ABC Sand and Rock Company Incorporated v. Maricopa, County of et al, No. 2:2016cv01129 - Document 58 (D. Ariz. 2016)

Court Description: ORDER denying 2 Plaintiff ABC's Motion for aTemporary Restraining Order with Notice and Preliminary Injunction. IT IS FURTHER ORDERED granting BoHR Defendants' Motion to Dismiss (Doc. 25 ) and the District Defendants' Motion to Dismiss (Doc. 37 ). All other pending motions are denied as moot. The Clerk shall enter judgment accordingly and close this matter. Signed by Judge John J Tuchi on 8/29/16.(DXD)

Download PDF
ABC Sand and Rock Company Incorporated v. Maricopa, County of et al 1 WO Doc. 58 NOT FOR PUBLICATION 2 3 4 5 6 IN THE UNITED STATES DISTRICT COURT 7 FOR THE DISTRICT OF ARIZONA 8 9 ABC Sand and Rock Company Incorporated, Plaintiff, 10 11 ORDER v. 12 No. CV-16-01129-PHX-JJT Maricopa, County of, et al., 13 Defendants. 14 15 Plaintiff ABC Sand & Rock Co., Inc. (“ABC”) filed a Motion for a Temporary 16 Restraining Order with Notice and Preliminary Injunction (Doc. 2, Prelim. Inj. Mot.) 17 against Defendants in this matter. Defendants are the County of Maricopa, the Maricopa 18 County Flood Control District (the “District”), and individual Defendants and their 19 spouses. The Board of Hearing Review (“BoHR”) is an entity created by Arizona statute 20 to review enforcement orders that the District’s chief engineer issues. ABC has named as 21 Defendants individual former and present members of the BoHR and their spouses, 22 which the Court refers to collectively as “BoHR Defendants.”1 The remaining individual 23 24 25 26 27 28 1 The BoHR Defendants include the following Board members and their spouses: Robert Dewayne Justice and Jane Doe Justice, Melvin Martin and Jane Doe Martin, Hemant Patel and Jane Doe Patel, Scott Ward and Jane Doe Ward, Wylie Bearup and Jane Doe Bearup, Richard Schaner and Jane Doe Schaner, Gregg Monger and Jane Doe Monger, Robert Larchick and Jane Doe Larchick, and Ray Dovalina and Jane Doe Dovalina. Dockets.Justia.com 1 Defendants and their spouses2 were or are employees, officers, or agents of the District 2 during the relevant period. Because these individuals and their spouses, Maricopa 3 County, and the District are jointly represented, the Court refers to these Defendants 4 collectively as the “District Defendants.” 5 The BoHR Defendants filed a Response to ABC’s Motion for a Temporary 6 Restraining Order with Notice and Preliminary Injunction (Doc. 9, BoHR Defs.’ Resp.), 7 as did the District Defendants (Doc. 10, District Defs.’ Resp.). Also at issue in this case 8 are the following Motions: the BoHR Defendants’ Motion to Dismiss (Doc. 25, BoHR 9 Defs.’ MTD), to which ABC filed a Response (Doc. 27, Pl.’s Resp. to BoHR Defs.’ 10 MTD) and the BoHR Defendants filed a Reply (Doc. 29, BoHR Defs.’ Reply); and the 11 District Defendants’ Motion to Dismiss (Doc. 37, District Defs.’ MTD), to which ABC 12 filed a Response (Doc. 57, Pl.’s Resp. to District Defs.’ MTD). The Court did not await 13 the District Defendants’ Reply for reasons that follow. 14 On April 21, 2016, the Court held a hearing, at which it denied ABC’s request for 15 a temporary restraining order. (Doc. 11.) On July 21 and 22, 2016, the Court held a 16 Preliminary Injunction hearing and took the matter under review. (Docs. 42, 44.) 17 I. BACKGROUND 18 A. 19 ABC is a sand and gravel mining operation along the Agua Fria River near the 20 Phoenix metropolitan area that has been in operation since 1985. The District is 21 responsible for operating and maintaining flood control works and storm drainage 22 facilities. It may issue permits for operation in the floodplain area as well as adopt and 23 enforce civil penalties for violations of its regulations. The District regulates and issues 24 permits to mining operations like ABC as part of its floodplain management duties. Factual Background 25 26 2 27 28 The other individual Defendants and their spouses include: Timothy Phillips and Jane Doe Phillips, William Wiley and Jane Doe Wiley, Jack Guzman and Jane Doe Guzman, Mike Jones and Jane Doe Jones, Ed Raleigh and Jane Doe Raleigh, and Anthony Beuché and Jane Doe Beuché. -2- 1 This case arises from a protracted on-going dispute between ABC and the District 2 regarding ABC’s permission to mine in the floodplain. ABC alleges the issues began 3 around February 2011, when the owner of ABC, David Waltemath, sent a letter to the 4 District in which he voiced his concerns about the District’s proposed new regulations. 5 (See Pl.’s Prelim. Inj. Hr’g Ex. 9.) In his letter, which ABC characterizes as “politically 6 charged,” Mr. Waltemath laments the “crushing tide of debilitating regulations 7 accompanied by the constant barrage of costly new requirements, staggering increases in 8 fees, devastating assessments and a firestorm of crippling restrictions” that “has created 9 an insurmountable nightmare that has finally eliminated the opportunity to move 10 forward.” (Pl.’s Prelim. Inj. Hr’g Ex. 9 at 1.) Mr. Waltemath continued, “[t]herefore, the 11 only action required for the [District] at this time is a simple summary approval, 12 renewing [ABC’s] current permit.” (See Pl.’s Prelim. Inj. Hr’g Ex. 9 at 1.) 13 ABC’s then-current mining permit was set to expire around the same time in 2011. 14 ABC argues that pursuant to the District’s historical practices and according to the then- 15 current Floodplain Regulations for Maricopa County (the “Regulations”),3, 4 its mining 16 permit should have been deemed renewed when it paid the appropriate fees. Instead, the 17 District requested additional information from ABC, and on May 31, 2011, issued a 18 Notice of Violation—Cease and Desist Order (“NOV”)—an enforcement violation 19 against ABC that stated ABC was engaging in activity with an expired floodplain use 20 permit. (See Pl.’s Prelim. Inj. Hr’g Ex. 15.) ABC contends that these actions were the 21 beginning of the District’s retaliation against ABC in response to ABC’s vocalization of 22 its political views. 23 3 24 25 26 27 28 See Floodplain Regulations for Maricopa County §§ 501–03 (governing the process for obtaining an initial permit); §§ 1101–03 (governing enforcement procedures for violations of an existing permit), Flood Control District of Maricopa County (2006). (Pl.’s Prelim. Inj. Hr’g Ex. 8.) 4 The Court takes judicial notice of the BoHR Orders, state court Orders, Floodplain Regulations for Maricopa County, and other court filings attached to the parties’ filings and provided as exhibits at the Preliminary Injunction Hearing because they are matters of public record. See Lee v. City of Los Angeles, 250 F.3d 668, 689 (9th Cir. 2001); U.S. ex rel. Robinson Rancheria Citizens Council v. Borneo, Inc., 971 F.2d 244, 248 (9th Cir. 1992). -3- 1 Since then, ABC and the District have engaged in a dispute both in court and out 2 of court as to whether ABC is entitled to continue its mining operations. ABC states that 3 during the course of its interactions with the District, it believed it was operating under a 4 valid 2011 to 2016 permit, which the District denies. ABC argues that it has continually 5 attempted to comply with the District’s requirements, but the District constantly changes 6 the conditions that ABC must meet to obtain a permit. In response, the District contends 7 ABC has not attempted to comply with permit requirements in good faith and it would be 8 unsound to allow ABC to mine where requirements, including safety requirements, are 9 unmet, notwithstanding that ABC has in fact continued to mine for the entire time from 10 2011 to the present day. 11 B. 12 After the District issued the NOV in May 2011, ABC requested a hearing, which 13 was held in September 2011 before Hearing Officer Harold J. Merkow. On October 11, 14 2011, Officer Merkow issued his Report and Recommendation to the District’s Chief 15 Engineer, Timothy Phillips. On November 16, 2011, Chief Engineer Phillips issued a 16 Final Decision and Order in which he stated ABC was required to obtain a floodplain use 17 permit and pay a fine of $1,000 per day from the date of the May 2011 NOV until the 18 violation is resolved and the fine is paid in full. On December 1, 2011, ABC requested 19 review of the Chief Engineer’s Order and a hearing before the BoHR. The 2011 NOV Enforcement Violation Case 20 On January 25, 2012, the BoHR met with its then-attorney, Dean Wolcott, and 21 Chief Engineer Phillips. During this meeting, remarks were made that ABC believes 22 suggest the BoHR and the other individuals at the meeting were trying to avoid the issues 23 ABC had raised and the burden ABC had become to them. ABC characterizes this 24 meeting as an “ex parte” hearing. While Defendants concede that some comments made 25 were inappropriate, they contend the meeting was not in bad faith and the BoHR was 26 trying to learn about the hearing process because it was the first time it had held such a 27 hearing. 28 -4- 1 The BoHR held a hearing on March 28, 2012, and on June 27, 2012, it issued its 2 Order in favor of ABC and reversed the Order of the Chief Engineer. On July 31, 2012, 3 the District appealed the BoHR’s Order to the Maricopa County Superior Court, and in 4 May 2013, the Superior Court remanded the matter back to the BoHR with instructions to 5 provide findings of fact and conclusions of law. ABC appealed that decision and the 6 Arizona Court of Appeals affirmed in July 2014, thus remanding the case back to the 7 BoHR. On January 28, 2015, the BoHR issued its Final Decision and Order on Remand. 8 It found that the submission of application fees alone does not constitute a sufficient 9 application and thus, no effective permit was currently in place. In other words, on 10 remand, the BoHR upheld the Chief Engineer’s decision that ABC was required to obtain 11 and maintain a floodplain use permit and pay the appropriate fees to do so. It also found, 12 however, that the Chief Engineer’s decision to assess a fine of $1,000 per day that ABC 13 operated without a permit was arbitrary. 14 On March 4, 2015, ABC appealed the BoHR’s second Order to the Maricopa 15 County Superior Court. The Superior Court, on March 18, 2016, issued a decision 16 slightly modifying the wording of the BoHR’s Order, but otherwise affirming. On April 17 22, 2016, ABC appealed the Superior Court’s decision to the Arizona Court of Appeals, 18 and the appeal is pending. 19 C. 20 On December 18, 2012, ABC filed a state court action against Maricopa County, 21 the District, and individual Defendants and their spouses affiliated with the District.5 22 Defendants removed the case to this Court on January 9, 2013, and the case was assigned 23 to District Court Judge Wake. On November 18, 2013, Judge Wake dismissed the case 24 because he found the claims were not ripe, and the Ninth Circuit Court of Appeals 25 affirmed with regard to ABC’s federal claims. See ABC Sand & Rock Co. v. Maricopa The Parties’ 2013 Federal Court Case 26 5 27 28 These individuals include: Timothy Phillips and Jane Doe Phillips, Jack Guzman and Jane Doe Guzman, Mike Jones and Jane Doe Jones, Ed Raleigh and Jane Doe Raleigh, Dewayne Justice and Jane Doe Justice, Melvin Martin and Jane Doe Martin, Hemant Patel and Jane Doe Patel, Scott Ward and Jane Doe Ward, Wylie Bearup and Jane Doe Bearup, and Jane and John Doe county employees. -5- 1 Cty., No. CV-13-00058-PHX-NVW, 2013 WL 6059296, at *3–5 (D. Ariz. Nov. 18, 2 2013), aff’d in part as modified sub nom. ABC Sand & Rock Co. Inc. v. Cty. of Maricopa, 3 627 F. App’x 626 (9th Cir. 2015). 4 D. 5 On May 8, 2015, the District issued a second NOV against ABC. On March 7, 6 2016, after a hearing was held on the second NOV before Hearing Officer Merkow, 7 Officer Merkow issued a recommended decision that Chief Engineer William Wiley 8 enter an order directing, in part, that ABC immediately obtain an approved permit for its 9 mining operations and cease and desist its operations until it obtains such permit. On 10 March 21, 2016, Chief Engineer Wiley issued a Final Decision and Order requiring ABC 11 to cease and desist mining operations in the floodplain of the Agua Fria River and to 12 comply with relevant regulations by obtaining a floodplain use permit based upon a plan 13 showing past and proposed operations within the floodplain of the Agua Fria River. The 14 Order also required that ABC pay fines for certain periods of time. The 2015 NOV Enforcement Violation Case 15 ABC requested review of the Order, and the BoHR held a hearing on June 16, 16 2016. The BoHR issued a Final Decision and Order on July 1, 2016. It found ABC had 17 continued to operate without a floodplain use permit since its last Permit for Short 18 Duration expired in July 2012 and ordered that ABC obtain a permit if it wished to 19 continue operations, thus upholding the cease and desist order. On August 4, 2016, after 20 the Court held the Preliminary Injunction hearing in this matter, ABC appealed the 21 BoHR’s Order to the Maricopa County Superior Court.6 22 In sum, there are two pending actions that were ongoing when ABC filed the case 23 in this Court—ABC’s appeal of the Superior Court’s decision to the Arizona Court of 24 Appeals arising from the 2011 NOV enforcement action and ABC’s appeal of the 25 BoHR’s decision to the Superior Court arising from the 2015 NOV enforcement action. 26 6 27 28 The Court takes judicial notice of ABC’s new action in Maricopa County Superior Court. See Lee, 250 F.3d at 689; Borneo, 971 F.2d at 248. ABC filed a Complaint on August 1, 2016, in which it alleges similar constitutional claims as those at issue in this case. -6- 1 E. 2 ABC now brings a Motion for Preliminary Injunction. ABC contends that it is 3 likely to succeed on the merits of its First Amendment retaliation, due process, equal 4 protection, and Arizona Constitution and Regulatory Bill of Rights claims. (Prelim. Inj. 5 Mot. at 5–16.) ABC initially requested that the Court enjoin the District from enforcing 6 the Chief Engineer’s March 21, 2016 Order and issue ABC a Permit of Short Duration 7 for the remainder of ABC’s permit application process. (Prelim. Inj. Mot. at 18.) In its 8 Supplemental Briefing and at the Preliminary Injunction Hearing, ABC amended its 9 requested preliminary injunction relief. It asked the Court to issue an injunction requiring 10 Defendants to give ABC 45 days’ notice “prior to filing or causing to be filed any action 11 wherein the relief requested would enjoin, or have the practical effect of enjoining” ABC 12 from continuing its mining operations. (Doc. 41-1 at 2.) In the alternative, ABC requested 13 that the Court require the District to issue a Permit of Short Duration. (Doc. 41, Pl.’s 14 Supp. Br. at 1.) The Present Motions 15 The BoHR Defendants move to dismiss this case pursuant to Federal Rule of Civil 16 Procedure 12(b)(6). (BoHR Defs.’ MTD at 5.) The BoHR Defendants’ main arguments 17 are that all personal claims against BoHR members should be dismissed on absolute 18 immunity grounds and the Court should abstain on all official claims under Younger 19 abstention. (BoHR Defs.’ MTD at 5.) 20 The District Defendants also move to dismiss this case pursuant to Federal Rules 21 of Civil Procedure 12(b)(1) and (6), contending subject matter jurisdiction is lacking and 22 ABC fails to state a claim upon which relief can be granted. (District Defs.’ MTD at 2.) 23 The District Defendants argue: 1) ABC’s claims are not yet ripe; 2) ABC is barred by res 24 judicata; 3) the Court lacks jurisdiction under the Rooker-Feldman doctrine; 4) ABC’s 25 claim for injunctive relief is barred; and 5) the Court should abstain under the Younger 26 doctrine. (See District Defs.’ MTD at 10–17.) 27 Before reaching the underlying merits of the parties’ Motions, the Court must 28 inquire into its subject matter jurisdiction and dismiss a case when jurisdiction is lacking. -7- 1 See Valdez v. Allstate Ins. Co., 372 F.3d 1115, 1116 (9th Cir. 2004); Fed. R. Civ. P. 2 12(h)(3). The Court finds the jurisdictional issues of ripeness and Younger abstention are 3 dispositive and thus does not consider the parties’ other arguments. 4 II. RIPENESS 5 Federal courts are limited to deciding “cases” and “controversies.” U.S. Const. art. 6 III, § 2. Two closely related components of the Article III case or controversy 7 requirement are standing and ripeness. Bova v. City of Medford, 564 F.3d 1093, 1096 (9th 8 Cir. 2009). To establish standing, “a plaintiff must have suffered an injury in fact that is 9 ‘concrete and particularized;’ that can be fairly traced to the defendant’s action; and that 10 can be redressed by a favorable decision of the court.” Id. (citing Lujan v. Defenders of 11 Wildlife, 504 U.S. 555, 560–61 (1992)). “While standing is primarily concerned with who 12 is a proper party to litigate a particular matter, ripeness addresses when litigation may 13 occur,” and prevents courts from deciding cases prematurely. Id. (internal citations 14 omitted) (emphasis in original); United States v. Lazarenko, 476 F.3d 642, 649 (9th Cir. 15 2007). When a claim is contingent upon future events that may not occur as anticipated, 16 or at all, the claim is not ripe for adjudication. Bova, 564 F.3d at 1096. This is because, 17 “if the contingent events do not occur, the plaintiff likely will not have suffered an injury 18 that is concrete and particularized enough to establish the first element of standing.” Id. 19 Underlying all of ABC’s claims and injuries is its allegation that the District 20 engaged in vindictive and retaliatory actions against it. (See Doc. 18, Am. Compl. at 3.) 21 ABC states the vindictive actions include indefensibly denying ABC’s permit renewal in 22 2011, demanding compliance with permit requirements that have no basis, selectively 23 imposing permit requirements on ABC, and continuously changing or failing to fully 24 disclose permit requirements, making it impossible for ABC to renew its permit and/or 25 obtain a new permit. (Am. Compl. at 3.) As stated, the District has taken two NOV cease 26 and desist enforcement actions against ABC in response to what the District views as 27 ABC’s noncompliance. ABC contends these actions, and the appeals processes that 28 followed, are also part of the District’s vindictive and retaliatory acts against it. -8- 1 ABC has appealed the two District enforcement actions taken against it, and those 2 actions are now pending in the state courts. Because no final decision has been made as 3 to whether ABC has been mining unlawfully and without a permit, and because ABC 4 continues to engage in its mining operations, it is premature to conclude that ABC has 5 suffered a concrete and particularized injury. This is not the first time the Court has 6 arrived at this conclusion. In ABC’s 2013 federal court action, Judge Wake found that 7 because ABC had appealed the Superior Court’s Order on the 2011 NOV action, ABC’s 8 claims—nearly identical to those here—were not ripe. Judge Wake stated the claims were 9 “not fit for decision because the validity of Plaintiff’s Plant 1 permit still is being decided 10 by judicial review of the administrative proceedings.” ABC Sand & Rock Co., 2013 WL 11 6059296, at *4. Indeed, Judge Wake’s statement continues to be true. As indicated above, 12 the validity of that permit still is under judicial review before the Arizona Court of 13 Appeals. 14 The Court thus finds Judge Wake’s reasoning just as persuasive and applicable in 15 the present case because ABC is now in the midst of the appeals process for both the 16 2011 and 2015 NOV enforcement actions. The Court acknowledges that the appeal and 17 NOV enforcement action process has been extensive. ABC’s issues are still not fit for 18 decision, however, because they remain under judicial review and ABC has not yet 19 suffered a concrete and particularized injury. As Judge Wake noted, this case is unlike 20 Carpinteria Valley Farms, Ltd. v. Cty. of Santa Barbara, 344 F.3d 822, 830 (9th Cir. 21 2003), where the Ninth Circuit found plaintiff’s constitutional claims were ripe because 22 he was deprived of commercial use of his land while awaiting a final decision on the 23 relevant property permit. The court stated in Carpinteria the plaintiff would have been 24 injured by the treatment he received through the procedure he contested—retaliation for 25 exercising his First Amendment rights and restricting him from playing polo on his 26 property for nine years while waiting for a major conditional use permit. The Court finds 27 the present cause distinguishable. See id. 28 -9- 1 Here, ABC also contests the procedure it has had to undergo in its attempt to 2 renew and obtain a permit to mine. However, unlike Carpinteria, ABC has not been 3 deprived commercial use of its land and has not paid the fines the District assessed 4 against it in the NOVs. Thus, ABC has not shown that it has already suffered actual, 5 concrete and particularized injury. See id. at 830–31. ABC’s ripeness defect from its 2013 6 federal court action remains, and because the 2015 NOV enforcement action is also under 7 judicial review, it is similarly not fit for decision by this Court. Because ABC has failed 8 to meet the constitutional component of ripeness, the Court may not exercise jurisdiction 9 and must dismiss ABC’s claims. See Wolfson v. Brammer, 616 F.3d 1045, 1058 (9th Cir. 10 2010). Although the Court must dismiss ABC’s claim on this basis, because the same 11 factors that render the matter unripe—the nature of ABC’s claims and the posture of the 12 underlying state actions—also implicate Younger abstention, the Court addresses that 13 doctrine below. 14 III. YOUNGER ABSTENTION 15 Younger abstention is a jurisprudential doctrine rooted in the principles of equity, 16 comity, and federalism. See Steffel v. Thompson, 415 U.S. 452, 460–73 (1974) (stating 17 the history and purposes of the doctrine); Younger v. Harris, 401 U.S. 37, 43–49 (1971); 18 (discussing the jurisprudential background of abstention); San Jose Silicon Valley 19 Chamber of Commerce Political Action Comm. v. City of San Jose, 546 F.3d 1087, 1091– 20 92 (9th Cir. 2008); Gilbertson v. Albright, 381 F.3d 965, 970–75 (9th Cir. 2004) (en 21 banc) (following the Supreme Court’s application of the doctrine). The doctrine 22 establishes an exception to mandatory federal jurisdiction, and the Court must dismiss the 23 action under certain circumstances. Baffert v. Cal. Horse Racing Bd., 332 F.3d 613, 617 24 (9th Cir. 2003). 25 26 27 28 In civil cases . . . Younger abstention is appropriate only when the state proceedings: (1) are ongoing, (2) are quasi-criminal enforcement actions or involve a state’s interest in enforcing the orders and judgments of its courts, (3) implicate an important state interest, and (4) allow litigants to raise federal challenges. If these “threshold elements” are met, we then consider - 10 - 1 2 3 whether the federal action would have the practical effect of enjoining the state proceedings and whether an exception to Younger applies. Each element must be satisfied, and the date for determining whether Younger applies is the date the federal action is filed. 4 5 ReadyLink Healthcare, Inc. v. State Comp. Ins. Fund, 754 F.3d 754, 759 (9th Cir. 2014) 6 (internal citations and quotations omitted) (citing Sprint Commc’ns, Inc. v. Jacobs, 134 S. 7 Ct. 584, 593–94 (2013)). 8 A. 9 The first requirement for Younger abstention is met. The United States Supreme 10 Court has held that Younger abstention applies where a losing litigant has not exhausted 11 its state appellate remedies. Dubinka v. Judges of Superior Court of State of Cal. for Cty. 12 of L.A., 23 F.3d 218, 223 (9th Cir. 1994) (citing Huffman v. Pursue, Ltd., 420 U.S. 592, 13 607–11 (1975)). Here, there were ongoing state judicial proceedings stemming from the 14 2011 and 2015 NOV enforcement actions at the time ABC filed its Complaint in this 15 Court on April 19, 2016 (Doc. 1). As of that date, the Superior Court had issued a 16 decision on the 2011 action that ABC appealed three days after it filed its Complaint in 17 this case, and the parties were awaiting their June 2016 hearing in front of the BoHR on 18 the 2015 action. Thus, ABC was still pursuing its state appellate remedies and the 19 proceedings were ongoing. Ongoing State Proceedings 20 B. 21 The enforcement actions the District initiated against ABC are the type of 22 proceeding that triggers Younger abstention. “[O]nly exceptional circumstances justify a 23 federal court’s refusal to decide a case in deference to the States.” New Orleans Pub. 24 Serv., Inc. v. Council of City of New Orleans, 491 U.S. 350, 368 (1989) (“NOPSI”). 25 Those “exceptional circumstances” exist in three types of proceedings: 1) state criminal 26 prosecutions; 2) certain “civil enforcement proceedings;” and 3) “civil proceedings 27 involving certain orders . . . uniquely in furtherance of the state courts’ ability to perform 28 their judicial functions.” Sprint Commc’ns, Inc. v. Jacobs, 134 S. Ct. 584, 591 (2013). Type of Cases in Which Younger Abstention Applies - 11 - 1 The Supreme Court has applied Younger to instances of civil enforcement where 2 state proceedings are “akin to criminal prosecution” in “important respects.” Sprint, 134 3 S. Ct. at 592. As the Supreme Court described: 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Such enforcement actions are characteristically initiated to sanction the federal plaintiff, i.e., the party challenging the state action, for some wrongful act. See, e.g., [Middlesex Cty. Ethics Comm. v. Garden State Bar Ass’n, 457 U.S. 423, 433–34] (1982) (state-initiated disciplinary proceedings against lawyer for violation of state ethics rules). In cases of this genre, a state actor is routinely a party to the state proceeding and often initiates the action. See, e.g., Ohio Civil Rights Comm’n v. Dayton Christian Schools, Inc., 477 U.S. 619 (1986) (state-initiated administrative proceedings to enforce state civil rights laws); Moore v. Sims, 442 U.S. 415, 419–420 (1979) (state-initiated proceeding to gain custody of children allegedly abused by their parents); Trainor v. Hernandez, 431 U.S. 434, 444 (1977) (civil proceeding “brought by the State in its sovereign capacity” to recover welfare payments defendants had allegedly obtained by fraud); [Huffman, 420 U.S. at 598] (state-initiated proceeding to enforce obscenity laws). Investigations are commonly involved, often culminating in the filing of a formal complaint or charges. See, e.g., Dayton, 477 U.S. at 624 (noting preliminary investigation and complaint); Middlesex, 457 U.S. at 433 (same). Sprint, 134 S. Ct. at 592. In this case, a state actor, the District, initiated the enforcement actions against ABC via the issuance of the NOVs. The District did so to sanction ABC, the federal plaintiff, through the use of fines and cease and desist orders, and the District remains a party to the enforcement actions. The enforcement actions here are thus similar to those the Supreme Court has found were proper for Younger abstention. See Sprint, 134 S. Ct. at 592. Accordingly, the second Younger factor is also met. C. Important State Interests In considering the third Younger factor, the importance of the state interest “is measured by considering its significance broadly, rather than by focusing on the state’s interest in the resolution of an individual case.” Baffert, 332 F.3d at 618 (citing NOPSI, 491 U.S. at 365). The State of Arizona has a significant interest in mitigating flood - 12 - 1 hazards and accordingly, the District was created to adopt and enforce floodplain 2 regulations consistent with the Director of Arizona Department of Water Resources’s 3 adopted criteria. See Floodplain Regulations for Maricopa County § 102, Flood Control 4 District of Maricopa County (2014);7 A.R.S. §§ 48-3601–650. The Floodplain 5 Regulations for Maricopa County explain the Regulations were adopted to mitigate and 6 avoid significant flood hazards. Specifically, the Regulations provide: 7 8 9 10 11 The flood hazard areas of Maricopa County are subject to periodic inundation that may result in loss of life and property, health and safety hazards, disruption of commerce and governmental services, extraordinary public expenditures for flood protection and relief, and impairment of the tax base, all of which adversely affect the public health, safety, and general welfare. 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Floodplain Regulations for Maricopa County §§ 101(A), 103. In accordance with the District’s mandate and mission to promote safety, the Regulations set forth under what circumstances a floodplain use permit is required, which includes an entity’s extraction of sand and gravel in certain areas. See Floodplain Regulations for Maricopa County § 401. Because of the flood hazards and county land and residents at stake, Arizona has an important state interest in regulating the floodplain and mining therein. The state proceedings implicate this state interest because they determine whether ABC has met the requirements for a floodplain use permit established to promote the state’s safety interests, and whether ABC has been mining in accordance with the Regulations. In addition, “[w]hether the state proceedings are ‘judicial in nature’ or ‘quasicriminal’ also plays a role in assessing the significance of the state interest.” Baffert, 332 F.3d at 618. Here, the BoHR held adjudicatory hearings, which are quasi-judicial, and ABC’s permit was at issue, making the proceedings quasi-criminal. See id. These factors further support that the ongoing state proceedings implicate an important state interest. The Court finds the third Younger factor is met. 7 Available at: http://www.fcd.maricopa.gov/downloads/permitting/Floodplain_Reg_Book.pdf. - 13 - 1 D. 2 The fourth Younger factor requires that the state proceedings allow litigants to 3 raise federal challenges. The Supreme Court has held that even if underlying 4 administrative proceedings do not provide litigants with the opportunity to bring their 5 constitutional challenges, it is sufficient that constitutional claims may be raised in state- 6 court judicial review of the administrative proceeding. Dayton, 477 U.S. at 629 (citing 7 Middlesex, 457 U.S. at 436). Here, the Regulations provide for, and ABC has availed 8 itself of, state-court judicial review of the BoHR decisions. See Floodplain Regulations 9 for Maricopa County § 409. ABC does not cite any persuasive authority that it is barred 10 from raising its constitutional challenges in state court. The Court finds the fourth 11 Younger element is also met. Opportunity to Litigate Federal Claims 12 E. 13 The Court also considers whether any exception to Younger abstention applies. 14 The Court must examine whether the state proceeding demonstrates bad faith, 15 harassment, or some other extraordinary circumstances that would make abstention 16 inappropriate. Kenneally v. Lungren, 967 F.2d 329, 332 (9th Cir. 1992). “Bias exists 17 where a court has prejudged, or reasonably appears to have prejudged, an issue.” Id. at 18 333. The party raising bias must overcome a presumption of honesty and integrity in 19 those serving as adjudicators. Id. Bad faith typically means that a prosecution has been 20 brought without a reasonable expectation of obtaining a valid conviction. Baffert, 332 21 F.3d at 621. Exceptions to Younger Abstention 22 ABC argues that the BoHR members’ actions demonstrate bad faith, bias, and 23 disregard for ABC’s constitutional rights and thus constitute an “extraordinary 24 circumstance” preventing ABC from raising its constitutional claims. (Pl.’s Resp. to 25 BoHR Defs.’ MTD at 13.) In support of its bias argument, ABC points to statements 26 made by BoHR members in an “ex parte hearing” that occurred in January 2012 while 27 ABC’s appeal of the Chief Engineer’s Order was pending and before the BoHR hearing 28 had occurred. ABC also states that it tried to raise the issue of bias at its March 2012 - 14 - 1 hearing before the BoHR, but the BoHR refused to hear ABC’s constitutional arguments. 2 The Court also heard argument regarding bias at the Preliminary Injunction hearing and 3 reviewed the January 2012 meeting transcript. The Court is troubled by the inappropriate 4 comments made at the January 2012 “ex parte” meeting, some of which suggest some 5 Board members’ predisposition against ABC. (See Pl.’s Prelim. Inj. Hr’g Ex. 33.) The 6 Court finds, however, that when looking at the broader context of ABC’s multiple 7 hearings before the BoHR and Arizona state courts in the 2011 and 2015 NOV 8 enforcement actions, ABC has not overcome the presumption of honesty and integrity in 9 those serving as adjudicators. See Kenneally, 967 F.2d at 333. Nothing else in those 10 hearings or events surrounding those hearings shows that ABC has been subject to bias. 11 Indeed, the BoHR’s June 2012 Order that issued after the March 2012 hearing wherein 12 ABC tried to raise bias found in favor of ABC. Moreover, the recent BoHR Order 13 recognized the District’s faults and acknowledged that “the District has been at times less 14 than clear in providing specific deadlines for ABC.” (Doc. 40, Ex. A, BoHR Final 15 Decision and Order, July 1, 2016 at 9.) The BoHR set forth recommendations for 16 establishing deadlines in the future, thus acknowledging that both ABC and the District 17 were at fault for misunderstandings. (Doc. 40, Ex. A, BoHR Final Decision and Order, 18 July 1, 2016 at 9–10.) ABC also has and will be able to present its case to the Maricopa 19 County Superior Court and the Arizona Court of Appeals and has presented no evidence 20 of those adjudicators’ bias. The Court acknowledges that the comments at the January 21 2012 BoHR meeting were inappropriate and disconcerting, but it finds that in light of the 22 history of the BoHR’s and state courts’ review of ABC’s case, ABC is unable to 23 overcome the presumption of the adjudicators’ honesty and integrity. 24 As for the District’s bad faith, the District had a reasonable expectation of 25 obtaining a valid “conviction” in both the 2011 and 2015 NOV enforcement actions. See 26 Baffert, 332 F.3d at 621. The Court finds it was not clear whether ABC was permissibly 27 mining in accordance with a valid permit and the Regulations at the relevant times. The 28 Court does not advance that either the District or ABC was correct in its position when - 15 - 1 the NOV actions were initiated. Rather, the Court finds that given the degree of 2 uncertainty as to ABC’s rights, the District had some reasonable expectation that ABC 3 would be found out of compliance with the applicable Regulations. 4 F. 5 After the threshold elements are met, for Younger abstention to apply, “[t]he 6 requested [federal court] relief must seek to enjoin—or have the practical effect of 7 enjoining—ongoing state proceedings.” ReadyLink Healthcare, 754 F.3d at 758. 8 Although a “direct” interference is not a threshold requirement, there must be some 9 interference with state court proceedings for Younger to apply. AmerisourceBergen Corp. 10 11 Effect of Requested Relief v. Roden, 495 F.3d 1143, 1149 n.9 (9th Cir. 2007). In its Amended Complaint, ABC requests the following injunctive relief: 12 13 14 15 16 17 (1) Enjoin Defendants from continuing to violate ABC’s state and federal constitutional rights; (2) enjoin Defendants from further violating Arizona’s Regulatory Bill of Rights; (3) enjoin Defendants to honor the de facto permit they granted ABC in February 2015 for the duration of its current permit application process; (4) enjoin Defendants to process ABC’s current permit application in accordance with Arizona’s Regulatory Bill of Rights; and (5) enjoin the imposition of the arbitrary and capricious fine assessed on March 21, 201[6]. 18 19 (Am. Compl. at 42–43.) 20 ABC’s requested relief is inextricably intertwined with the ongoing state 21 proceedings. ABC’s federal claims are a constitutional challenge to the pending BoHR 22 and state proceedings. In Gilbertson, the Ninth Circuit held that Younger principles 23 applied to plaintiff’s § 1983 claim because the constitutional issues raised in his federal 24 complaint, including First Amendment retaliation, due process, and equal protection, “go 25 to the heart of his opposition to the Board’s action in the state proceeding, such that a 26 federal court’s decision on the merits of [plaintiff’s] claims would have the same 27 practical effect on the state proceeding as an injunction.” 381 F.3d at 979–82. Similarly, 28 ABC has raised the same constitutional claims that go to the heart of its opposition to the - 16 - 1 District’s initial action and the BoHR’s subsequent actions. The Court’s determination of 2 those claims would interfere with the state proceedings as it “would frustrate the state’s 3 interest in administering its judicial system, cast a negative light on the state court’s 4 ability to enforce constitutional principles, and put the federal court in the position of 5 prematurely or unnecessarily deciding a question of federal constitutional law.” Id. at 6 980. In addition, ABC requests that the Court enjoin Defendants from engaging in 7 unconstitutional conduct, which based on ABC’s allegations includes the NOV 8 enforcement actions and hence the pending state court proceedings. Thus, ABC’s request 9 would have the result of vacating the BoHR and state court decisions and halting the 10 pending proceedings. 11 ABC also requests that the Court require Defendants to honor and process its 12 mining permits and enjoin the imposition of fines, which are the precise issues of the 13 ongoing state proceedings. ABC’s requested relief as to fines, some of which the BoHR 14 has upheld, would conflict with the BoHR’s Order and prevent the Maricopa County 15 Superior Court from affirming and enforcing the Order. The Ninth Circuit has held that 16 where a requested injunction would prohibit a commission or other governmental entity 17 from imposing a fine against plaintiffs, the relief sought by plaintiffs would interfere and 18 effectively enjoin ongoing state proceedings, thus meeting the final Younger abstention 19 requirement. See City of San Jose, 546 F.3d at 1095–96 (holding plaintiffs’ requested 20 relief against defendants to preclude them from enforcing a statute consequently 21 prohibited the Elections Commission from imposing fines against plaintiffs and 22 constituted the requisite interference or enjoining of state proceeding under Younger). 23 As to its permit, ABC requests that the Court require Defendants to honor their 24 February 2015 “de facto” permit and process their current permit application in 25 accordance with Arizona’s Regulatory Bill of Rights. Such a determination would 26 conflict with the BoHR’s factual determination underlying its decision to uphold fines. It 27 would also impede the state court’s review of the facts on appeal because it conflicts with 28 the BoHR’s Order. ABC’s requested relief disrupts the State’s efforts to protect its - 17 - 1 interests that underlie the Floodplain Regulations and to obtain compliance with those 2 regulations, further supporting that the requested relief would interfere with the ongoing 3 state action. See Huffman, 420 U.S. at 604–05 (“Similarly, while in this case the District 4 Court’s injunction has not directly disrupted Ohio’s criminal justice system, it has 5 disrupted that State’s efforts to protect the very interests which underlie its criminal laws 6 and to obtain compliance with precisely the standards which are embodied in its criminal 7 laws”). 8 At the Preliminary Injunction Hearing and in its Supplemental Briefing, ABC 9 amended its requested preliminary injunction relief. (Pl.’s Supp. Br. at 1.) It argued that 10 its revised preliminary injunction request for 45 days’ notice prior to the filing of any 11 action that would enjoin or have the practical effect of enjoining ABC from its mining 12 operations was so narrow that it did not enjoin or have the practical effect of enjoining 13 the state proceedings under Younger. (Pl.’s Supp. Br. at 1.) As in the cases cited, the 14 Court considers the effect of the ultimate requested federal action under Younger, not the 15 requested relief in a preliminary injunction motion. Were the Court to adopt ABC’s 16 contention that it should only look at the preliminary injunction relief sought, it might be 17 deciding the Preliminary Injunction Motion only to later find Younger abstention 18 precluded the Court from exercising jurisdiction over the action at all. The Court also 19 finds that despite ABC’s contention, its requested relief does not threaten merely a 20 “potential” for conflict with the state proceedings, but rather, for the reasons stated, is 21 completely intertwined and conflicts with the state proceedings. 22 The Court thus finds that ABC’s requested federal action would have the practical 23 effect of enjoining the ongoing state proceedings. 24 IV. CONCLUSION 25 The Court finds it does not have jurisdiction over this matter because ABC’s 26 claims are not yet ripe. The Court also determines it must abstain under Younger because 27 all of the Younger elements are met, no exceptions apply, and ABC’s requested federal 28 action would have the practical effect of enjoining the ongoing state proceedings. - 18 - 1 Because the Court has found the case is not ripe, it will dismiss all of ABC’s claims, 2 including its monetary damages claim, and not issue a stay. See Gilbertson, 381 F.3d at 3 981 (directing courts to stay, as opposed to dismiss, where monetary damages are sought 4 and Younger abstention is applied). In addition, because the Court finds it does not have 5 jurisdiction, it does not reach the other arguments in Plaintiff’s Motion for Preliminary 6 Injunction and Defendants’ Motions to Dismiss. 7 8 IT IS THEREFORE ORDERED denying Plaintiff ABC’s Motion for a Temporary Restraining Order with Notice and Preliminary Injunction (Doc. 2). 9 IT IS FURTHER ORDERED granting the BoHR Defendants’ Motion to 10 Dismiss (Doc. 25) and the District Defendants’ Motion to Dismiss (Doc. 37) on ripeness 11 and abstention grounds. All other pending motions are denied as moot. The Clerk of the 12 Court shall enter judgment accordingly and close this matter. 13 Dated this 29th day of August, 2016. 14 15 16 Honorable John J. Tuchi United States District Judge 17 18 19 20 21 22 23 24 25 26 27 28 - 19 -

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.