership Agreement (ECF No. 39-3), the Consulting Services Agreement (ECF No. 39-2), the Salem Loan Agreement (ECF No. 39-4), the Subordination Agreement (ECF No. 10-4), and the Building Loan Agreement (ECF Nos. 39-6, 39-7, 39-8). See, e.g., Swartz v. KPMG LLP, 476 F.3d 756, 763 (9th Cir. 2007) (“[I]n order to prevent plaintiffs from surviving a Rule 12(b)(6) motion by deliberately omitting documents upon which their claims are based, a court may consider a writing referenced in a complaint but not explicitly incorporated therein if the complaint relies on the document and its authenticity is unquestioned.”) (internal quotations omitted). Page 6 of 9 1 court. Fed. R. Civ. Proc. 15(a)(2). The Court’s October 17, 2014 Dismissal Order granted 2 Plaintiffs leave to amend only to address the deficiencies in the specified claim. It did not grant 3 leave to add new claims for relief. Plaintiffs were therefore required to seek leave of the court 4 or Defendant Guanci’s written consent prior to asserting new claims for breach of contract or 5 fraud. Thus, Court finds that the addition of the new breach of contract and fraud claims 6 exceeds the scope of Plaintiffs’ leave to amend, and these claims will therefore be stricken. See, 7 e.g., Benton v. Baker Hughes, No. 12-cv-7735-MMM-MRWX, 2013 WL 3353636, at *2-3 8 (C.D. Cal. June 30, 2013); DeLeon v. Wells Fargo Bank, N.A., No. 10-cv-1390-LHK, 2010 WL 9 4285006, at *3 (N.D. Cal. Oct. 22, 2010); PB Farradyne, Inc. v. Peterson, No. 05-cv-3447-SI, 10 2006 WL 2578273, at *3 (N.D. Cal. Sept. 6, 2006). 11 B. 12 In their Response to the instant Motion, Plaintiffs acknowledge that the Third Amended Rule 12(b)(6) Dismissal 13 Complaint does not contain any new factual allegations to support their claim that Defendant 14 Guanci breached the Partnership Agreement by executing the Subordination Agreement. (Resp. 15 4:3-4, ECF No. 149). Nonetheless, Plaintiffs assert that the totality of Defendant Guanci’s 16 actions, rather than one discrete act, illustrate that Defendant Guanci carried out an intricate 17 scheme to “induce [Plaintiff Salem Vegas] to make a loan that [Defendant Guanci] knew would 18 not be repaid.” (Id. at 5:8-9). However, as this assertion disregards the requirements for a 19 breach of contract claim in the partnership context under Delaware law, it is not sufficient to 20 overcome Defendant’s Motion to Dismiss. 21 As an initial matter, the Court has already ruled that Plaintiffs’ claims are governed by 22 Delaware law, and therefore consults Delaware statutes and decisions of Delaware courts in 23 determining whether dismissal is warranted. (See Order 5:10-13, ECF No. 144). Similarly, the 24 Court has already recognized that Section 9.5 of the Partnership Agreement precluded 25 individual liability except in cases of bad faith; therefore Plaintiffs must allege that Defendant Page 7 of 9 1 Guanci’s acts amounted to bad faith in order to sufficiently state a claim for relief. (Id. at 8:2). 2 In its October 17, 2014 Dismissal Order, the Court relied upon Brinckerhoff v. Enbridge 3 Energy Company in finding that Plaintiffs had failed to sufficiently state a claim that Defendant 4 Guanci breached the Partnership Agreement. 67 A.3d 369, 373 (Del. 2013). Brinckerhoff 5 involved claims for express and implied breaches of a partnership agreement based on 6 allegations that a managing partner had improperly allowed its owner to fund a portion of the 7 partnership’s business venture in exchange for a share of the profits. Id. at 370-71. The 8 Delaware Supreme Court held that a claim for bad faith in the context of a partnership 9 agreement requires allegations showing that a business decision was “so far beyond the bounds 10 of reasonable judgment that it seems essentially inexplicable on any ground other than bad 11 faith.” Id. at 373 (quoting Parnes v. Bally Entm’t Corp., 722 A.2d 1243, 1246 (Del. 1999)). 12 The Brinckerhoff Court went on to find that the plaintiff had failed to sufficiently state a claim 13 because the complaint did not “directly or by inference” indicate that the profit-sharing 14 agreement was not simply a good-faith business transaction. Id. 15 After observing that the Building Loan Agreement expressly required that the interests 16 of the Bank Lenders be made senior to those of other lenders involved in the Palms Place 17 Project, the Court, in its October 17, 2014 Dismissal Order, held that Plaintiffs had failed to 18 sufficiently allege that Defendant Guanci’s decision to execute the Subordination Agreement 19 was inexplicable on any ground other than bad faith. (Order 9:11-21). Indeed, the fact that 20 most of the funding for the Palms Place Project might not have been obtained if Defendant 21 Guanci had refused to execute the Subordination Agreement stands as a reasonable explanation 22 for Defendant Guanci’s actions that does not, in any way, indicate bad faith. 23 Plaintiffs argue that Defendant Guanci’s alleged failure to properly disclose the 24 Consulting Services Agreement coupled with his position as the only individual who could 25 negotiate with Palms Place, LLC on Salem Vegas’ behalf implies that the Subordination Page 8 of 9 1 Agreement was executed solely to ensure that Defendant Guanci received payment prior to 2 Plaintiffs. (Resp. 4:15-5:18). However, this theory regarding the Defendant Guanci’s 3 motivation is immaterial to the question at hand. Pursuant to Brinckerhoff, Plaintiffs must set 4 forth factual allegations showing that the decision to execute the Subordination Agreement was 5 so unreasonable that it appears “essentially inexplicable on any ground other than bad faith.” 67 6 A.3d at 373 (emphasis added). Plaintiffs’ allegations speak only to Defendant Guanci’s 7 subjective reason for executing the Subordination Agreement and not whether the decision was 8 objectively unreasonable. Because the Third Amended Complaint fails to sufficiently allege 9 that Defendant Guanci’s acts were beyond the bounds of reasonable judgment, Plaintiffs have 10 failed to state claim upon which relief can be granted. Accordingly, Defendant Guanci’s 11 Motion to Dismiss will be granted. As Plaintiffs have failed to state a claim after being given 12 leave to amend, the dismissal will be with prejudice. 13 IV. 14 15 16 CONCLUSION IT IS HEREBY ORDERED that Defendant Guanci’s Motion, (ECF No. 148), is GRANTED. IT IS FURTHER ORDERED that Plaintiffs’ claim for fraud in the inducement, (Third 17 Am. Compl. 10:10-12:9), as well as their additional breach of contract claims, (Third Am. 18 Compl. 9:11-15), are STRICKEN. 19 20 IT IS FURTHER ORDERED that Plaintiffs’ Third Amended Complaint is DISMISSED with prejudice. 21 The Clerk shall enter judgment accordingly and close the case. 22 DATED this 3rd day of June, 2015. 23 24 25 ___________________________________ Gloria M. Navarro, Chief Judge United States District Court Page 9 of 9

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.