West Charleston Lofts I, LLC et al., v. R&O Construction Company, No. 2:2009cv00392 - Document 289 (D. Nev. 2013)

Court Description: ORDER Denying 243 Third Party Defendant Park 209 LLC's Motion to Dismiss and 248 Third Party Defendant Suzanne Renee West's Joinder. IT IS FURTHER ORDERED that 257 Third Party Defendant Thom Antonopouloss Motion to Dismiss and 261 Third Party Defendant Suzanne Renee Wests Joinder are hereby DENIED. Signed by Judge Philip M. Pro on 01/15/2013. (Copies have been distributed pursuant to the NEF - AC)

Download PDF
West Charleston Lofts I, LLC et al., v. R&O Construction Company Doc. 289 1 2 3 UNITED STATES DISTRICT COURT 4 DISTRICT OF NEVADA 5 6 7 WEST CHARLESTON LOFTS I, LLC and WCL COMMERCIAL, LLC, Plaintiffs, 8 9 10 v. R&O CONSTRUCTION COMPANY, Defendant. 11 12 13 AND ALL RELATED THIRD PARTY CLAIMS. *** ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) 2:09-cv-00392-PMP-VCF ORDER 14 Presently before the Court is Third Party Defendant Park 209 LLC’s (“Park 209”) 15 16 Motion to Dismiss (Doc. #243) supported by a Request for Judicial Notice (Doc. #244), 17 filed on November 6, 2012. Third Party Defendant Suzanne Renee West (“West”) filed a 18 Joinder (Doc. #248) on November 14, 2012. Third Party Plaintiff R&O Construction 19 Company (“R&O”) filed an Opposition (Doc. #255) on November 21, 2012. Park 209 filed 20 a Reply (Doc. #263) on December 5, 2012. West filed a Joinder (Doc. #266) on December 21 19, 2012. 22 Also before the Court is Third Party Defendant Thom Antonopoulos’s 23 (“Antonopoulos”) Motion to Dismiss (Doc. #257) supported by a Request for Judicial 24 Notice (Doc. #258), filed on November 26, 2012. West filed a Joinder (Doc. #261) 25 supported by a Request for Judicial Notice (Doc. #262) on November 29, 2012. R&O filed 26 an Opposition (Doc. #264) on December 13, 2012. Antonopoulos filed a Reply (Doc. Dockets.Justia.com 1 #274) on December 24, 2012. The Court held a hearing on these motions on January 7, 2 2013. (Mins. of Proceedings (Doc. #284).) 3 I. BACKGROUND R&O performed work at the West Charleston Lofts Project (the “Project”) for 4 5 which it was not completely paid. (Am. Third Party Compl. (Doc. #187) at 7.) A 6 deficiency of approximately $682,595 remains. (Id. at 8.) R&O filed Notices of Lien 7 against the Project in January 2009. (Id.) R&O alleges that it sent copies of the Notices of 8 Lien to the respective condominium owners in West Charleston Lofts. (Id.) R&O further 9 alleges that it complied with Nevada Revised Statutes §§ 108.221-.246 in serving and 10 recording the Notices of Lien. (Id.) According to the Amended Third Party Complaint, 11 “[a]ny subsequent purchasers of the condominium units at the Project have taken title with 12 record notice of R&O’s mechanics liens.” (Id.) Through the Amended Third Party 13 Complaint, R&O asserts claims for foreclosure on mechanic’s liens and unjust enrichment 14 against various subsequent purchasers of condominium units at the Project. (Id. at 8-10.) Third Party Defendants Park 209, Antonopoulos, and West are unit owners at 15 16 West Charleston Lofts. Park 209 and Antonopoulos move for dismissal, and West joins the 17 Motions. The Third Party Defendants argue that R&O cannot pursue a foreclosure claim 18 against them because R&O failed to file a notice of pendency of action as required by the 19 Nevada mechanic’s lien statutes. The Third Party Defendants also argue that because R&O 20 failed to file a notice of pendency of action, R&O’s recorded Notice of Lien expired after 21 six months and cannot serve as record notice. Finally, Antonopoulos argues he is a bona 22 fide purchaser for value without notice. As to the unjust enrichment claim, the Third Party 23 Defendants argue an unjust enrichment claim is inappropriate because a written contract 24 existed between R&O and West Charleston Lofts, and because the Third Party Defendants 25 did not request or agree to allow R&O to perform any work for them. 26 /// 2 1 R&O responds that failure to file a notice of pendency of action does not 2 automatically preclude suit on the lien so long as the other party had actual or constructive 3 notice of the lien. R&O argues that other recorded documents--specifically a Notice of 4 Discharge, a Notice of Appeal, and a Notice of Appellate Ruling--serve the functional 5 equivalent of a notice of pendency of action. R&O contends the Third Party Defendants 6 thus had constructive notice of R&O’s lien. R&O also argues Park 209 had actual notice of 7 R&O’s liens through its managing member. R&O further asserts the Notice of Lien did not 8 expire because a lien expires only if no action to foreclose on the lien is commenced within 9 six months after recording the lien. R&O contends it recorded the liens on January 2, 2009 10 and filed a foreclosure action on March 11, 2009, and thus its Notice of Lien did not expire. 11 As to Antonopoulos’s status as a bona fide purchaser without notice, R&O argues this is an 12 affirmative defense for which Antonpoulos and the other Third Party Defendants bear the 13 burden of proof, and thus this issue is not suitable for determination on a motion to dismiss 14 for failure to state a claim. 15 As to the unjust enrichment claim, R&O responds that the existence of an express 16 written contract bars an unjust enrichment claim only when the agreement exists between 17 the plaintiff and the defendant. R&O contends that because there was no express agreement 18 between R&O and the Third Party Defendants, the unjust enrichment claim is not barred. 19 II. MOTIONS TO DISMISS 20 In considering a motion to dismiss, “all well-pleaded allegations of material fact 21 are taken as true and construed in a light most favorable to the non-moving party.” Wyler 22 Summit P’ship v. Turner Broad. Sys., Inc., 135 F.3d 658, 661 (9th Cir. 1998). However, 23 the Court does not necessarily assume the truth of legal conclusions merely because they are 24 cast in the form of factual allegations in the plaintiff’s complaint. See Clegg v. Cult 25 Awareness Network, 18 F.3d 752, 754-55 (9th Cir. 1994). There is a strong presumption 26 against dismissing an action for failure to state a claim. Ileto v. Glock Inc., 349 F.3d 1191, 3 1 1200 (9th Cir. 2003). A plaintiff must make sufficient factual allegations to establish a 2 plausible entitlement to relief. Bell Atl. Corp. v Twombly, 550 U.S. 544, 556 (2007). 3 Such allegations must amount to “more than labels and conclusions, [or] a formulaic 4 recitation of the elements of a cause of action.” Id. at 555. 5 A. Filing a Notice of Pending Action 6 “A mechanic’s lien is a statutory creature established to help ensure payment for 7 work or materials provided for construction or improvements on land.” In re Fontainebleau 8 Las Vegas Holdings, 289 P.3d 1199, 1210 (Nev. 2012). Pursuant to Nevada Revised 9 Statutes § 108.239(1), a notice of lien may be enforced by a lawsuit in which the complaint 10 sets forth the demand and a description of the property charged with the lien. Pursuant to 11 § 108.239(2), the party seeking to enforce the lien “shall,” among other things, “[a]t the 12 time of filing the complaint and issuing the summons . . . [f]ile a notice of pendency of the 13 action in the manner provided in NRS 14.010.” 14 Section 14.010 provides: 15 1. In an action for the foreclosure of a mortgage upon real property, or affecting the title or possession of real property, the plaintiff, at the time of filing the complaint . . . shall record with the recorder of the county in which the property, or some part thereof, is situated, a notice of the pendency of the action, containing the names of the parties, the object of the action and a description of the property in that county affected thereby . . . . 2. A notice of an action affecting real property, which is pending in any United States District Court for the District of Nevada may be recorded and indexed in the same manner and in the same place as provided with respect to actions pending in courts of this state. 3. From the time of recording only, . . . the pendency of the action is constructive notice to a purchaser or encumbrancer of the property affected thereby. In case of the foreclosure of the mortgage, all purchasers or encumbrancers, by unrecorded deed or other instrument in writing made before the recording of the notice, and after the date of the mortgage, shall be deemed purchasers or encumbrancers after the recording of the notice, and subject thereto, unless NRS 14.017 is applicable or they can show that, at the time of recording the notice, the plaintiff had actual notice of the purchase or encumbrance. 16 17 18 19 20 21 22 23 24 25 26 Section 14.017 provides that upon withdrawal of a notice of pendency of action, even 4 1 someone who had actual knowledge shall be deemed to be without notice of the lien to 2 allow for transferability of real property after a notice of pendency of action is withdrawn. 3 Nevada has not specifically addressed whether failure to file a notice of pendency 4 of action precludes suit on the lien. The Court therefore must predict what Nevada would 5 do. “Where the state’s highest court has not decided an issue, the task of the federal courts 6 is to predict how the state high court would resolve it.” Giles v. Gen. Motors Acceptance 7 Corp., 494 F.3d 865, 872 (9th Cir. 2007) (quotation omitted). “In answering that question, 8 this court looks for ‘guidance’ to decisions by intermediate appellate courts of the state and 9 by courts in other jurisdictions.” Id. (quotation omitted). 10 Although § 108.239(2) states a lienholder “shall” file a notice of pendency of 11 action, that section does not specify the consequences for failure to do so. However, 12 § 108.239(2) refers to § 14.010, which provides for the consequence: constructive notice is 13 not imparted until the notice of pendency of action is recorded. Nothing in the statutory 14 language suggests that failure to record the notice precludes suit on the claim. Rather, the 15 consequence of the failure to record is the lienholder subjects himself to potential bona fide 16 purchaser for value defenses for lack of constructive notice. 17 This conclusion is consistent with other Nevada case law which holds that failure 18 to file a pre-lien notice under Nevada Revised Statutes § 108.245, which also uses the word 19 “shall,” does not bar suit on the lien where the other party had actual notice of the potential 20 lien claim and the other party was not prejudiced by failure to receive the statutory notice. 21 Fondren v. K/L Complex, Ltd., 800 P.2d 719, 721-22 (Nev. 1990). It also is consistent with 22 the purpose of recording a notice of pending action, which is “to cloud title before a sale of 23 property occurs so that the claims of a party may be resolved before transfer of title.” 24 Coury v. Tran, 895 P.2d 650, 653 (Nev. 1995) (emphasis omitted). 25 Consequently, failure to file a notice of pendency of action does not deprive the 26 Court of jurisdiction over the matter or otherwise preclude suit on the lien. Rather, failure 5 1 to file the notice merely affects whether subsequent purchasers had actual or constructive 2 notice of the lien. See Patten-Blinn Lumber Co. v. Francis, 333 P.2d 255, 257-60 (Cal. Ct. 3 App. 1958) (interpreting a similar provision in California law); Pitt v. Rodgers, 104 F. 387, 4 390 (9th Cir. 1900) (stating that under a prior version of the Nevada statute, “purchasers are 5 not charged with constructive notice of the pendency of an action affecting the title to real 6 estate, unless at the date of their purchase there is on file with the recorder of the county in 7 which the property is situated a notice of the pendency of such action”). The Court 8 therefore will deny the Third Party Defendants’ Motions on this basis. B. Bona Fide Purchaser Without Notice 9 The parties’ arguments regarding whether the Third Party Defendants took 10 11 without actual or constructive notice are premature in the context of a motion to dismiss for 12 failure to state a claim. Bona fide purchaser status is an affirmative defense for which the 13 Third Party Defendants bear the burden of proof. Nev. Rev. Stat. § 111.325; Berge v. 14 Fredericks, 591 P.2d 246, 247-48 (Nev. 1979). R&O need not anticipate and plead facts to 15 defeat an affirmative defense to survive a motion to dismiss for failure to state a claim. 16 Indep. Trust Corp. v. Stewart Info. Servs. Corp., 665 F.3d 930, 935 (7th Cir. 2012); Fed. R. 17 Civ. P. 8(a), (c). The Court therefore will deny the Third Party Defendants’ Motions on this 18 basis. 19 C. Unjust Enrichment 20 Under Nevada law, unjust enrichment “occurs whenever a person has and retains 21 a benefit which in equity and good conscience belongs to another.” In re Amerco 22 Derivative Litig., 252 P.3d 681, 703 (Nev. 2011) (quotation omitted); Leasepartners Corp. 23 v. Robert L. Brooks Trust Dated Nov. 12, 1975, 942 P.2d 182, 187 (Nev. 1997). An unjust 24 enrichment claim cannot lie where an express written contract exists “because no agreement 25 can be implied when there is an express agreement.” Leasepartners, 942 P.2d at 187. 26 /// 6 1 Although a written agreement existed between R&O and West Charleston Lofts, 2 no agreement existed between R&O and any of the Third Party Defendants. Under 3 Leasepartners, an unjust enrichment claim may lie under these circumstances. See id. at 4 183-85, 187. Consequently, R&O’s unjust enrichment claim against the Third Party 5 Defendants is not precluded based on the existence of a written agreement between R&O 6 and West Charleston Lofts. The Court therefore will deny the Third Party Defendants’ 7 Motions on this basis. 8 Finally, the Court disagrees with the Third Party Defendants’ interpretation of 9 Certified Fire Protection, Inc. v. Precision Construction, Inc., 283 P.3d 250 (Nev. 2012). 10 The Third Party Defendants contend that under Certified, a required element of any unjust 11 enrichment claim is that the benefit must be conferred at the defendant’s request. Certified 12 states: “Quantum meruit, then, is the usual measurement of enrichment in cases where 13 nonreturnable benefits have been furnished at the defendant’s request, but where the parties 14 made no enforceable agreement as to price.” 283 P.3d at 257 (quotation omitted). 15 However, Certified does not set forth a rule of law that in all unjust enrichment cases, the 16 benefit conferred must be at the defendant’s request. Rather, Certified dealt with whether a 17 benefit was conferred where the defendant could not use any of the plaintiff’s work to 18 complete the project. Id. at 258. 19 Requiring that the benefit be conferred at the defendant’s request as a necessary 20 element of an unjust enrichment claim would conflict with other Nevada Supreme Court 21 authority. The defendant in Leasepartners had not requested the work performed by the 22 plaintiff. 942 P.2d at 183-85, 187-88. The Nevada Supreme Court nevertheless found the 23 plaintiff had a potentially viable unjust enrichment claim. Id. at 187-88. Leasepartners 24 neither stated nor applied a rule that the benefit must be conferred at the defendant’s 25 request. If the Nevada Supreme Court intended to overrule Leasepartners on this point, it 26 would have said so. The Court therefore will deny the Third Party Defendants’ Motions to 7 1 Dismiss on this basis. 2 III. CONCLUSION 3 IT IS THEREFORE ORDERED that Third Party Defendant Park 209 LLC’s 4 Motion to Dismiss (Doc. #243) and Third Party Defendant Suzanne Renee West’s Joinder 5 (Doc. #248) are hereby DENIED. 6 IT IS FURTHER ORDERED that Third Party Defendant Thom Antonopoulos’s 7 Motion to Dismiss (Doc. #257) and Third Party Defendant Suzanne Renee West’s Joinder 8 (Doc. #261) are hereby DENIED. 9 10 11 12 DATED: January 15, 2013 _______________________________ PHILIP M. PRO United States District Judge 13 14 15 16 17 18 19 20 21 22 23 24 25 26 8

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.