Central Coast Pipe Lining Inc v. Pipe Shield USA Inc et al, No. 2:2013cv00639 - Document 22 (C.D. Cal. 2013)

Court Description: ORDER GRANTING IN PART AND DENYING IN PART DEFENDANTS MOTION TO DISMISS 17 by Judge Otis D. Wright, II: Defendants Motion is DENIED with respect to Central Coasts first claim and GRANTED as to Plaintiffs second through seventh claims. Since Central Coast had several attempts to strengthen its allegations but continually failed, the second through seventh claims are DISMISSED WITH PREJUDICE. Defendants shall file an answer within 14 days of this order. (lc). Modified on 4/19/2013 .(lc).

Download PDF
Central Coast Pipe Lining Inc v. Pipe Shield USA Inc et al Doc. 22 O 1 2 3 4 5 6 7 8 UNITED STATES DISTRICT COURT 9 CENTRAL DISTRICT OF CALIFORNIA 10 11 12 13 14 15 16 CENTRAL COAST PIPE LINING, INC., v. Plaintiff, PIPE SHIELD USA, INC.; PIPE SHIELD SERVICES, LTD.; B.G. ARNOLD SERVICES T/A BRADLEY MECHANICAL SERVICES; ELASTOCHEM COMPANY SPECIALTY, INC.; DOES 1–100, inclusive, 17 Case No. 2:13-cv-639-ODW(Ex) ORDER GRANTING IN PART AND DENYING IN PART DEFENDANTS’ MOTION TO DISMISS [17] Defendants. 18 I. 19 INTRODUCTION 20 Plaintiff Central Coast Pipe Lining, Inc., BG Arnold Services T/A Bradley 21 Mechanical Services (“BMS”), Pipe Shield USA, Inc., and Pipe Shield Services, Ltd. 22 entered into a Settlement Agreement on January 18, 2012, severing their business 23 relationship. 24 business from Elastochem, the manufacturer of the epoxy formerly sold to Central 25 Coast by Pipe Shield USA. Since Elastochem does not sell directly to consumers, it 26 declined to sell epoxy to Central Coast except for Plaintiff’s personal use. Armed 27 with this refusal, Central Coast alleges that Defendants breached the Settlement 28 Agreement and conspired with each other to cut off Plaintiff’s epoxy access. After Central Coast then attempted to purchase epoxy necessary for its Dockets.Justia.com 1 considering Central Coast’s seven claims, the Court GRANTS IN PART and 2 DENIES IN PART Defendants’ Motion to Dismiss.1 II. 3 FACTUAL BACKGROUND Central Coast is a California corporation with its principal place of business in 4 5 San Luis Obispo County, California. 6 Central Coast engages in the “blow through epoxy lining” business and sells supply 7 agreements for implementation of epoxy-lining products. (Id. ¶ 5.) Pipe Shield USA is incorporated and has its principal place of business in 8 9 (First Amended Complaint (“FAC”) ¶ 2.) Connecticut. (Id. ¶ 3.) Pipe Shield Services and BMS are Canadian companies. (Id.) 10 Between January 1, 2010, and January 18, 2012, Pipe Shield USA, Pipe Shield 11 Services, and BMS (collectively, the “Pipe Shield Defendants”2) were Central Coast’s 12 sole suppliers of AN 500, a specialized type of epoxy. (Id. ¶ 6.) But on January 18, 13 2012, Central Coast and the Pipe Shield Defendants entered into a Settlement 14 Agreement. (Id. ¶ 8, Ex. 1.) Under this agreement, Pipe Shield USA and Central 15 Coast agreed to terminate Plaintiff’s licensing agreement, which had previously given 16 Central Coast certain rights to Pipe Shield’s products in California. (Id. Ex. 1.) Pipe 17 Shield USA agreed in exchange to refund $70,000 of the $100,000 licensing fee 18 Central Coast had previously paid. (Id.) 19 Under paragraph 4 of the Settlement Agreement, all parties also agreed “that 20 each [would] for itself and/or directly or indirectly through any other party, refrain 21 from interfering with, hindering or by any means impeding the business operations 22 and/or expansion of any other Party.” (Id.) But the parties were allowed to compete 23 with each other in a “commercially reasonable manner.” (Id.) 24 Elastochem manufactures the AN 500 epoxy and the allegedly identical AG 310 25 epoxy, which Central Coast attempted to purchase directly from Elastochem instead of 26 27 28 1 After carefully considering the papers filed with respect to this Motion, the Court deems the matter appropriate for decision without oral argument. Fed. R. Civ. P. 78; L.R. 7-15. 2 Central Coast refers to all three of these entities as “Pipe Shield Defendants,” so the Court does too. 2 (Id. ¶ 11(a).3) 1 through Pipe Shield USA. Central Coast’s President Stan Rutiz 2 emailed Elastochem three times, inquiring whether he could purchase the AG 310 3 epoxy directly from Elastochem. 4 declined, informing Rutiz that he had to purchase the epoxy through BMS. (Id. 5 Ex. 3.) But Elastochem did offer to sell the epoxy to Central Coast for its personal, 6 rather than commercial, use. (Id. ¶ 11(a)(i), (b).) On February 29, 2012, Elastochem ultimately 7 Despite Elastochem’s response, Central Coast alleges that Elastochem offered 8 AG 310 for sale on the Internet to the general public for $135 a gallon and that Central 9 Coast was the only prospective purchaser denied the ability to purchase AG 310. (Id. 10 ¶ 11(a)(ii)–(iv).) Central Coast argues that it was unable to obtain the epoxy because 11 Defendants conspired to obstruct its access to AG 310. (Id. ¶ 11(a).) Plaintiff 12 contends that it lost some $250,000 per year in anticipated profits due to this alleged 13 conspiracy. (Id. ¶ 11-2.) Central Coast maintains that it could have sold at least 1,500 14 gallons of AG 310 per year at over $300 per gallon. (Id.) 15 On December 17, 2012, Central Coast filed a Complaint against Defendants in 16 California state court. BMS and Elastochem then removed the action to this Court. 17 On February 5, 2013, Defendants filed their first motion to dismiss. (ECF No. 11.) 18 Central Coast failed to oppose the motion, so the Court granted it. (ECF No. 12.) 19 After Central Coast filed its seven-claim First Amended Complaint, Defendants again 20 moved for dismissal on March 22, 2013. (ECF No. 17.) Plaintiff timely opposed. 21 (ECF No. 18.) That Motion is now before the Court for decision. III. 22 LEGAL STANDARD 23 Dismissal under Rule 12(b)(6) can be based on “the lack of a cognizable legal 24 theory” or “the absence of sufficient facts alleged under a cognizable legal theory.” 25 Balistreri v. Pacifica Police Dep’t, 901 F.2d 696, 699 (9th Cir. 1990). A complaint 26 need only satisfy the minimal notice pleading requirements of Rule 8(a)(2)—a short 27 28 3 Central Coast includes two paragraphs numbered “11” in its First Amended Complaint. For clarity, the Court will refer to the second paragraph 11 as “¶ 11-2.” 3 1 and plain statement—to survive a motion to dismiss for failure to state a claim under 2 Rule 12(b)(6). Porter v. Jones, 319 F.3d 483, 494 (9th Cir. 2003); Fed. R. Civ. P. 3 8(a)(2). For a complaint to sufficiently state a claim, its “[f]actual allegations must be 4 enough to raise a right to relief above the speculative level.” Bell Atl. Corp. v. 5 Twombly, 550 U.S. 544, 555 (2007). While specific facts are not necessary so long as 6 the complaint gives the defendant fair notice of the claim and the grounds upon which 7 the claim rests, a complaint must nevertheless “contain sufficient factual matter, 8 accepted as true, to state a claim to relief that is plausible on its face.” Ashcroft v. 9 Iqbal, 556 U.S. 662, 678 (2009). 10 Iqbal’s plausibility standard “asks for more than a sheer possibility that a 11 defendant has acted unlawfully,” but does not go so far as to impose a “probability 12 requirement.” Id. Rule 8 demands more than a complaint that is merely consistent 13 with a defendant’s liability—labels and conclusions, or formulaic recitals of the 14 elements of a cause of action do not suffice. Id. Instead, the complaint must allege 15 sufficient underlying facts to provide fair notice and enable the defendant to defend 16 itself effectively. 17 determination whether a complaint satisfies the plausibility standard is a “context- 18 specific task that requires the reviewing court to draw on its judicial experience and 19 common sense.” Iqbal, 556 U.S. at 679. Starr v. Baca, 652 F.3d 1202, 1216 (9th Cir. 2011). The 20 When considering a Rule 12(b)(6) motion, a court is generally limited to the 21 pleadings and must construe “[a]ll factual allegations set forth in the complaint . . . as 22 true and . . . in the light most favorable to [the plaintiff].” Lee v. City of L.A., 250 F.3d 23 668, 688 (9th Cir. 2001). Conclusory allegations, unwarranted deductions of fact, and 24 unreasonable inferences need not be blindly accepted as true by the court. Sprewell v. 25 Golden State Warriors, 266 F.3d 979, 988 (9th Cir. 2001). Yet a complaint should be 26 dismissed only if “it appears beyond doubt that the plaintiff can prove no set of facts” 27 supporting plaintiff’s claim for relief. Morley v. Walker, 175 F.3d 756, 759 (9th Cir. 28 1999). 4 1 As a general rule, leave to amend a complaint that has been dismissed should be 2 freely granted. Fed. R. Civ. P. 15(a). But leave to amend may be denied when “the 3 court determines that the allegation of other facts consistent with the challenged 4 pleading could not possibly cure the deficiency.” Schreiber Distrib. Co. v. Serv-Well 5 Furniture Co., 806 F.2d 1393, 1401 (9th Cir.1986); see Lopez v. Smith, 203 F.3d 6 1122, 1127 (9th Cir. 2000). IV. 7 DISCUSSION 8 In its First Amended Complaint, Central Coast alleges that the Pipe Shield 9 Defendants breached the noninterference provision of the Settlement Agreement by 10 conspiring with and persuading Elastochem not to sell the AG 310 epoxy to Central 11 Coast. Plaintiff contends that Elastochem offered the epoxy for sale to the general 12 public on the Internet, so Elastochem’s refusal to sell the epoxy to Central Coast 13 constitutes an anticompetitive and unfair business practice. 14 Defendants disagree, arguing that the Settlement Agreement imposed no 15 affirmative obligations on them to provide Central Coast with epoxy. They also 16 contend that if any party breached the agreement it was Central Coast, as Plaintiff 17 attempted to circumvent BMS’s exclusive-epoxy-distribution right in California by 18 attempting to purchase AG 310 directly from Elastochem, the manufacturer. The 19 Court considers the pleading adequacy of each claim in turn. 20 A. Breach of contract 21 Under California law, the essential elements of a breach-of-contract claim are 22 “(1) the contract, (2) plaintiff’s performance or excuse for nonperformance, 23 (3) defendant’s breach, and (4) the resulting damages to plaintiff.” Reichert v. Gen. 24 Ins. Co. of Am., 68 Cal. 2d 822, 830 (1968) (in bank). 25 Central Coast alleges that Defendants breached the Settlement Agreement’s 26 noninterference clause by conspiring to deprive Central Coast of the ability to 27 purchase AG 310, which is allegedly the same product as the epoxy Plaintiff formerly 28 purchased from Pipe Shield USA. Central Coast contends that Defendants understood 5 1 how vital this epoxy was to Plaintiff’s business, yet BMS allegedly told Elastochem 2 not to sell to Central Coast. Plaintiff also asserts that it performed all of its obligations 3 under the contract and that there were no valid reasons for Defendants not to perform. Defendants disagree, arguing that Central Coast’s breach-of-contract claim 4 5 doesn’t hold water. They contend that the agreement imposed no affirmative 6 obligations on them to provide Central Coast with any epoxy; indeed, the whole point 7 of the agreement was to sever ties between Central Coast and the Pipe Shield 8 Defendants. 9 because it sidestepped BMS by trying to purchase epoxy directly from Elastochem. Defendants further assert that Central Coast is the breaching party 10 While Central Coast’s breach allegations are tenuous, the Court must accept 11 them at this stage as true. Essentially the case comes down to the noninterference 12 provision’s interpretation, that is, what the parties meant when they agreed that each 13 party would “refrain from interfering with, hindering or by any means impeding the 14 business operations and/or expansion of any other Party.” Certainly if Central Coast 15 could not obtain any epoxy, it could not grow as a business—thus suffering lost-sales 16 damages. Though Elastochem was not a party to the agreement, if the Pipe Shield 17 Defendants persuaded Elastochem not to sell to Central Coast, that conspiracy could 18 rise to the level of interference—and thus breach. The Court therefore finds that Central Coast sufficiently stated a breach-of- 19 20 contract claim and DENIES Defendant’s Motion on this ground. 21 B. Fraud 22 The Federal Rules of Civil Procedure establish a higher water mark for pleading 23 fraud. Rule 9(b) requires a plaintiff to “state with particularity the circumstances 24 constituting fraud.” 25 plaintiff may not merely lump the defendants together; Rule 9(b) requires plaintiffs to 26 “inform each defendant separately of the allegations surrounding his alleged 27 participation in the fraud.” Swartz v. KPMG LLP, 476 F.3d 756, 764–65 (9th Cir. 28 2007). When a plaintiff alleges fraud by multiple defendants, the 6 1 Central Coast alleges that when the Pipe Shield Defendants entered into the 2 Settlement Agreement they did not really intend to perform their promises not to 3 hinder Plaintiff’s business. Central Coast contends that there is a “strong inference” 4 of fraud because Defendants allegedly conspired to thwart Plaintiff’s epoxy supply 5 within one year of executing the agreement. 6 Defendants respond that Central Coast’s fraud allegations are “patently 7 conclusory” and that Plaintiff fails to differentiate between the different Defendants 8 and their respective participation in the alleged fraud. The Court agrees. 9 Central Coast had three chances between its original 10 Complaint, First Amended Complaint, and Opposition to meet its heightened pleading 11 burden under Rule 9(b). Yet Plaintiff sticks to its watery group-fraud allegations, 12 conclusorily comingling all Defendants together. 13 inference” is really nothing more than fallacious post hoc reasoning—that Defendants 14 must not have intended to perform their promises simply because Plaintiff alleges 15 some breach occurred after the parties signed the agreement. Defendants are not 16 apprised of specifically how they allegedly defrauded Central Coast. 17 Plaintiff’s claim sounds more in contract than it does in tort. And Central Coast’s “strong Rather, The Court therefore GRANTS Defendants’ Motion with respect to Central 18 19 Coast’s fraud claim. 20 C. Intentional-interference claims 21 California law prohibits third parties from intentionally interfering with any 22 contract. Pac. Gas & Elec. Co. v. Bear Stearns & Co., 50 Cal. 3d 1118, 1126 (1990). 23 The elements of an intentional-interference claim are “(1) a valid contract between 24 plaintiff and a third party; (2) defendant’s knowledge of this contract; (3) defendant’s 25 intentional acts designed to induce a breach or disruption of the contractual 26 relationship; (4) actual breach or disruption of the contractual relationship; and 27 (5) resulting damage.” Id. 28 /// 7 1 The elements for intentional interference with prospective economic advantage 2 are essentially the same, just substituting an economic relationship with a contract. 3 Westside Ctr. Assocs. v. Safeway Stores 23, Inc., 42 Cal. App. 4th 507, 521–22 4 (1996). But in the latter type of claim, the interference must be “independently 5 wrongful,” that is, it must be “proscribed by some constitutional, statutory, regulatory, 6 common law, or other determinable legal standard.” Edwards v. Arthur Andersen 7 LLP, 44 Cal. 4th 937, 944 (2008). 8 Central Coast alleges that it “had contracts and/or business relationships and/or 9 prospective business advantage and relationship with various customers . . . many of 10 which customers were known to the plaintiff.” (FAC ¶ 22.) Plaintiff broadly 11 identifies its class of customers as those which would not otherwise purchase AG 310 12 from Elastochem on the Internet. 13 Defendants contend that if Central Coast did not know all its customers, then 14 there is no way Defendants knew them either. And since knowledge is an essential 15 element of interference claims, Central Coast’s third claim fails. 16 Defendants’ point is well taken. In its third claim, Central Coast simply alleges 17 elements without plausibly demonstrating how its allegations fit the interference 18 claims. It is also rather odd—and fatal to Central Coast’s claim—that Plaintiff does 19 not allege one single specific contract or business relationship Central Coast either had 20 or that was interrupted by the Defendants’ alleged actions. See Susilo v. Wells Fargo 21 Bank, N.A., 796 F. Supp. 2d 1177, 1188 (C.D. Cal. 2011) (requiring the terms of the 22 contracts in question to be set out in the complaint). The Court accordingly GRANTS Defendants’ Motion on the third claim. 23 24 D. Cartwright Act 25 To allege a Cartwright Act violation, a plaintiff must establish “(1) the 26 formation and operation of the conspiracy, (2) the wrongful act or acts done pursuant 27 thereto, and (3) the damage resulting from such act or acts.” Chavez v. Whirlpool 28 Corp., 93 Cal. App. 4th 363, 373 (2001). But as the United States Supreme Court 8 1 noted, a manufacturer “generally has a right to deal, or refuse to deal, with whomever 2 it likes, as long as it does so independently.” Monsanto Co. v. Spray-Rite Serv. Corp., 3 465 U.S. 752, 761 (1984) (interpreting the Sherman Act); see also Marin Cnty. Bd. of 4 Realtors, Inc. v. Palsson, 16 Cal. 3d 920, 925 (1976) (“[F]ederal cases interpreting the 5 Sherman Act are applicable to problems arising under the Cartwright Act.”). 6 Central Coast contends that Defendants’ alleged conduct constituted a “scheme 7 or design” to restrain trade. Despite Elastochem’s alleged representation that it would 8 sell epoxy to anyone, Elastochem refused to sell to Central Coast, a member of the 9 general public. Defendants allegedly recognized that Central Coast was a substantial 10 enough competitor that it posed a major threat to the Pipe Shield Defendants, so they 11 conspired to “destroy plaintiff’s ability to obtain product,” thereby injuring Central 12 Coast’s business. 13 Defendants disagree, arguing that Elastochem simply informed Central Coast 14 that any epoxy sales had to go through BMS, the exclusive California distributor. 15 Additionally, Elastochem did not completely refuse to sell epoxy to Central Coast, as 16 Elastochem offered to sell Plaintiff epoxy for its personal use. 17 Elastochem could refuse to sell epoxy to anyone it wanted without violating 18 antitrust laws, especially considering that Elastochem is a manufacturer and not a 19 distributor. 20 anticompetitive trust but rather the simple reality of the parties’ severed business 21 relationship. Further undergirding this conclusion is the fact that Elastochem offered 22 to sell Central Coast whatever epoxy it needed for its personal use—hardly the mark 23 of a conspiratorial trust. Any refusal by Defendants to sell Plaintiff epoxy was not an Since Central Coast has not stated a Cartwright Act claim, the Court GRANTS 24 25 Defendants’ Motion on that ground. 26 E. Conspiracy and aiding and abetting 27 Central Coast asserts that Defendants conspired with and aided and abetted each 28 other to carry out “fraudulent, illegal, oppressive and tortious conduct, acts, practices 9 1 and schemes.” Central Coast argues that a conspiracy can be inferred from all of its 2 other allegations in the First Amended Complaint. 3 But Defendants correctly point out that Central Coast’s sixth claim states only 4 bare conclusions devoid of any factual support. Central Coast does not include one 5 single fact in its conspiracy claim to demonstrate how Defendants allegedly conspired 6 with and aided and abetted each other in carrying out any illegal activities. Since 7 Defendants are simply left to guess at what Central Coast means by its leaky 8 allegations, the Court GRANTS Defendants’ Motion on Central Coast’s sixth claim. 9 F. Negligence 10 In its last claim, Central Coast tersely alleges that the “actions of the defendants 11 were done negligently.” As Defendants argue, Central Coast does not allege any legal 12 duty of care owed by Defendants to Central Coast or how they allegedly breached that 13 duty. And again, Central Coast weaves no facts into its threadbare allegations, leaving 14 but a thin veil over what really is a breach-of-contract claim dressed in different 15 clothing. The Court thus GRANTS Defendants’ Motion on this claim. 16 G. Unfair Competition Law 17 A breach-of-contract claim can form the basis of an unfair-competition law 18 claim—but only if the plaintiff alleges conduct that is unlawful, unfair, or fraudulent. 19 Puentes v. Wells Fargo Home Mortg., Inc., 160 Cal. App. 4th 638, 645 (2008). 20 Conduct is “unfair” when it “threatens an incipient violation of an antitrust law, or 21 violates the policy or spirit of one of those laws because its effects are comparable to 22 or the same as a violation of the law, or otherwise significantly threatens or harms 23 competition.” Cel-Tech Commc’ns, Inc. v. L.A. Cellular Tel. Co., 20 Cal. 4th 163, 24 187 (1999). 25 As discussed above, the Court finds that Central Coast failed to state any claim 26 other than a breach-of-contract claim. Although Central Coast alleges some facts 27 showing questionable behavior, those facts do not suffice to support a claim under 28 California’s unfair-competition law. Without pleading additional facts, the allegations 10 1 in the First Amended Complaint demonstrate nothing more than the harsh reality of 2 competition. The Court thus GRANTS Defendants’ Motion on this claim. V. 3 CONCLUSION 4 In summary, Defendants’ Motion is DENIED with respect to Central Coast’s 5 first claim and GRANTED as to Plaintiff’s second through seventh claims. Since 6 Central Coast had several attempts to strengthen its allegations but continually failed, 7 the second through seventh claims are DISMISSED WITH PREJUDICE. 8 Defendants shall file an answer within 14 days of this order. 9 IT IS SO ORDERED. 10 11 April 19, 2013 12 13 14 ____________________________________ OTIS D. WRIGHT, II UNITED STATES DISTRICT JUDGE 15 16 17 18 19 20 21 22 23 24 25 26 27 28 11

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.